Universal v. CSI-Concrete Sys.

2012 DNH 115
District Court, D. New Hampshire·Decided July 5, 2012·No. CV-11-030-LM·Published·Cited by 2 cases

Opinion

Universal v . CSI-Concrete Sys. CV-11-030-LM 7/5/12 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Universal Am-Can, Ltd.

v. Civil N o . 11-cv-030-LM Opinion N o . 2012 DNH 115 CSI-Concrete Systems, Inc.

O R D E R

After a two-day trial, the jury in this civil action rendered a verdict in favor of CSI-Concrete Systems, Inc. (“CSI”) on the breach-of-contract claim asserted against it by Universal Am-Can, Ltd. (“Universal”). The jury also rendered an advisory verdict in favor of Universal on its equitable claim for quantum meruit and found damages of $13,475. Before the court for final resolution are Universal’s quantum-meruit claim and its claim under New Hampshire’s Consumer Protection Act (“CPA”), N.H. Rev. Stat. Ann. (“RSA”) ch. 358-A. For the reasons that follow, the court finds and rules that Universal is entitled to $13,475 in damages on its claim for quantum meruit, and that CSI is entitled to judgment on Universal’s CPA claim.

Quantum Meruit

“A valid claim in quantum meruit requires [that]: . . . (1)

services were rendered to the defendant by the plaintiff; (2) with the knowledge and consent of the defendant; and (3) under

circumstances that make it reasonable for the plaintiff to expect payment.” Gen. Insul. C o . v . Eckman Constr., 159 N.H. 601, 612 (2010) (quoting Paffhausen v . Balano, 708 A.2d 269, 271 (Me. 1998)).

CSI first argues that Universal has not even met the necessary prerequisite for making a quantum-meruit claim, i.e., the lack of a valid contract covering the subject matter of the parties’ dispute. That argument is not persuasive. The Supreme Judicial Court of Massachusetts has explained that “[r]ecovery in quantum meruit presupposes that no valid contract covers the subject matter of a dispute.” MCI WorldCom Commc’ns, Inc. v . Dep’t of Telecoms. & Energy, 802 N.E. 2d 8 0 2 , 812 (Mass. 2004) (quoting Boswell v . Zephyr Lines, Inc., 606 N.E.2d 1336, 1342 (Mass. 1993)). In CSI’s view, Universal’s agreement to haul its goods for $1,360 per load “so long as the fuel stays at a level under $2.22 per gallon,” Pl.’s Ex. 1 , was a valid contract that covered the subject matter of the dispute. CSI is mistaken. The subject matter of the dispute is the amount CSI was obligated to pay Universal for hauling the last 275 loads of the job. Those loads were all hauled at times when the cost of fuel was more than $2.22 per gallon. The contract between Universal and CSI only obligated Universal to haul CSI’s goods for $1,360 per load when fuel cost less than $2.22 per gallon. As much as

CSI might wish it had entered into a fixed-price contract, it did not do s o . For reasons best understood by the parties themselves, they entered into an agreement that did not establish a rate for loads hauled when fuel cost $2.22 per gallon or more. Because there was no valid contract that covered the subject matter of the dispute, i.e., the rate for hauling CSI’s goods when fuel cost $2.22 per gallon or more, Universal has established the prerequisite for a quantum-meruit claim described in MCI WorldCom. Accordingly, the court turns to the elements of Universal’s claim.

Universal hauled 275 loads of CSI’s concrete forms after February 9, 2010, and CSI concedes that Universal has established the first element of a claim for quantum meruit. There is no dispute that those loads were hauled with the knowledge and consent of C S I , which satisfies the second element. CSI argues that Universal has not established that element because i t , C S I , did not consent to payment of the fuel surcharge. But that is not the question. The question is whether Universal rendered services to CSI with CSI’s knowledge and consent, and there is no reasonable argument to be made that CSI did not know about or consent to Universal hauling the last 275 loads of its job. Without CSI’s knowledge and consent, Universal’s drivers would not have been able to pick up the

concrete forms they hauled to Milwaukee. That leaves the third element of Universal’s quantum-meruit claim.

Based on the evidence presented at trial, the court concludes that Universal hauled CSI’s goods under circumstances that made it reasonable for Universal to expect payment of more than $1,360 per load. Those circumstances include the following: (1) the agreement between Universal and CSI specified that the rate per load would be $1,360 only if the cost of fuel remained below $2.22 per gallon; (2) in mid February of 2010, the cost of fuel was approximately $2.76 per gallon; (3) when Steven Coughlin of Universal spoke with CSI’s Louis Falco on February 9, to inform CSI of his decision to impose a fuel surcharge of $204 per load, Falco did not assert that the parties had a fixed-price contract or deny that the rate per load was subject to a fuel-cost ceiling;1 and (4) after Coughlin broached the issue of a fuel surcharge with Falco, Coughlin was not informed by C S I , until after the last load had been delivered, that CSI was not going to pay the fuel surcharge Universal had been including on its invoices. Under those circumstances, it was reasonable for Universal, at the time it

1 Rather, he attempted to convince Coughlin that the parties had agreed to a fuel-cost ceiling of $3.22 per gallon rather than the $2.22 per gallon stated in Coughlin’s e-mail of May 2009.

hauled the final 275 loads of CSI’s job, to expect payment by CSI of some amount in excess of $1,360 for each of those loads.

CSI responds by arguing that “[t]he evidence submitted at trial demonstrates that it was unreasonable for Universal to expect payment of the disputed fuel surcharge.” Def.’s O b j . (doc. n o . 6 7 ) , at 5 . In support of that argument, CSI notes evidence that: (1) Falco did not agree to the surcharge; (2) Coughlin waited until after the job was finished to raise the issue with CSI’s Len Worden; and (3) CSI’s John Perry was not authorized to agree to the surcharge. Whether it was reasonable for Universal to expect payment of the $204-per-load fuel surcharge is beside the point. The question is whether it was reasonable for Universal to expect to be paid some amount in excess of $1,360 for hauling each of the last 275 loads of the job. And, for the reasons the court has already given, that was a reasonable expectation.

Because CSI is liable to Universal in quantum meruit, the only issue that remains is the amount of Universal’s damages. “In quantum meruit . . . the damages are not measured by the benefit realized and retained by the defendant, but rather are based on the value of the services provided by the plaintiff.” Paffhausen, 708 A.2d at 271 (citing William Mushero, Inc. v . Hull, 667 A.2d 853, 855 (Me. 1995) (“The measure of recovery is

equal to the reasonable value of the services.”); Siciliani v . Connolly, 651 A.2d 386, 387 (Me. 1994)).

In the opinion of the jury, Universal is entitled to $13,475. Universal moves for an award in one of three amounts: (1) $56,100, which equals the $204-per-load surcharge Universal attempted to impose, multiplied by 275 loads; (2) $89,158.98, the amount of the expenses Universal says Falco determined it incurred as a result of increased fuel costs; or (3) $113,401.50, the total amount of the fuel surcharge Louisiana Pacific would have imposed on the last 275 loads of CSI’s job. CSI, in turn, argues that because none of Universal’s theories has adequate evidentiary support, any award of quantum-meruit damages should be limited to the $13,475 suggested by the jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Universal v. CSI-Concrete Sys., 2012 DNH 115 (D.N.H. 2012).

2012 DNH 115 (Universal v. CSI-Concrete Sys.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related