Guyotte v. O'NEILL

958 A.2d 939, 157 N.H. 616
CourtSupreme Court of New Hampshire
DecidedAugust 20, 2008
Docket2007-183
StatusPublished
Cited by11 cases

This text of 958 A.2d 939 (Guyotte v. O'NEILL) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guyotte v. O'NEILL, 958 A.2d 939, 157 N.H. 616 (N.H. 2008).

Opinion

Galway, J.

The plaintiffs, Howard Joseph Guyotte and Louise A Guyotte, appeal, and the defendants, Michael O’Neill and Bay Shores Building and Remodeling, LLC, cross-appeal, from a jury verdict in Superior Court (Smukler, J.) in favor of the defendants. We affirm.

The record supports the following facts. In 2004, the plaintiffs contracted with the defendants to construct a house in Laconia. The project was financed by a construction loan from Centrix Bank (bank). By the terms of the loan agreement with the bank, money was to be disbursed to the plaintiffs in lump sums at various intervals to pay for the construction as work was completed. To receive each disbursement, the plaintiffs were required to submit to the bank a “Builder’s Waiver of Mechanic’s Lien” (lien waiver) signed by the defendants. A total of six lien waivers were submitted to the bank.

*618 Each lien waiver stated, in relevant part:

The undersigned states that as of the date of this waiver all invoices and payments due from the owner for this property have been paid except for the following [invoice.]
The undersigned hereby releases any and all lien, or claim or right to lien, on said above described building and premises under the statutes of the State of New Hampshire relating to mechanics liens, on account of labor or materials or both, furnished by the undersigned to the account of said property for the period through the date of_(if not filled in presumed to be the date of the waiver) with the exception of the above stated outstanding invoice(s). >
Upon payment of the outstanding invoice(s) the undersigned releases the owner and Centrix Bank & Trust of and from any and all claims for monies due and owing [as] of the date of this waiver, and all rights to assert a Mechanic Lien pursuant to New Hampshire law, relative to the same. The undersigned states that this waiver shall be enforceable, and that we have not been induced by any party to execute this Waiver, and the facts as asserted in it are voluntarily given under pains and penalty [of] perjury.

Except for different dates and amounts requested, the lien waivers were identical. The plaintiffs paid the defendants pursuant to the first five lien waivers, the last of which was dated February 14,2005. The plaintiffs admit that the defendants were not paid pursuant to the sixth lien waiver dated April 25, 2005.

In May 2005, due to a disagreement with the plaintiffs, the defendants ceased work and the plaintiffs hired other contractors to complete the job. In November 2005, the plaintiffs sued the defendants, alleging that they had failed to build the house according to the specifications and that they had failed to complete work required by the parties’ contract. The defendants counterclaimed, alleging that the plaintiffs had breached the parties’ agreement by failing to pay amounts due under the contract, and that the plaintiffs had been unjustly enriched.

At the close of evidence, the plaintiffs orally moved to dismiss the defendants’ claims, arguing that the defendants had not complied with discovery requests and that the evidence was insufficient to support their claims. Additionally, the plaintiffs contended that the defendants’ claims were barred by the lien waivers. The trial court denied the plaintiffs’ claim that the evidence was insufficient to go to the jury, but did not address *619 whether the defendants had complied with the plaintiffs’ discovery requests. The trial court also declined to rule on the plaintiffs’ argument regarding the lien waivers, but allowed the plaintiffs to address it later by memorandum. Subsequently, the jury found for the defendants and awarded them $43,422.84 in damages. The plaintiffs filed various post-trial motions including: a renewal of their oral motion to dismiss; motions for judgment notwithstanding the verdict (JNOV); motions to set aside the verdict; and a motion for remittitur. The trial court remitted the damage award to $35,324.00, but otherwise denied the plaintiffs’ motions. After ensuing motions for clarification and reconsideration were denied, the parties cross-appealed.

As several of the plaintiffs’ arguments on appeal relate to the lien waivers, we address them together. The plaintiffs first contend that the trial court erred in denying their motions to dismiss, for JNOV, and to set aside the verdict, which all argued that the defendants’ claims were barred by the lien waivers. According to the plaintiffs, the lien waivers act as general releases both of the right to assert mechanic’s liens and any claims by the defendants for “any and all monies due as of the date of the release.” More specifically, the plaintiffs argue that the defendants are barred from asserting their claims for any “extra” items — that is, any items beyond those covered in the parties’ construction contract — which were not invoiced, as well as for work performed pursuant to the contract that predated the effective date of the fifth lien waiver. Because the defendants’ claims are barred by the lien waivers, the plaintiffs contend, the trial court erred in denying their motions to avoid or overturn the jury’s verdict in favor of the defendants. The defendants counter that the plaintiffs’ interpretation of the lien waivers is erroneous, because the use of the phrase “relative to the same” in the lien waivers prevents them from acting as general releases. Alternatively, the defendants argue that if the plaintiffs’ reading is correct, the evidence at trial demonstrated that their claims were not barred by the lien waivers.

Though we review each motion ruled upon by the trial court under a different standard, we conclude that under any of the applicable standards, the plaintiffs do not prevail. The standard of review for a motion to dismiss (or nonsuit) is to take the evidence presented and determine if, viewed most favorably to the non-moving party, it establishes a prima facie case. Renovest Co. v. Hodges Development Corp., 135 N.H. 72, 75 (1991); see also Morrill v. Tilney, 128 N.H. 773, 777 (1986). Denying the motion is proper if the defendants’ allegations are reasonably susceptible of a construction that would permit recovery. Bohan v. Ritzo, 141 N.H. 210, 212 (1996).

Similarly, a party is entitled to JNOV only when the sole reasonable inference that may be drawn from the evidence, which must be viewed in *620 the light most favorable to the nonmoving party, is so overwhelmingly in favor of the moving party that no contrary verdict could stand. Blouin v. Sanborn, 155 N.H. 704, 706 (2007). In deciding whether to grant the motion, the trial court cannot weigh the evidence or inquire into the credibility of witnesses. Id. If the evidence adduced at trial is conflicting, or if several reasonable inferences may be drawn, the court must deny the motion. Id. Our standard of review of a trial court’s denial of a motion for JNOV is extremely narrow and we will not overturn the trial court’s decision absent an unsustainable exercise of discretion. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fraser Engineering v IPS-Integrated
2018 DNH 067 (D. New Hampshire, 2018)
Wyle v. Lees
33 A.3d 1187 (Supreme Court of New Hampshire, 2011)
George v. Al Hoyt & Sons, Inc.
27 A.3d 697 (Supreme Court of New Hampshire, 2011)
Akwa Vista, LLC v. NRT, INC.
8 A.3d 97 (Supreme Court of New Hampshire, 2010)
Brousseau v. Superintendent
1 A.3d 596 (Supreme Court of New Hampshire, 2010)
Haniffy v. NHSP Warden
2010 DNH 090 (D. New Hampshire, 2010)
Forsberg v. Kearsarge Regional School District
999 A.2d 278 (Supreme Court of New Hampshire, 2010)
Huard v. Town of Pelham
986 A.2d 460 (Supreme Court of New Hampshire, 2009)
New Hampshire Ball Bearings, Inc. v. Jackson
969 A.2d 351 (Supreme Court of New Hampshire, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
958 A.2d 939, 157 N.H. 616, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guyotte-v-oneill-nh-2008.