Anderson v. Shattuck

81 A. 781, 76 N.H. 240, 1911 N.H. LEXIS 196
Supreme Court of New Hampshire·Decided November 7, 1911·Published·Cited by 3 cases

Opinion

Walker, J.

At the time of the fire the plaintiffs were engaged in constructing the building under the contract, with the acquiescence and consent of the defendant, although the time limited in the contract for the completion of the building had expired four days before. The fact that the time limit had expired does not affect the legal theory, in accordance with which the plaintiffs’ right to recover for the benefits they had conferred upon the defendant must be determined. The plaintiffs, with the assent of the defendant, were rightfully engaged in the prosecution of the work at the time of the fire. They had already performed a substantial part of the work they contracted to do, when the fire destroyed the buildings with the attendant result of terminating the contract in accordance with the understanding of the parties when they executed it. In accordance with the decision in Dame v. Woods, 73 N. H. 222, — 8. C., 75 N. H. 38, it is found that the labor and materials actually furnished by the plaintiffs were attached to the defendant’s real estate as the work progressed and constituted a benefit to the defendant for which the plaintiffs are entitled to recover. Upon this point there is no contention. The principal question presented relates to the rule or principle by which the plaintiffs’ recoverable damages shall be determined.

It is necessary to bear in mind that the plaintiffs’ action at law is not based upon a breach of the written contract by the defendant. There has been no breach of the express contract by the defendant, and neither party is in fault for the fire which put an end to the contract and caused the situation now existing between the parties. But justice does not require that they should remain in that situation, or that the contractors should be remediless, merely because they cannot maintain an- action against the defendant upon the contract. As was said in Dame v. Woods, 73 N. H. 222: “This proceeding is not an action upon the special contract, but of quasi-contract, to recover the benefits, if any, which the plaintiff may have conferred upon the defendant by his part performance of the special contract.” In cases where the part performance results from the plaintiff’s breach of the contract, as by his voluntary *243 failure to fully perform the work he agreed to do, he is entitled to recover what the benefits conferred upon the defendant are reasonably worth estimated upon the basis of the agreed price for the entire work, less any damage suffered by the defendant in consequence of the plaintiff’s breach of the special contract (Danforth v. Freeman, 69 N. H. 466, 468; Hutt v. Hickey, 67 N. H. 411; Chartier v. Marshall, 56 N. H. 478; Horn v. Batchelder, 41 N. H. 89; Britton v. Turner, 6 N. H. 481); and in some cases the sum the defendant should pay the plaintiff may be "conveniently ascertained by deducting from the contract price” (Danforth v. Freeman, supra) the cost of completing the work. Horn v. Batchelder, supra.

Subject to the plaintiffs’ exception, the superior court in accordance with this rule determined the amount of the defendant’s liability by deducting from the contract price for the whole work the amount it would have cost at the date of the fire to complete the building according to the terms of the contract. While the plaintiffs were not entitled to recover the whole contract price without diminution, they were not chargeable with the cost of completing the building, unless they had in some way broken their contract and caused such damage to the defendant. The charge of 82,500 which represents the cost of completing the work could only be sustained on the ground that it represented the defendant’s damages caused by the plaintiffs’ failure to finish the building. But the plaintiffs committed no. breach of the contract in this respect. The damage to the defendant, whatever it was, was caused by the fire for which no one is responsible. “In such a case neither party is in fault, and therefore is not responsible to the other for failing to fulfil. In a recovery on a quantum meruit there is an apportionment of so much of the agreed compensation to the contractor as he has earned in what he has done; he recovers such part- of the entire amount as is equal to the part he has performed of the whole contract.” 3 Suth. Dam., s. 709. If there had been no fire, and the plaintiffs without any reasonable excuse had abandoned the contract and refused to finish the work, they might have been liable to the defendant for what it would cost to complete the building; but such liability would result from the plaintiffs’ breach of the contract, which is wanting in this case.

Nor is this a correct method of ascertaining the benefits which the plaintiffs had conferred upon the defendant. If the contract price for the whole work was less than its reasonable cost, which seems to be the fact, it would clearly be inequitable to the plaintiffs *244 to deduct from the contract price the cost of completing the work. Justice would require that the sum deducted should bear the same relation to the cost as the contract price does. Upon such a theory the plaintiffs would receive, for the work and materials rendered to and accepted by the defendant, pay for the same regulated and determined by the contract price for the whole work; and that is evidently what they are entitled to. To state the same idea in another and more practical way, “the plaintiff was entitled to recover such a part of the contract price as the work and materials he had done and furnished was of the work and materials he agreed to perform and furnish.” Dame v. Wood, 75 N. H. 38, 39.

Free access — add to your briefcase to read the full text and ask questions with AI

Anderson v. Shattuck, 81 A. 781, 76 N.H. 240, 1911 N.H. LEXIS 196 (N.H. 1911).

81 A. 781 (Anderson v. Shattuck) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Burgess v. Queen
470 A.2d 861 (Supreme Court of New Hampshire, 1983)
R. J. Berke & Co. v. J. P. Griffin, Inc.
367 A.2d 583 (Supreme Court of New Hampshire, 1976)
United States Fidelity & Guaranty Co. v. Parsons
112 So. 469 (Mississippi Supreme Court, 1927)