Universal v. CSI-Concrete Sys.

2012 DNH 115
CourtDistrict Court, D. New Hampshire
DecidedJuly 5, 2012
DocketCV-11-030-LM
StatusPublished
Cited by2 cases

This text of 2012 DNH 115 (Universal v. CSI-Concrete Sys.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal v. CSI-Concrete Sys., 2012 DNH 115 (D.N.H. 2012).

Opinion

Universal v . CSI-Concrete Sys. CV-11-030-LM 7/5/12 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Universal Am-Can, Ltd.

v. Civil N o . 11-cv-030-LM Opinion N o . 2012 DNH 115 CSI-Concrete Systems, Inc.

O R D E R

After a two-day trial, the jury in this civil action

rendered a verdict in favor of CSI-Concrete Systems, Inc.

(“CSI”) on the breach-of-contract claim asserted against it by

Universal Am-Can, Ltd. (“Universal”). The jury also rendered an

advisory verdict in favor of Universal on its equitable claim

for quantum meruit and found damages of $13,475. Before the

court for final resolution are Universal’s quantum-meruit claim

and its claim under New Hampshire’s Consumer Protection Act

(“CPA”), N.H. Rev. Stat. Ann. (“RSA”) ch. 358-A. For the

reasons that follow, the court finds and rules that Universal is

entitled to $13,475 in damages on its claim for quantum meruit,

and that CSI is entitled to judgment on Universal’s CPA claim.

Quantum Meruit

“A valid claim in quantum meruit requires [that]: . . . (1)

services were rendered to the defendant by the plaintiff; (2)

with the knowledge and consent of the defendant; and (3) under circumstances that make it reasonable for the plaintiff to

expect payment.” Gen. Insul. C o . v . Eckman Constr., 159 N.H.

601, 612 (2010) (quoting Paffhausen v . Balano, 708 A.2d 269, 271

(Me. 1998)).

CSI first argues that Universal has not even met the

necessary prerequisite for making a quantum-meruit claim, i.e.,

the lack of a valid contract covering the subject matter of the

parties’ dispute. That argument is not persuasive. The Supreme

Judicial Court of Massachusetts has explained that “[r]ecovery

in quantum meruit presupposes that no valid contract covers the

subject matter of a dispute.” MCI WorldCom Commc’ns, Inc. v .

Dep’t of Telecoms. & Energy, 802 N.E. 2d 8 0 2 , 812 (Mass. 2004)

(quoting Boswell v . Zephyr Lines, Inc., 606 N.E.2d 1336, 1342

(Mass. 1993)). In CSI’s view, Universal’s agreement to haul its

goods for $1,360 per load “so long as the fuel stays at a level

under $2.22 per gallon,” Pl.’s Ex. 1 , was a valid contract that

covered the subject matter of the dispute. CSI is mistaken.

The subject matter of the dispute is the amount CSI was

obligated to pay Universal for hauling the last 275 loads of the

job. Those loads were all hauled at times when the cost of fuel

was more than $2.22 per gallon. The contract between Universal

and CSI only obligated Universal to haul CSI’s goods for $1,360

per load when fuel cost less than $2.22 per gallon. As much as

2 CSI might wish it had entered into a fixed-price contract, it

did not do s o . For reasons best understood by the parties

themselves, they entered into an agreement that did not

establish a rate for loads hauled when fuel cost $2.22 per

gallon or more. Because there was no valid contract that

covered the subject matter of the dispute, i.e., the rate for

hauling CSI’s goods when fuel cost $2.22 per gallon or more,

Universal has established the prerequisite for a quantum-meruit

claim described in MCI WorldCom. Accordingly, the court turns

to the elements of Universal’s claim.

Universal hauled 275 loads of CSI’s concrete forms after

February 9, 2010, and CSI concedes that Universal has

established the first element of a claim for quantum meruit.

There is no dispute that those loads were hauled with the

knowledge and consent of C S I , which satisfies the second

element. CSI argues that Universal has not established that

element because i t , C S I , did not consent to payment of the fuel

surcharge. But that is not the question. The question is

whether Universal rendered services to CSI with CSI’s knowledge

and consent, and there is no reasonable argument to be made that

CSI did not know about or consent to Universal hauling the last

275 loads of its job. Without CSI’s knowledge and consent,

Universal’s drivers would not have been able to pick up the

3 concrete forms they hauled to Milwaukee. That leaves the third

element of Universal’s quantum-meruit claim.

Based on the evidence presented at trial, the court

concludes that Universal hauled CSI’s goods under circumstances

that made it reasonable for Universal to expect payment of more

than $1,360 per load. Those circumstances include the

following: (1) the agreement between Universal and CSI specified

that the rate per load would be $1,360 only if the cost of fuel

remained below $2.22 per gallon; (2) in mid February of 2010,

the cost of fuel was approximately $2.76 per gallon; (3) when

Steven Coughlin of Universal spoke with CSI’s Louis Falco on

February 9, to inform CSI of his decision to impose a fuel

surcharge of $204 per load, Falco did not assert that the

parties had a fixed-price contract or deny that the rate per

load was subject to a fuel-cost ceiling;1 and (4) after Coughlin

broached the issue of a fuel surcharge with Falco, Coughlin was

not informed by C S I , until after the last load had been

delivered, that CSI was not going to pay the fuel surcharge

Universal had been including on its invoices. Under those

circumstances, it was reasonable for Universal, at the time it

1 Rather, he attempted to convince Coughlin that the parties had agreed to a fuel-cost ceiling of $3.22 per gallon rather than the $2.22 per gallon stated in Coughlin’s e-mail of May 2009.

4 hauled the final 275 loads of CSI’s job, to expect payment by

CSI of some amount in excess of $1,360 for each of those loads.

CSI responds by arguing that “[t]he evidence submitted at

trial demonstrates that it was unreasonable for Universal to

expect payment of the disputed fuel surcharge.” Def.’s O b j .

(doc. n o . 6 7 ) , at 5 . In support of that argument, CSI notes

evidence that: (1) Falco did not agree to the surcharge; (2)

Coughlin waited until after the job was finished to raise the

issue with CSI’s Len Worden; and (3) CSI’s John Perry was not

authorized to agree to the surcharge. Whether it was reasonable

for Universal to expect payment of the $204-per-load fuel

surcharge is beside the point. The question is whether it was

reasonable for Universal to expect to be paid some amount in

excess of $1,360 for hauling each of the last 275 loads of the

job. And, for the reasons the court has already given, that was

a reasonable expectation.

Because CSI is liable to Universal in quantum meruit, the

only issue that remains is the amount of Universal’s damages.

“In quantum meruit . . . the damages are not measured by the

benefit realized and retained by the defendant, but rather are

based on the value of the services provided by the plaintiff.”

Paffhausen, 708 A.2d at 271 (citing William Mushero, Inc. v .

Hull, 667 A.2d 853, 855 (Me. 1995) (“The measure of recovery is

5 equal to the reasonable value of the services.”); Siciliani v .

Connolly, 651 A.2d 386, 387 (Me. 1994)).

In the opinion of the jury, Universal is entitled to

$13,475. Universal moves for an award in one of three amounts:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2012 DNH 115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-v-csi-concrete-sys-nhd-2012.