George v. Al Hoyt & Sons, Inc.

27 A.3d 697, 162 N.H. 123
CourtSupreme Court of New Hampshire
DecidedJune 2, 2011
Docket2010-015
StatusPublished
Cited by35 cases

This text of 27 A.3d 697 (George v. Al Hoyt & Sons, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George v. Al Hoyt & Sons, Inc., 27 A.3d 697, 162 N.H. 123 (N.H. 2011).

Opinion

Hicks, J.

The plaintiffs, Adelaide V. George d/b/a Homes by George (Homes by George) and Rick George, appeal, and the defendant, Al Hoyt & Sons, Inc., cross-appeals, from rulings of the Trial Court (McHugh, J.). We affirm in part, vacate in part, and remand.

The record supports the following facts and procedural history. Homes by George was the developer of a residential real estate development known as Esther’s Estates in Newton. Rick George, Adelaide George’s son, worked for Homes by George building houses for the development. Esther’s Estates was financed by loans from EML Builders, which were secured by a mortgage on the property.

On December 13,2001, Rick, on behalf of Homes by George, entered into a written contract with the defendant in which the defendant agreed to perform certain work in connection with the Esther’s Estates development, including building a road. The contract specified a total price of $79,278.31.

In January and February 2002, the defendant began work on Esther’s Estates. On February 15, the plaintiffs paid the defendant $10,500 as a deposit for a bridge that was necessary to complete the road and, ultimately, the development of Esther’s Estates. Pursuant to the plaintiffs’ wetlands permit, the bridge had to be installed by July 2002. In June 2002, a disagreement arose between the parties as to whether the contract required the defendant to construct and install the bridge as part of the road construction. That same month, the defendant informed the plaintiffs that it would not construct and install the bridge. Shortly thereafter, the plaintiffs entered into a contract with Concrete Systems, Inc. for the purchase of a bridge for $21,140 but learned that it would take three months for the bridge to be built.

As a result of the delay in installation of the bridge, the plaintiffs returned deposits to two prospective purchasers of homes to be built in Esther’s Estates and voided their respective purchase and sale agreements. The plaintiffs had planned to use the profits from these sales to pay down the mortgage with EML Builders and to continue with the project. However, after learning that the bridge would not be installed in July, Leo LaRochelle, the president of EML Builders, “called the note” because “performance wasn’t being done” and the plaintiffs were not paying him. Consequently on August 22, the plaintiffs transferred Esther’s Estates to EML Builders via a deed in lieu of foreclosure for the amount of $300,000.

In May 2005, the plaintiffs sued the defendant, alleging breach of contract in that the defendant had “failed to complete the road in a good, *127 workmanlike or timely manner, including the acquisition, installation and oversight of the construction of the . . . bridge.” The plaintiffs further alleged that the defendant committed certain unfair and deceptive business practices in violation of the New Hampshire Consumer Protection Act (CPA), see RSA ch. 358-A (2009 & Supp. 2010), and unlawfully removed loam and other top soils from Esther’s Estates. The defendant counterclaimed, alleging that the plaintiffs breached the parties’ agreement by failing to pay amounts due under the contract and that the plaintiffs had been unjustly enriched.

The trial court bifurcated the proceedings to allow a jury to first determine the liability claims. A jury trial was held in May 2008 and the jury returned a verdict in favor of the plaintiffs on all liability claims. The defendant unsuccessfully moved to set aside the jury’s verdict on the plaintiffs’ breach of contract and CPA claims. Thereafter, the trial court notified the parties that it would determine damages on the CPA claims.

In March 2009, a jury trial was held on damages with respect to the breach of contract and unlawful removal of loam claims. The jury awarded the plaintiffs $835,000 for the breach of contract claim and $14,400 for the unlawful removal of loam claim. The defendant filed a motion for remittitur, judgment notwithstanding the verdict and to set aside the damages verdict. The court set aside the jury’s $835,000 award but upheld the $14,400 award. The court then scheduled another jury trial on damages for the plaintiffs’ breach of contract claim.

Shortly thereafter, the plaintiffs filed a motion seeking to have the judge recuse himself from any further proceedings in the case. The plaintiffs also moved for an award of attorney’s fees under the CPA. The trial court denied the motion to recuse and awarded the plaintiffs $5,000 in attorney’s fees for the prosecution of their CPA claim. See RSA 358-A:10 (2009).

In October 2009, another jury trial was held on damages and the jury awarded the plaintiffs $500,000 for their breach of contract claim. The trial court set this award aside and instead awarded the plaintiffs damages of $56,680, comprised of $42,280 as double damages under the CPA for the cost of the bridge and $14,400 for the unlawful removal of loam. The plaintiffs moved to reconsider the court’s damages award and earlier award of attorney’s fees. The court denied the motion as to damages but increased the award of attorney’s fees to $25,000. This appeal followed.

On appeal, the plaintiffs argue that the trial court erred in: (1) vacating the jury’s verdict on damages and substituting its own damages award; (2) calculating damages and attorney’s fees under the CPA; and (3) denying their motion to recuse. The plaintiffs also claim that the trial court improperly communicated with the jury.

*128 The defendant cross-appeals, arguing that: (1) the trial court erred in its application of the CPA to the facts of this case; (2) the plaintiffs are not entitled to any damages for the removal of loam; and (3) the first jury’s breach of contract finding was conclusively against the weight of the evidence. We first address the defendant’s cross-appeal and then turn to the plaintiffs’ appeal.

I. Defendant’s Cross-Appeal

A. CPA Claim

The defendant challenges the trial court’s application of the CPA to the facts of this case. First, the defendant argues that the plaintiffs are not entitled to bring a private cause of action under the CPA because Homes by George was “an ‘experienced’ development company . . . and not a ‘consumer.’ ” To address this argument, we must interpret the CPA, which is a question of law that we review de novo. Green Mt. Realty Corp. v. Fifth Estate Tower, 161 N.H. 78, 82 (2010).

“On questions of statutory interpretation, this court is the final arbiter of the intent of the legislature as expressed in the words of a statute considered as a whole.” Milford Lumber Co. v. RCB Realty, 147 N.H. 15, 17 (2001) (quotation omitted). We first look to the language of the statute itself, and, if possible, construe that language according to its plain and ordinary meaning. State v. Merrill, 160 N.H. 467, 471 (2010). In conducting our analysis we will focus on the statute as a whole, not on isolated words or phrases. Milford Lumber Co., 147 N.H. at 17. We interpret legislative intent from the statute as written and will not consider what the legislature might have said or add language that the legislature did not see fit to include.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TJN, Inc. v. Abigail Mathes Pitou
Supreme Court of New Hampshire, 2024
John Doe v. P Trustees of Dartmouth College
2024 DNH 032 (D. New Hampshire, 2024)
Richard E. Clark, Esq. v. Ryan Carrier & a.
Supreme Court of New Hampshire, 2021
Seacoast Helicopters, LLC v. Kevin Beaulieu
Supreme Court of New Hampshire, 2020
Dawn Cate & a. v. Linda Hemingway & a.
Supreme Court of New Hampshire, 2020
Aleksandr Rudyak & a. v. Bearfoot Creek, LLC & a.
Supreme Court of New Hampshire, 2020
Michael Weeden v. Shawn O'Brien
Supreme Court of New Hampshire, 2018
Eugene Gaudreau & a. v. Wal-Mart Stores, Inc. & a.
Supreme Court of New Hampshire, 2017
Fat Bullies Farm, LLC v. Lori Devenport & a.
164 A.3d 990 (Supreme Court of New Hampshire, 2017)
Moulton v. Bane, et al.
2016 DNH 090 (D. New Hampshire, 2016)
Moulton v. Bane
2016 DNH 058 (D. New Hampshire, 2016)
Peter Saunders & a. v. Town of Kingston
Supreme Court of New Hampshire, 2015
Gallagher v Funeral Source et al.
2015 DNH 033 (D. New Hampshire, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
27 A.3d 697, 162 N.H. 123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-v-al-hoyt-sons-inc-nh-2011.