Eastern Elec. v. FERD Const., et al.
Opinion
Eastern Elec. v . FERD Const., et a l . CV-05-303-JD 12/15/05 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
Eastern Electrical Corp.
v. Civil N o . 05-cv-303-JD Opinion N o . 2005 DNH 164 FERD Construction, Inc., and BAE Systems, Inc.
O R D E R
Eastern Electrical Corporation provided electrical work as a subcontractor during the renovation of a building owned by BAE Systems, Inc., where FERD Construction, Inc., was the general contractor. When Eastern did not receive the amount it expected in payment for its work, it brought suit, alleging a claim of breach of contract against FERD and claims of unjust enrichment and quantum meruit against FERD and BAE. BAE moves to dismiss the unjust enrichment and quantum meruit claims against i t .
Standard of Review
In considering a motion to dismiss, pursuant to Federal Rule of Civil Procedure 12(b)(6), the court accepts the facts alleged in the complaint as true and draws all reasonable inferences in favor of the plaintiff. Citibank v . Grupo Cupey, Inc., 382 F.3d 2 9 , 31 (1st Cir. 2004). The court must determine whether the complaint, construed in the proper light, “alleges facts
sufficient to make out a cognizable claim.” Carroll v . Xerox Corp., 294 F.3d 2 3 1 , 241 (1st Cir. 2002). All that is required is a short and plain statement of the claim. See Gorski v . N.H. Dep’t of Corr., 290 F.3d 466, 473 (1st Cir. 2002) (citing Swierkiewicz v . Sorema N.A., 534 U.S. 506 (2002)).
The court “must carefully balance the rule of simplified civil pleadings against our need for more than conclusory
allegations.” Aybar v . Crispin-Reyes, 118 F.3d 1 0 , 13 (1st Cir. 1997). To avoid dismissal, “the complaint should at least set forth minimal facts as to who did what to whom, when, and why . . . .” Redondo-Borges v . U.S. Dep’t of Housing & Urban Dev., 421 F.3d 1 , 9 (1st Cir. 2005) (internal quotation marks omitted). “Even within the generous confines of notice pleading, courts must continue to eschew reliance on bald assertions and unsupportable conclusions.” Id.
Background
Eastern alleges that BAE engaged FERD to act as general contractor for the renovation of its building on Canal Street in Nashua, New Hampshire. After the first electrical contractor was unable to complete the project, FERD contracted with Eastern, on a time and materials basis, to complete the electrical work. The subcontract was executed by Eastern on September 7 , 2004, and by
FERD on September 2 0 , 2004.
Eastern alleges that the contract provided a limit on the amount to be paid for its electrical work as follows: “The value of this subcontract shall not exceed $125,000 without prior written authorization.” Complaint ¶ 1 3 . According to Eastern, a handwritten note was added on September 7 , 2004, indicating that the initial scope of the electrical work was “to complete up to $125,000 remaining electrical work.” Id. ¶ 1 5 . Eastern alleges that it submitted two change orders that FERD approved which increased the limit on Eastern’s work to $275,000. Eastern contends that the changes were made because of “field directives” issued by FERD and BAE and that FERD and BAE continued to issue field directives for the remainder of the project. Eastern also alleges that it submitted daily inventories and labor time sheets to FERD that were approved and that its representatives attended
regular project meetings with representatives of FERD and BAE.
By the time it completed the electrical work in late
November of 2004, Eastern alleges it had furnished time and materials totaling $448,081.77. FERD has paid Eastern $149,301.98 and provided a retainer of $16,589.11. Eastern has demanded additional payment from FERD, but FERD has refused to make any additional payments.
Discussion
Eastern brings a claim of breach of contract against FERD and alleges separate claims of unjust enrichment and quantum meruit against BAE and FERD. BAE moves to dismiss both claims against it on the grounds that such claims are not available as a
matter of law, that Eastern failed to state claims of unjust enrichment and quantum meruit, and that a quantum meruit claim
must be based on an underlying contractual relationship. Eastern objects.
A. Availability of Equitable Remedy Restitution under theories of quantum meruit and unjust enrichment is an equitable remedy. See In re Haller, 150 N.H. 427, 430 (2003); Kowalski v . Cedars of Portsmouth Condo. Ass’n, 146 N.H. 1 3 0 , 134 (2001). Equitable remedies are not available in New Hampshire courts when the plaintiff has an adequate legal remedy. See, e.g., Concord Orthopaedics Prof. Ass’n v . Forbes, 142 N.H. 440 445-46 (1997); Fischer v . City of Dover, 131 N.H. 469, 476 (1989). Indeed, it is a basic tenet of equity jurisprudence “that courts of equity should not act . . . when the moving party has an adequate remedy at law and will not suffer irreparable injury if denied equitable relief.” Younger v . Harris, 401 U.S. 3 7 , 43-44 (1971); accord Morales v . Trans
World Airlines, Inc., 504 U.S. 3 7 4 , 381 (1992); Parsons Infrastructure & Tech. Group, Inc. v . Gilbane Bldg. Co., 2005 WL 2978901, at *1 (D.N.H. Nov. 7 , 2005); Massachusetts v . Mylan Labs., 357 F. Supp. 2d 3 1 4 , 324 (D. Mass. 2005).
Under New Hampshire law, subcontractors have a statutory
right to a lien on the materials provided and the structure where the work was done, provided that the subcontractor gives notice
in writing to the owner of the property before performing the work o r , for a more limited lien, after the work has begun. See RSA 447:5; RSA 447:6. Russell v . Woodbury, 135 N.H. 4 3 2 , 433 (1992). In addition, in this case, Eastern had a contract with FERD that covered its work on BAE’s building. Eastern has brought a breach of contract claim as part of this suit to recover the amounts it claims are owed.
Eastern explains that recovery under the mechanics’ lien statute is not available because it did not give the required
notice. Eastern argues that it will suffer irreparable injury if it is not permitted to maintain its equitable claims against BAE because it would lose $300,000. Eastern’s argument, however, does not explain why the remedy it seeks against FERD for breach of contract, seeking damages for the amounts that it alleges have not been paid, is not adequate. No irreparable injury exists if the injury is compensable in damages. See Exeter Realty Corp. v .
Buck, 104 N.H. 199, 201 (1962); see also Matrix Group Ltd., Inc. v . Rawlings Sporting Goods Co., Inc., 378 F.3d 2 9 , 33-34 (1st Cir. 2004).
Because Eastern has not explained why it does not have an adequate remedy at law in the circumstances of this case, it is
not entitled to the equitable remedy of restitution under either of its theories. See Parsons, 2005 WL 2978901. Even if that
explanation were forthcoming, however, the complaint is insufficient to state those claims.
B. Unjust Enrichment and Quantum Meruit “The doctrine of unjust enrichment is that one shall not be allowed to profit or enrich himself at the expense of another contrary to equity.” Pella Windows & Doors, Inc. v . Faraci, 133 N.H. 585, 586 (1990) (internal quotation marks omitted). A claim of quantum meruit asserts the plaintiff’s right “only to obtain what equitably belongs to him.” Blanchard v . Calderwood, 110 N.H. 2 9 , 34 (1969) (internal quotation marks omitted). The elements of a restitution claim under unjust enrichment or quantum meruit are that the defendant was unjustly enriched “either through wrongful acts or passive acceptance of a benefit
that would be unconscionable to permit the defendant to retain.”1 R. Zoppo Co., Inc. v . City of Manchester, 122 N.H. 1109, 1113 (1982).
Free access — add to your briefcase to read the full text and ask questions with AI
2005 DNH 164 (Eastern Elec. v. FERD Const., et al.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.