Macquesten General Contracting, Inc. v. HCE, Inc.

128 F. App'x 782
CourtCourt of Appeals for the Second Circuit
DecidedMarch 23, 2005
DocketNos. 04-0418CVL, 04-0503CVCON
StatusPublished
Cited by7 cases

This text of 128 F. App'x 782 (Macquesten General Contracting, Inc. v. HCE, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Macquesten General Contracting, Inc. v. HCE, Inc., 128 F. App'x 782 (2d Cir. 2005).

Opinion

SUMMARY ORDER

This is an appeal from a judgment of the District Court entered in favor of HCE, Inc. and its president John Hildreth (collectively, “HCE”), and against MacQuesten General Contracting, Inc. (“MacQuesten”) and the American Motorist Insurance Company (“AMIC”). The case arises out of a dispute between MacQuesten (the general contractor) and HCE (the subcontractor). It has been the subject of a summary judgment opinion, MacQuesten General Contracting, Inc. v. HCE, Inc., 191 F.Supp.2d 407 (S.D.N.Y.2002) (Marrero, J.), and a decision on the post-trial [784]*784motions, MacQuesten General Contracting, Inc. v. HCE, Inc., 296 F.Supp.2d 437 (S.D.N.Y.2003) (Francis, M.J.). Familiarity with each of these and the underlying facts is assumed.

After a jury trial before Magistrate Judge James C. Francis, IV, the jury awarded HCE damages on its counterclaims against MacQuesten for, among other things, breach of written and oral contracts and for conversion. MacQuesten filed post-trial motions for a new trial pursuant to Federal Rule of Civil Procedure 59(a), arguing primarily that, as a matter of law, the damage award based on certain “unpaid invoices” was improper. Mac-Questen also raised (unpreserved) objections to the jury charge under Rule 51, and it sought a new trial on the compensatory and punitive damages arising out of the conversion claim. The Magistrate Judge denied MacQuesten’s post-trial motions, except that it ordered remittitur as to certain damages. (HCE accepted the remittitur.)

In addition, following the jury trial, HCE moved to foreclose on a Notice of Mechanics’ Lien and collect on a discharge bond issued by AMIC to secure the lien. MacQuesten and AMIC opposed the motion and filed cross-motions to vacate the lien on various grounds, including that the Notice of Lien had not completely described the property subject to lien. The Magistrate Judge denied the cross-motions, granted HCE permission to amend its lien nunc pro tunc to correct the property description, and granted HCE’s motion to foreclose on the amended lien.

After judgment was entered, MaeQues-ten and AMIC timely filed notices of appeal and challenge the Magistrate Judge’s denial of their post-trial motions. For substantially the reasons stated in the Magistrate Judge’s thoughtful and thorough opinion, we AFFIRM the judgment.

DISCUSSION

MacQuesten moved for a new trial under Rule 59(a) on the grounds that HCE, as a matter of law, has no right to damages for “unpaid invoices.” While MacQuesten failed during the trial to make a motion for judgment as a matter law pursuant to Rule 50(a), that is no impediment to a Rule 59(a) motion. Under Rule 59(a), a new trial may be granted even if there is substantial evidence supporting the jury’s verdict, and the trial judge is free to weigh the evidence independently and need not view it in the light most favorable to the verdict winner. See Manley v. Ambase Corp. 337 F.3d 237, 244-45 (2d Cir.2003). Nonetheless, to order a new trial under Rule 59(a), the trial judge must conclude that “the jury has reached a seriously erroneous result or ... the verdict is a miscarriage of justice.” Song v. Ives Labs., Inc., 957 F.2d 1041, 1047 (2d Cir.1992) (internal quotation marks omitted); see also Manley, 337 F.3d at 245. We review a trial court’s denial of a Rule 59(a) motion for abuse of discretion. See Manley, 337 F.3d at 245; Song, 957 F.2d at 1047.

On appeal, MacQuesten argues that, as a matter of law, HCE has no right to damages for “unpaidr’invoices” — unpaid amounts stated in HCE’s invoices but not stated in certain “Payment Forms” that HCE submitted as progress payment applications. MacQuesten argues that, under the subcontracts, the submission of Payment Forms was a condition precedent to any payment and precludes recovery of any amount not stated in the Forms. MacQuesten also argues that HCE unambiguously waived its right to payment on the invoices because the Payment Forms contained a certification that HCE was being paid in full for all work done during the relevant pay period and contained a release (“Partial Waiver of Lien”) as to any claims against the owner or contractor for services rendered during the pay peri[785]*785od. Throughout the litigation, however, HCE has argued that, due to MacQuesten’s financial difficulties during the project, MacQuesten and HCE orally agreed to a system of partial payments. According to HCE, under this system, the Payment Forms reflected amounts that MacQuesten was able to pay at the time and MacQuesten agreed to pay HCE the full amounts stated in the invoices. We agree with the Magistrate Judge that MacQuesten’s arguments in this regard do not merit a new trial.

First, the District Judge1 denied Mac-Questen’s motion for summary judgment based on the waiver argument and found that, despite the waiver in the Payment Forms, a factual issue existed “as to whether the parties did in fact implement a system of partial payment for work performed.” The District Judge noted evidence of a practice of the parties to treat “the waivers in the progress payment applications [as] receipts of partial payments with full payment on the invoices due at a later date.” New York case law directly on point supports the District Judge’s conclusion: ‘Where a waiver form [submitted by a subcontractor] purports to acknowledge that no further payments are owed, but the parties’ conduct indicates otherwise, the instrument will not be construed as a release.” West End Interiors, Ltd. v. Aim Constr. & Contracting Corp., 286 A.D.2d 250, 729 N.Y.S.2d 112, 114-15 (App. Div. 1st Dep’t 2001); see also Apollo Steel Corp. v. Sicolo & Massaro, Inc., 300 A.D.2d 1021, 752 N.Y.S.2d 493, 494 (4th Dep’t 2002) (reversing summary judgment dismissal on facts similar to this case).

Moreover, the jury was charged as to HCE’s breach of oral contract claim “that MacQuesten orally agreed to pay HCE for the entire amount HCE invoiced MacQues-ten for all of the goods and services provided by HCE in connection with the project.” The jury found that MacQuesten breached this oral contract. On appeal, MacQuesten does not specifically dispute— or even mention — the breach of the oral contract. The jury’s finding that Mac-Questen agreed to implement a partial-payment system and pay HCE based on the invoices vitiates any argument that a condition precedent or waiver under the initial written contracts precludes recovery. Thus the Magistrate Judge did not exceed his allowable discretion in finding no seriously erroneous result or miscarriage of justice as to the damages for the unpaid invoices.

Also with respect to HCE’s right to damages on the “unpaid invoices,” Mac-Questen asserts that the jury charge did not include proper waiver and condition precedent instructions. Because Mac-Questen did not preserve its objections during trial, pursuant to Fed.R.Civ.P. 51(d)(2), as amended effective December 1, 2003, we review the jury instructions for plain error. The plain error standard replaces the more stringent “fundamental error” standard that was employed in this Circuit prior to the 2003 amendment and that was applied by the Magistrate Judge on the post-trial motions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Medisim Ltd. v. Bestmed, LLC
758 F.3d 1352 (Federal Circuit, 2014)
Rasanen v. Brown
723 F.3d 325 (Second Circuit, 2013)
Medisim Ltd. v. BestMed LLC
959 F. Supp. 2d 396 (S.D. New York, 2013)
Henry v. Dinelle
929 F. Supp. 2d 107 (N.D. New York, 2013)
Snyder v. New York State Education Department
486 F. App'x 176 (Second Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
128 F. App'x 782, Counsel Stack Legal Research, https://law.counselstack.com/opinion/macquesten-general-contracting-inc-v-hce-inc-ca2-2005.