MacQuesten General Contracting, Inc. v. HCE, INC.

296 F. Supp. 2d 437, 2003 U.S. Dist. LEXIS 21493, 2003 WL 22845779
CourtDistrict Court, S.D. New York
DecidedDecember 1, 2003
Docket99 Civ. 8598(JCF)
StatusPublished
Cited by3 cases

This text of 296 F. Supp. 2d 437 (MacQuesten General Contracting, Inc. v. HCE, INC.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MacQuesten General Contracting, Inc. v. HCE, INC., 296 F. Supp. 2d 437, 2003 U.S. Dist. LEXIS 21493, 2003 WL 22845779 (S.D.N.Y. 2003).

Opinion

MEMORANDUM OPINION ' AND ORDER

FRANCIS, United States Magistrate Judge.

This case arises from a dispute between a general contractor and a subcontractor. The general contractor, MacQuesten General Contracting, Inc. (“MacQuesten”), brought suit alleging that the subcontractor, HCE, Inc. (“HCE”) failed to complete the work required under contracts between them. HCE counterclaimed, asserting that MacQuesten had locked it out of the worksite and had failed to make payment for much of the work that was done. HCE also filed third-party claims against the owner of the property, Palmer Court Associates, LLC (“Palmer' Court”), and a surety, American Motorists Insurance Company (“AMIC”) for foreclosure of a mechanic’s lien against the property and against a bond issued by AMIC. The case proceeded to a jury trial over which I presided upon consent of the parties pursuant to 28 U.S.C. § 636(c).

HCE prevailed at trial. The jury rejected MacQuesten’s claims and awarded HCE substantial damages on its counterclaims. The parties reserved issues concerning the mechanic’s lien for subsequent determination by the Court. MacQuesten now moves pursuant to Rules 50(b) and 59(a)(1) of the Federal Rules of Civil Procedure for an order setting aside the jury verdict on damages and granting a new trial, or, in the alternative, for a remittitur of the verdict on damages. HCE, in turn, moves to amend and enforce its mechanic’s lien. Finally, Palmer Court and AMIC cross-move for summary judgment vacating the lien. Background,

In August 1998, Palmer Court entered into a contract with MacQuesten, providing that MacQuesten would serve as general contractor for construction of affordable housing on property owned by Palmer Court at 3300 Palmer Avenue in the Bronx. (Tr. 28-29; PI. Exh. I). 1 Immediately thereafter, MacQuesten executed two subcontracts with HCE. One subcontract provided that HCE would be paid $544,150 for-foundation work, including construction of concrete footings, walls, and slab-on-grade (the “foundation contract”). (Def.Exh. 2). The contract sum for the foundation work was later increased to $705,300 based on additional work requested by MacQuesten. (Tr. 622-23, 742, 751). The second subcontract provided that HCE would be paid $2,198,000 to install the planks, Vestcom Structural Floor System, and concrete columns and beams for the project (the “plank contract”). (PI. Exh. 3). In February 1999, HCE began performing masonry work under a third contract that was never signed. (Tr. 701-OS; PI. Exh. 4).

Each month, HCE submitted invoices to MacQuesten for the work completed. (Tr. *441 628). Before these invoices were considered final, HCE’s president, John Hil-dreth, met with Alan Goncharoff, Mac-Questen’s project manager, to negotiate any discrepancies. (Tr. 629, 739-40). Once the invoices were agreed to by Mr. Goncharoff, they were formally presented to MacQuesten. (Tr. 629). However, before MacQuensten made payment, it required HCE to execute a subcontractor payment form that included a partial waiver of lien and represented that the subcontractor had been paid in full for work done to date. (Tr. 630, 740-41; PL Exh. 8A). Nevertheless, according to HCE, Mr. Gon-charoff persuaded HCE to sign the subcontractor payment forms for less than the invoiced amount on the basis that Mac-Questen could not afford to pay any more at the time. (Tr. 760-61). Mr. Goncharoff reportedly agreed that MacQuesten would ultimately pay the full amount reflected in the invoices. (Tr. 760-68, 772-73, 776-77, 780, 817-18).

Over time, the relationship between the parties deteriorated. First, HCE encountered a significant amount of unanticipated rock and unsuitable soil as it began excavating for the foundation. (Tr. 618-19). Removal of the rock and additional excavation delayed the project for about six weeks and increased HCE’s costs. (Tr. 619-22). As the work continued, the gap between the amount invoiced by HCE and the total payments made by Mac-Questen grew wider. When HCE raised this issue in January 1999, MacQuesten agreed to an immediate payment of $100,000, with another $400,000 to be provided when MacQuesten paid HCE’s then outstanding invoice. (Tr. 760-64). Further, MacQuesten represented that all of HCE’s invoices would be paid in full when additional funding was received for the project in April. (Tr. 776-79).

By the end of April, MacQuesten had not made the promised $400,000 payment, and HCE was experiencing difficulty paying its suppliers. (Tr. 793-95). On May 13, 1999, Mr. Hildreth met with Mr. Gon-charoff and Sabino Fogliano, one of Mac-Questen’s principals. (Tr. 824). By that time, the difference between HCE’s invoices and MacQuesten’s payments had grown to approximately $1.3 million. (Tr. 831). Mr. Fogliano promised to pay $440,000 by May 21, but that payment was never made. (Tr. 834-35). Accordingly, on June 1, 1999, counsel for HCE sent a letter to MacQuesten advising that it intended to file a lien on the project. (Tr. 840; Def. Exh. 412). Thereafter, according to HCE, MacQuesten refused to allow HCE to return to the site to continue work or to recover its equipment. (Tr. 845-46).

MacQuesten then brought suit, alleging that HCE had abandoned the project, thereby breaching the contracts and causing damage to MacQuesten. HCE counterclaimed and filed third-party claims against Palmer Court and AMIC. Following the completion of discovery, the parties submitted cross-motions for partial summary judgment. The Honorable Victor Marrero, U.S.D.J., who was then presiding over the case, granted HCE’s motion and dismissed a claim of fraud asserted by MacQuesten. (Statement of the Court, attached to Order dated March 22, 2002 (“Order”) at 4-5). Judge Marrero also granted MacQuesten’s motion for summary judgment to the extent of dismissing breach of contract claims against Sabino and Relia Fogliano. (Order at 5-6). However, he denied the balance of MacQues-ten’s motion with respect to HCE’s claims of breach of contract against MacQuesten, lien enforcement, conversion, and interference with economic and business relations. (Order at 6-9).

The case then proceeded to trial. After HCE presented evidence on its counterclaims, MacQuesten failed to move for *442 judgment as a matter of law under Rule 50. (Tr. 1105-10). The jury returned a verdict rejecting MacQuesten’s claims for breach of contract. It also rejected HCE’s claims of fraud against MacQues-ten, Sabino Fogliano, and Relia Fogliano. However, the jury found for HCE on its remaining counterclaims. Concluding that MacQuesten had breached written and oral contracts and had violated the implied covenant of good faith and fair dealing, the jury awarded HCE $1,042,355.79 on unpaid invoices, $86,000 for equipment that remained on site, and $149,065.72 for extended overhead and profit. Further, the jury found MacQuesten liable for conversion of HCE’s machinery and equipment and awarded $86,000 in compensatory damages and $27,500 in punitive damages. Finally, it found that MacQuesten had been unjustly enriched and awarded $416,942.32 on that counterclaim. (Jury Verdict Form, attached as Exhibit 1 to Certification of Peter S. Herman dated July 2, 2003 (“Herman Cert.”)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Buchwald v. Renco Group
539 B.R. 31 (S.D. New York, 2015)
Macquesten General Contracting, Inc. v. HCE, Inc.
128 F. App'x 782 (Second Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
296 F. Supp. 2d 437, 2003 U.S. Dist. LEXIS 21493, 2003 WL 22845779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/macquesten-general-contracting-inc-v-hce-inc-nysd-2003.