Fraser Engineering v IPS-Integrated

2018 DNH 067
District Court, D. New Hampshire·Decided March 27, 2018·No. 17-cv-102-JD·Published·Cited by 1 cases

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Fraser Engineering Company, Inc.

v. Case No. 17-cv-102-JD Opinion No. 2018 DNH 067

IPS-Integrated Project Services, LLC and Lonza Biologics, Inc.

O R D E R

Fraser Engineering Company, Inc., alleges that IPS-

Integrated Project Services, LLC, and Lonza Biologics, Inc., wrongfully withheld payments for subcontract work Fraser performed on a construction project. IPS served as general contractor on the project, which involved the design and construction of a building in Portsmouth, New Hampshire. Lonza owned the building. Fraser entered into a subcontract with IPS to provide mechanical and plumbing services as part of the project.

The sole issue before the court is whether Fraser may perfect a mechanics lien on the property. 1 Fraser moved for, and was granted, an ex parte attachment in state court. The

1 Arbitration will resolve the merits of the parties’

dispute. See Jan. 11, 2018 Order (doc. no. 40) at 8-9 (DiClerico, J.) (ordering the parties to proceed to arbitration).

defendants objected to that attachment before removing the case to this court. They then filed an assented-to motion for a hearing on their objections pursuant to N.H. Rev. Stat. Ann. (RSA) § 511-A:3. The district judge granted that motion and directed Fraser to refile its complaint and its motion for ex parte attachment and the defendants to refile their objections to that motion. Mar. 22, 2017 Order (doc. no. 8) at 2-3 (DiClerico, J.). The district judge designated the undersigned magistrate judge, pursuant to 28 U.S.C. § 636(b)(1)(A), to consider and resolve the defendants’ objections. 2 The court held a hearing on the objections in May 2017. At that time, the court granted the parties leave to file post- hearing memoranda and statements of fact. Following the hearing, Fraser moved to compel the defendants to produce the prime contract governing the project. The defendants objected, and the district judge referred the motion to the undersigned.

2 The undersigned indicated in a previous order that the mechanics lien issue had been referred for report and recommendation. In doing so, the undersigned misconstrued under which subsection of 28 U.S.C. § 636 the district judge designated this matter for review. Section 636(b)(1)(A) allows a district judge, with certain exceptions not presently applicable, to “designate a magistrate judge to hear and determine any pretrial matter pending before the court . . . .” The undersigned may therefore resolve the present matter by way of written order. See, e.g., Osgood v. Kent, No. 11-cv-477-SM, 2011 WL 6740411, at *1 (D.N.H. Dec. 21, 2011) (magistrate judge resolved mechanics lien issue via order); H.E. Contracting v. Franklin Pierce Coll., 360 F. Supp. 2d 289, 290 (D.N.H. 2005) (same).

The court initially deferred ruling on the motion to compel based on the parties’ representation that they would mediate this matter in November 2017. When that mediation did not occur, however, the court conducted an in camera review of the prime contract and granted the motion to compel in part. Following that ruling, the parties submitted a statement of undisputed facts, statements of disputed facts, post-hearing memoranda, and replies. The mechanics lien issue is therefore ripe for resolution.

Having reviewed the parties’ pre- and post-hearing filings and their arguments at the hearing, the court overrules the defendants’ objections to Fraser’s attachment. As discussed below, the defendants have not demonstrated that Fraser failed to timely perfect the lien, that Fraser waived the lien, or that the lien amount should be reduced. Fraser is accordingly entitled to a mechanics lien on the property in the amount of $4,917,122.02.

I. Standard of Review

Absent an applicable federal statute, “the law of the state where the [district] court is located” governs attachment proceedings. Fed. R. Civ. P. 64(a), (b). Under New Hampshire law, any person who performs labor or furnishes materials in the amount of $15 or more when erecting or repairing a building

pursuant to a contract with the owner of that building has a lien on the materials furnished and on the building. See RSA 447:2, I. RSA 447:5 extends that right to subcontractors performing work or furnishing materials pursuant to a subcontract, so long as certain notice requirements are met. The lien continues for 120 days after the work is performed or the materials are furnished, unless payment is made. See RSA 447:9. The lien may be secured beyond the 120-day period by attaching the subject property during the lien period. RSA 447:10.

RSA 511-A, which governs pre-judgment attachment procedures, applies to proceedings to secure mechanics liens under RSA 447. See Chagnon Lumber Co. v. Stone Mill Const. Corp., 124 N.H. 820, 823 (1984). Under RSA 511-A:8, a court may attach property ex parte if a plaintiff establishes probable cause of its basic right to recovery and the amount of the lien. RSA 511-A:8, III; Chagnon, 124 N.H. at 823. When a court grants an ex parte attachment, the party against which the attachment is made may object and is entitled to a prompt hearing. RSA 511-A:8.

Though a burden-shifting framework typically applies during attachment hearings, see RSA 511-A:3, several courts, including at least two in this district, have declined to follow this framework when analyzing mechanics liens, see Osgood v. Kent,

No. 11-cv-477-SM, 2011 WL 6740411, at *3 (D.N.H. Dec. 21, 2011); H.E. Contracting v. Franklin Pierce Coll., 360 F. Supp. 2d 289, 291 (D.N.H. 2005); W. Side Dev. Grp. v. D’Amour, No. 04-C-018 (N.H. Super. Mar. 24, 2004); Consolidated Elec. Distrib., Inc. v. SES Concord, Co., No. 89-C-571/579 (N.H. Super. Nov. 21, 1989). Those courts instead analyze whether a plaintiff has met its burden under RSA 511-A:8, which a defendant may rebut by challenging the plaintiff’s basic right to recovery, the lien amount, or the notice provisions. See Osgood, 2011 WL 6740411, at *3; H.E. Contracting, 360 F. Supp. 2d at 291. Both parties agreed at the hearing that the RSA 511-A:3 framework does not apply in the present context. See Hearing Trans. (doc. no. 29) at 71-74. Accordingly, the court will analyze this matter under the standard articulated by those courts that have found RSA 511-A:3 inapplicable.

II. Background 3

Lonza leases a building on property in Portsmouth, New Hampshire. Doc. no. 43 ¶ 1. On September 8, 2014, Lonza and IPS entered into an agreement for the design, procurement, and construction of a manufacturing facility on that property. Id. ¶ 2. That agreement was subsequently amended on July 19, 2016.

3 The following background is derived from the parties’

statement of undisputed facts and the evidence in the record.

Id. 4 Pursuant to these documents, Lonza was required to pay IPS for “the cost of trade labor including the indirect costs, overhead and profit for all [s]ubcontractors and equipment necessary for construction.” See Prime Contract § 17.16 On October 9, 2015, IPS notified Fraser that it intended to award Fraser a subcontract to perform mechanical piping and plumbing work on the project. Doc. no. 43 ¶ 5. Fraser and IPS executed a formal subcontract on February 11, 2016, whereby Fraser agreed to furnish all labor, services, materials, tools, equipment, supplies, and any other items necessary or incidental to perform the plumbing and mechanical scope of work on the project. Id. ¶¶ 3, 6. The original subcontract sum was $5,312,100. Id. ¶ 7.

The subcontract contained specific procedures for performing extra work. See, e.g., doc. no. 12-1 at 5, 71. Though Fraser did not always follow those procedures, IPS approved change orders totaling $1,535,350.87. See doc. nos. 12-2, 12-3. IPS rejected four change orders totaling $317,461.17. See doc. no. 12 ¶ 12; doc. no. 12-5.

In December 2015, Fraser and IPS began having discussions about Fraser potentially accelerating its work on the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Fraser Engineering v IPS-Integrated, 2018 DNH 067 (D.N.H. 2018).

2018 DNH 067 (Fraser Engineering v IPS-Integrated) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related