MacQuesten General Contracting, Inc. v. HCE, INC.

191 F. Supp. 2d 407, 2002 U.S. Dist. LEXIS 5295, 2002 WL 471745
CourtDistrict Court, S.D. New York
DecidedMarch 22, 2002
Docket99 CIV.8598(VM)
StatusPublished
Cited by7 cases

This text of 191 F. Supp. 2d 407 (MacQuesten General Contracting, Inc. v. HCE, INC.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MacQuesten General Contracting, Inc. v. HCE, INC., 191 F. Supp. 2d 407, 2002 U.S. Dist. LEXIS 5295, 2002 WL 471745 (S.D.N.Y. 2002).

Opinion

MARRERO, District Judge.

This proceeding is in the matter of MacQuesten General Contracting, Inc. v. HCE, Inc., et al, Docket No. 99 Civ. 8598. The Court called this conference to issue its ruling on the parties’ cross-motions for partial summary judgment. The filing of plaintiff MacQuesten’s complaint was followed by the filing of counterclaims and third party practice by defendant HCE. The cross-motions for partial summary judgment pertain to the underlying complaint, the counterclaims and the third-party claims.

At the outset, the Court notes that although the parties have come forward with seemingly complex cross-motions with voluminous submissions, most of the parties contentions merely underscore that there remain contested issues of material fact about which the parties’ have widely divergent views. Neither side makes a particularly convincing case to support its version of the events at issue, but at the same time, both parties have marshaled just enough, by way of sworn affidavits and documentary submissions, to raise several triable issues of fact.

The parties in this matter appear to be unable to agree on much of anything; nev *409 ertheless, the Court highlights two critical issues, among many, to illustrate the parties’ positions on their respective cross-motions. According to HCE, the manner in which MacQuesten made periodic monthly payments under the three subcontracts involved the use of two supporting documents: HCE’s invoices and the “progress payment applications,” required by Article 11 of the sub-contract agreements. (Declaration of John J. Hildreth, sworn to June 13, 2001 (“Hildreth Dec.”), ¶¶ 8-11.) In a sworn affidavit, the President of HCE, John J. Hildreth, avers that the HCE invoices reflected the true amount of the work completed by HCE to date and that the amount of the progress payment applications merely represented amounts that MacQuesten was able to pay at that time. {Id. at ¶ 9.) Hildreth further contends that he agreed with representatives of MacQuesten that the true amount of work completed, as reflected in its invoices, would be paid in full in future installments. {Id.) For its part, MacQues-ten’s Project Manager for the Palmer Court Homes, Alan Goncharoff, submitted his own sworn affidavit asserting that value of the work completed by HCE was reflected in the progress payment applications and not in the HCE invoices. (Reply Affidavit of Alan Goncharoff, sworn to July 13, 2001 (“Goncharoff Reply Aff.”), ¶¶ 10, 18.) Furthermore, in his reply affidavit, Goncharoff contends that “I also never advised HCE that MacQuesten would only pay what it could afford. In fact, HCE was repeatedly advised that it would be paid the full value of the work it completed, in accordance with its subcontract agreements.” {Id. at ¶ 17.)

The parties also disagree on the way in which their contractual relationship effectively ended. MacQuesten claims that HCE simply walked off the job. (Affidavit of Relia Fogliano, sworn to Apr. 25, 2001 (“Fogliano Aff.”), ¶ 8.) HCE contends that it was locked out of the project site and prohibited from re-entering. (Hildreth Dec., ¶ 27).

Thus, the Court is faced with a classic case of dueling affidavits that raise hotly contested issues of fact. As the Court noted earlier, neither party presents a factual case so convincing that the Court is compelled endorse it over the other. At the same time, both parties have come forward with sworn testimony and documentary submissions that, at least at this stage of the litigation, raise genuine issues of material fact. As such, the Court finds that most of the claims raised in the cross-motions should be denied, and the parties should be afforded an opportunity to prove their cases at trial.

Nevertheless, the Court is compelled to give fair warning to the parties at this point. In any litigation, it is commonplace for the parties to feel passionately about their respective positions. Oftentimes, the truth lies somewhere between the extremes taken up by litigants. That may be the case here. However, the Court has some concern that should be evident from its recitation of the two factual disputes above. In cases such as this, it may not be possible for both parties to be right, even though they support their positions with sworn affidavits. For example, it defies logic that HCE intentionally failed to return to the Palmer Court Housing Project and simultaneously was locked out of the construction site, with every intention of completing its tasks.

Despite the abundance of factual issues raised in the parties’ cross-motions, there are, however, discrete claims which are subject to disposition on summary judgment motions.

HCE’s Motion for Partial Summary Judgment

First, the Court grants HCE’s motion for summary judgment on MacQues- *410 ten’s second claim sounding in fraud. The law in this Circuit is well-settled: a party seeking to bring a claim of fraud, in addition to a claim of breach of contract, may do so only if it can: (1) demonstrate a legal duty separate from the duty to perform under the contract; (2) demonstrate a fraudulent misrepresentation collateral or extraneous to the contract; or (3) assert special damages that are caused by the misrepresentation and unrecoverable as contract damages. See Bridgestone/Firestone, Inc. v. Recovery Credit Services, Inc., 98 F.3d 13, 20 (2d Cir.1996); see also Ladenburg Thalmann & Co., Inc. v. Imaging Diagnostic Systems, Inc., 176 F.Supp.2d 199, 206 (S.D.N.Y.2001).

According to MacQuesten the separately actionable fraud here concerns Hil-dreth’s allegedly fraudulent statements that HCE had paid all of the laborers and vendors working towards the completion of HCE’s subcontract. The record reflects, however, that HCE’s duties to pay its laborers and vendors and to affirm its payment of those parties are firmly rooted in Articles 4.1.6 and 11.2 of the subcontract agreement. Therefore, the Court fails to see how these duties arise apart from the underlying obligations in the operative agreement. Furthermore, any representations made by HCE in this regard cannot be extraneous to the contract; the representations squarely addressed contractual obligations. Finally, damages for these alleged misrepresentations may be recoverable, if proven, through MacQuesten’s breach of contract claim. For these reasons, HCE’s motion for partial summary judgment on MacQuesten’s second claim is granted.

MacQuesten’s Motion for Partial Summary Judgment

MacQuesten moves to dismiss HCE’s counterclaims for breach of contract, lien enforcement, conversion and interference with HCE’s economic and business relations. MacQuesten’s motions are denied in substantial part and granted in limited respects.

The Court agrees with MacQues-ten in that Relia and Sabino Fogliano are not parties to any agreements between the corporate litigants. As the court noted in Polyglycoat Corp. v. C.P.C. Distributors, Inc., 534 F.Supp. 200, 204 n. 5 (S.D.N.Y.1982) (citations omitted), an officer “cannot be independently charged for breaching or conspiring to breach a contract to which he is not personally a party.” That same principle applies here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
191 F. Supp. 2d 407, 2002 U.S. Dist. LEXIS 5295, 2002 WL 471745, Counsel Stack Legal Research, https://law.counselstack.com/opinion/macquesten-general-contracting-inc-v-hce-inc-nysd-2002.