Kinetic System, Inc. v. IPS-Integrated Project Services, LLC

CourtDistrict Court, D. New Hampshire
DecidedFebruary 6, 2024
Docket1:20-cv-01125
StatusUnknown

This text of Kinetic System, Inc. v. IPS-Integrated Project Services, LLC (Kinetic System, Inc. v. IPS-Integrated Project Services, LLC) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kinetic System, Inc. v. IPS-Integrated Project Services, LLC, (D.N.H. 2024).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Kinetic Systems, Inc.

v. Civil No. 20-cv-1125-SM Opinion No. 2024 DNH 008 IPS-Integrated Project Services, LLC and Lonza Biologics, Inc.

O R D E R This dispute arises out of a commercial construction project in Portsmouth, New Hampshire. Kinetic Systems, Inc. was a subcontractor on that project and brought an action against Integrated Project Services, LLC (“IPS”), the project’s general contractor, and Lonza Biologics, Inc., the owner, seeking nearly $14 million for extra work it alleges that it did on that project.1 IPS moves for partial summary judgment, challenging Kinetics’s breach of contract claim for payment of amounts related to certain changes in the project. Kinetics objects to summary judgment, arguing that material factual disputes as to whether IPS waived contract provisions preclude summary judgment

1 In the complaint, the plaintiff refers to itself as “Kinetics” although the name of the company is Kinetic Systems, Inc. In the current motions and memoranda, the plaintiff refers to itself as “KSI”, while IPS uses “Kinetics”. On its website, the plaintiff refers to itself as “Kinetics”. www.kinetics.net (last visited January 18, 2024). To avoid confusion, the court will consistently refer to the plaintiff as “Kinetics”. and that the partial waivers and releases it signed are not enforceable.

Standard of Review Summary judgment is appropriate when the moving party shows that there is no genuine dispute of material fact and that it is

entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a); M.L. by and through D.L. v. Concord Sch. Dist., 86 F.4th 501, 510 (1st Cir. 2023) (internal quotation marks omitted). A genuine dispute “is one that must be decided at trial because the evidence, viewed in the light most flattering to the nonmovant, would permit a rational factfinder to resolve the issue in favor of either party.” Id. (internal quotation marks omitted). “Material facts are those that might affect the outcome of the suit under the governing law.” Id. Therefore, no genuine dispute of material fact is shown “if, based on the record, there is no factual determination which a rational

factfinder could make as to the existence or nonexistence of a fact that has the potential to change the outcome of the suit.” Gibson Found., Inc. v. Norris, 88 F.4th 1, 5 (1st Cir. 2023).

Background IPS was the general contractor on a project to construct a manufacturing facility for Lonza. It, in turn, hired Kinetics to construct and implement mechanical and process systems at the Lonza facility. That subcontracting relationship was governed by two contracts: the Early Mechanical Subcontract and the Process Piping Subcontract. Each Subcontract requires IPS to pay Kinetics a lump sum for the work specified. The Subcontracts also include provisions for changing the scope of

work, increasing the amount to be paid, and resolving disputes about changes and payments.

A. Subcontract Provisions for Changing Work and Payment The Subcontracts require certain procedures to make changes to the scope of Kinetics’s work on the project, including changes to the time required and payments due, which are found in Section 6 of each Subcontract, titled “Changes in the Work.” Doc. no. 57-2, at 20-22; Doc. no. 57-8, at 20-22. Section 7 provides the procedures for payment, and Section 12 provides the procedures for claims and disputes between IPS and its

subcontractors. Doc. no. 57-2, at 22-23 & 57-2, at 35-36; Doc. no. 57-8, at 22-3 & 57-8, at 35-36.2 To make a change to the requirements in the Subcontracts, IPS first is required to notify the subcontractor of the

2 The Subcontracts include the same language pertinent to changes in the work and related procedures. The court will cite to the Subcontract sections rather than the documents where the Subcontracts are filed. proposed change. § 6.2. After receiving notice - but before beginning the work - the subcontractor is required to submit “a written proposal for the Change, which proposal shall include, (a) the modification to the scope of Work to be performed under the proposed Change, (b) Subcontractor’s good faith estimate of the adjustment in the Subcontract Price payable as a result of

the proposed Change, and (c) Subcontractor’s estimate of the adjustment, if any, to the Subcontract Time resulting from the proposed Change.” § 6.4. IPS then decides whether to accept or reject the subcontractor’s written proposal for an adjustment to the subcontract. Id. If a subcontractor does not request a time or cost adjustment through a timely proposal, the subcontractor is deemed to represent that no adjustment is required and waives its right to any adjustment for that Change. § 6.5. The subcontractor is required to submit all claims for adjustment due to a change in the work within the time provided

in the change notice. § 6.8. If no time is provided, then claims are to be made within five business days of the date of the notice “but in no event less than two (2) Business Days prior to the date upon which IPS must respond with all such claims under the Prime Contract, whichever period is shorter.” Id. The parties expressly agree that the subcontractor waives any claims for adjustment to the price and time provided in the Subcontracts if a claim is not submitted to IPS within the time allowed. Id. A subcontractor can also make claims for increases in the price or time for the work “[d]ue to acceleration, disruption, inefficiency or for any other reason which may adversely impact the Work or Subcontractor’s performance under the Agreement

within two (2) Business Days following the occurrence of the event giving rise to the claim.” § 6.12.1. Such claims have to be supported by “appropriate information and documentation.” Id. The Subcontracts also provide that “Subcontractor’s timely compliance with the notice requirements in section 6.12.1 shall be a condition precedent to Subcontractor’s entitlement to a Subcontract adjustment in either the time or price and Subcontractor waives and releases any claim to additional compensation or an extension of time in the event that Subcontractor does not so comply.” § 6.12.4. If the parties are unable to agree upon a price for

Kinetics’s additional work, the Subcontracts allow IPS to compel Kinetics to perform the work through a “Change Directive,” after which the parties were committed to agree upon an appropriate adjustment to the price and time allowed. § 6.6. Importantly, however, Anthony Malvone, IPS’s Operations Manager, states in his declaration that IPS did not issue a Change Directive to Kinetics for the Lonza project to compel Kinetics to perform work outside the scope of the Subcontracts. Doc. no. 57-25, ¶ 12. Kinetics does not dispute that statement. The Subcontracts also provide a process for resolving claims and disputes between IPS and its subcontractors. § 12.2. The claims or disputes “shall first be attempted to be resolved by good-faith negotiation between senior management of the

Parties.” § 12.2.1. Second, if that process is unsuccessful, “then the Parties agree to try in good faith to settle the claims or disputes (or remaining portion thereof) by mediation administered by the American Arbitration Association.” Id. Finally, if unresolved disputes remain, the Subcontracts establish a bifurcated dispute resolution process, depending on the amount at issue. For disputes involving amounts less than $250,000, the parties agree that such disputes shall be resolved by arbitration. § 12.2.1.1. For disputes involving $250,000 or more, the parties agree that they may be resolved by arbitration or by litigation. § 12.2.1.2.

B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D. M. Holden, Inc. v. Contractor's Crane Service, Inc.
435 A.2d 529 (Supreme Court of New Hampshire, 1981)
MacQuesten General Contracting, Inc. v. HCE, INC.
191 F. Supp. 2d 407 (S.D. New York, 2002)
City of Portsmouth v. Nash
493 A.2d 1163 (Supreme Court of New Hampshire, 1985)
Gianola v. Continental Casualty Co.
817 A.2d 306 (Supreme Court of New Hampshire, 2003)
Daniel v. Hawkeye Funding, Ltd. Partnership
843 A.2d 946 (Supreme Court of New Hampshire, 2004)
Axenics, Inc. v. Turner Construction Co.
62 A.3d 754 (Supreme Court of New Hampshire, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Kinetic System, Inc. v. IPS-Integrated Project Services, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kinetic-system-inc-v-ips-integrated-project-services-llc-nhd-2024.