R. J. Berke & Co. v. J. P. Griffin, Inc.

367 A.2d 583, 116 N.H. 760, 1976 N.H. LEXIS 465
CourtSupreme Court of New Hampshire
DecidedDecember 30, 1976
Docket7242
StatusPublished
Cited by39 cases

This text of 367 A.2d 583 (R. J. Berke & Co. v. J. P. Griffin, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. J. Berke & Co. v. J. P. Griffin, Inc., 367 A.2d 583, 116 N.H. 760, 1976 N.H. LEXIS 465 (N.H. 1976).

Opinion

Per curiam.

These consolidated appeals involve contract disputes between J. P. Griffin, Inc., the general contractor and the R. J. Berke Co., a subcontractor. They arose out of the construction of a sewage treatment plant and related facilities for the town of Newmarket, New Hampshire.

The town of Newmarket and Green Engineering Affiliates, Inc., were joined as parties defendant in the cross-action of Griffin v. Berke, but those actions have been disposed of and form no part of the appeals. The two insurance companies provided bonds for the remaining principal parties.

The history of the dispute, as briefly as possible, may be summarized as follows:

On August 6, 1968, Griffin entered into a $1,047,650 general contract with the town to construct additions to the sewage treatment plant. The Aetna Insurance Company furnished bond. Green Engineering Affiliates, Inc., was designated as the engineer and authorized to act as the town’s representative in construction matters. Griffin entered into a subcontract for Berke to perform certain work for a price of $225,000. The St. Paul Fire and Marine Insurance Company furnished bond. All parties agreed that the completion time was 540 days from August 6, 1968. From the beginning, the actual construction work did not go well. The engineer had estimated that 4,100 cubic yards of ledge would need to be excavated but the actual amount encountered was approximately 12,000 cubic yards.

Numerous disputes as to the adequacy of the performance of each party’s contractual obligations arose and were compounded by personality clashes for which both were at fault. Griffin’s complaints included charges that Berke failed to adequately man the job thereby causing delays; performed sloppy work; failed to cooperate with other construction personnel in matters of scheduling; and failed to timely pay subcontractors. Berke’s complaints included charges that Griffin failed to pay for labor and materials as the job progressed; to pay for extras; to provide proper working conditions; to adequately prepare the work site; and to generally cooperate so that the work could be reasonably coordinated.

*762 Friction between the two companies reached the point where on February 13, 1970, with a substantial amount of the contract performed, Berke walked off the job. Berke returned to work on March 16, 1970, pursuant to a “letter agreement” negotiated March 12, 1970. Under this agreement, Berke was permitted to return to the site and complete the contract on the following conditions: (1) its guarantee “to provide sufficient competent personnel and all necessary materials to complete [its] portion of the treatment plant immediately”; (2) a proviso that no further funds would be paid to the company until it demonstrated that it had made all past payments owed to its subcontractor Standard Plumbing and Heating Corporation; and (3) a proviso that no further payments would be made to Berke “until completion and final acceptance by the Engineer of the project.” Troubles persisted even after Berke’s return to the job site. Griffin charged that Berke again had failed to adequately man the job and was still not timely in its payment to its subcontractors. On June 3, 1970, Berke was ordered to cease all work and to leave the premises. Griffin thereafter called in various subcontractors to complete or correct Berke’s unfinished work.

On March 11, 1970, the instant litigation was started by Berke through a bill in equity seeking payment under the bond issued to Griffin by the defendant Aetna. The petition alleged that the work was 97% completed and sought the balance due on the contract price. An amendment to the pleadings was filed on October 10, 1972, adding counts in assumpsit and quantum meruit and including a claim for “extras” and for additional unspecified damages.

Griffin filed a cross-action against Berke and its bonding company the St. Paul Fire and Marine Insurance Company. The action alleged inadequate performance by Berke and sought recovery for the damages incurred, including recovery for the penalty paid for failure to timely complete the contract.

The proceedings, heard by a Judicial Referee (Blandin, J.), were lengthy resulting in a voluminous record and many exhibits. The parties showed little inclination to reduce this complexity or to assist the trial court. The parties ignored the design of RSA 491:15 as succinctly set forth in Concord General Mutual Insurance Company v. Haynes, 110 N.H. 76, 79, 260 A.2d 99, 101 (1969), and the plaintiff filed 177 requests for findings and rulings and the defendant 993 such requests.

*763 The trial court found that both parties had materially breached their respective contracts in substantially the manner alleged in their pleadings; that the construction delays occurring prior to the time of the letter agreement were attributable to these breaches as well as to the unanticipated ledge conditions and to personality conflicts for which both parties were at fault. It concluded that “justice in this equitable proceeding requires that neither recover from the other for damage suffered prior to the letter agreement.”

The referee observed that the meaning of the letter agreement was “obscure” but construed it as an intent “to get the job done,” and not “intended to revitalize the original sub-contract... with its mass of provisions, some highly technical, contained in the hundreds of pages and integrated proposals and drawings.” He further found that Berke breached the terms of the letter agreement and that Griffin was justified in ordering it to cease all work and leave the premises. The referee thus concluded that Griffin alone was entitled to damages arising after the letter of agreement.

The court ruled that the fair market value of materials and labor, including extras furnished by Berke, was $240,562.18; credits awarded Griffin included its partial payment to Berke in the amount of $170,377.20, plus $33,299.05 admittedly due by Berke, and post letter agreement damages of $27,457.64 (including $6,000 as Berke’s share of liquidated damages for delay). The result was a net balance due Berke in the amount of $9,428.29.

Both parties have appealed from the verdict and all exceptions were reserved and transferred hy Bois, J. Berke has indicated that it does not intend to press its exception should the appeal be resolved in its favor.

Griffin’s contentions are fourfold: (1) Berke was not entitled to relief in quantum meruit; (2) Berke was not entitled to payment for the extras; (3) the referee erred in apportioning the liquidated damages for project time overruns; (4) the referee was in error in his method of determining the damages to be set off by Griffin.

I.

Griffin’s argument in contesting the recovery in quantum meruit is twofold. It argues that as a matter of law such recovery is not allowed (1) where substantial performance has not been *764 rendered and (2) where the defaulting party’s breach has been willful.

In support of its first contention, Griffin relies on Albre Marble & Tile Co. v. Goverman, 353 Mass. 546, 233 N.E.2d 533

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charles R. Estes, et al. v. P ECMC Group, Inc.
2020 DNH 159 (D. New Hampshire, 2020)
Estes v. ECMC Group, Inc.
D. New Hampshire, 2020
Axenics, Inc. v. Turner Construction Co.
62 A.3d 754 (Supreme Court of New Hampshire, 2013)
Eastern Elec. v. FERD Const., et al.
2005 DNH 164 (D. New Hampshire, 2005)
Rood v. Moore
807 A.2d 1225 (Supreme Court of New Hampshire, 2002)
Malone v. Cemetary St. Dev.
D. New Hampshire, 1995
Drucker's Case
577 A.2d 1198 (Supreme Court of New Hampshire, 1990)
Robert E. Tardiff, Inc. v. Twin Oaks Realty Trust
546 A.2d 1062 (Supreme Court of New Hampshire, 1988)
Howard v. Howard
531 A.2d 331 (Supreme Court of New Hampshire, 1987)
Parem Contracting Corp. v. Welch Construction Co.
512 A.2d 1104 (Supreme Court of New Hampshire, 1986)
V & V Corp. v. American Policyholders' Insurance
500 A.2d 695 (Supreme Court of New Hampshire, 1985)
Burgess v. Queen
470 A.2d 861 (Supreme Court of New Hampshire, 1983)
Taylor v. Davidson Rubber Co.
445 A.2d 1119 (Supreme Court of New Hampshire, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
367 A.2d 583, 116 N.H. 760, 1976 N.H. LEXIS 465, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-j-berke-co-v-j-p-griffin-inc-nh-1976.