Metropolitan Pier & Exhibition Authority Ex Rel. Pitt-Des Moines, Inc. v. Mc3d, Inc.

56 F. Supp. 2d 984, 1999 U.S. Dist. LEXIS 1979, 1999 WL 102787
CourtDistrict Court, N.D. Illinois
DecidedFebruary 19, 1999
Docket97 C 2126
StatusPublished
Cited by2 cases

This text of 56 F. Supp. 2d 984 (Metropolitan Pier & Exhibition Authority Ex Rel. Pitt-Des Moines, Inc. v. Mc3d, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metropolitan Pier & Exhibition Authority Ex Rel. Pitt-Des Moines, Inc. v. Mc3d, Inc., 56 F. Supp. 2d 984, 1999 U.S. Dist. LEXIS 1979, 1999 WL 102787 (N.D. Ill. 1999).

Opinion

MEMORANDUM AND ORDER

MORAN, Senior District Judge.

Pitt-Des Moines, Inc. brought this two-count complaint alleging that Metropolitan Pier & Exhibition Authority (MPEA), Mc3D, Inc. (the design/builder), American Home Assurance Company, St. Paul Fire & Marine Insurance Company, Seaboard Surety Company, Federal Insurance Company, United States Fidelity & Guaranty Company, Fidelity and Deposit Company of Maryland, and The Aetna Casualty & Surety Company (collectively known as the sureties) are liable for $15 million in damages as the result of a breach of PDM’s subcontract with McCormick Place Contractors (McPC).

*986 BACKGROUND

MPEA is a municipal corporation created pursuant to the Illinois Metropolitan Pier and Exposition Authority Act, 70 ILCS 210 et. seq., for the purpose of developing the McCormick Place expansion (the project). On December 23, 1991, MPEA hired Mc3D, Inc. (the design/builder) by written contract (the design/build contract) to design and develop the project. Under section 10 of the design/build contract Mc3D was required to obtain a payment bond that would guaranty payment for all materials used and labor performed under the contract, including that of subcontractors. Mc3D obtained this bond from the sureties listed above in the amount of $350,000,000. Mc3D engaged McPC as the general contractor on the project, and McPC in turn hired numerous subcontractors to complete the work. By written agreement (the PDM/McPC subcontract) Pitt-Des Moines agreed to supply and install the structural steel.

During construction, MPEA, McPC and Mc3D made numerous modifications to the project plans. In August 1993, McPC began to send PDM these design changes, requesting that PDM return a cost-impact analysis detailing any additional expenses PDM might incur as a result. Although the PDM/McPC subcontract required that PDM provide a detailed notice of such additional expenses within ten days of such requests, PDM instead sent a letter in response to each change proposal, stating that its costs would be affected but that it could not provide an estimate of the total amount of damage within the notice period because the frequency of the design changes prevented PDM from making a final estimate of its additional costs. PDM claims that it did not itemize or calculate its total cost for the additional work because it assumed that it would reach a total lump sum price for the extras with the contractor after the various design changes giving rise to the modifications had stopped, as the parties had previously done in making a $15 million amendment to the subcontract with Change Order Three.

At the same time PDM was submitting these letters, it was executing the monthly mechanic’s lien waivers (lien waivers) and contractor’s affidavits that were required for it to receive progress payments for the work already completed. The lien waivers state, in essence, that PDM has no outstanding claim for materials or labor furnished prior to the waiver’s date. Similarly, by executing the contractor’s affidavits PDM affirmed that it had no legal or equitable claim for material and labor costs outstanding at the time of execution. The last set of such documents that PDM executed was on November 30, 1995, by which time PDM admits it had completed 96.7% of its performance, and it is undisputed that PDM has been paid for all of the work described in those documents to that date.

Several months after PDM’s performance was completed, PDM gave McPC a detailed explanation of the costs it incurred as a result of the design changes and requested an additional 15 million dollars compensation. McPC refused to pay, stating that PDM had failed to comply with the subcontract’s notice provisions which required PDM to provide a detailed request for extra compensation within a limited time period after the design change giving rise to the modified cost. PDM then brought this action against McPC, Mc3D and Mc3D’s sureties.

Previously McPC moved for summary judgment, arguing that PDM’s failure to comply with the subcontract’s notice provisions barred any later claim for additional compensation. 1 PDM defended on the grounds that during the course of the subcontract’s performance PDM and McPC, by their conduct, modified the contractual *987 notice requirement agreeing, instead, that PDM would provide a detailed accounting of its expenses after the flow of the design changes had stopped. This court found that the facts surrounding PDM’s and McPC’s agreement were materially in dispute and consequently denied McPC’s motion for summary judgment. Now, Mc3D and the sureties have moved for summary judgment.

ANALYSIS

In their motion for summary judgment Mc3D and the sureties argue that the clear and unambiguous lien waivers and contractor’s affidavits that PDM executed prevent PDM from seeking to recover for materials and labor provided prior to the date of the last waiver, November 30, 1995. In response, PDM makes several arguments. First, it argues that a mechanic’s lien waiver does not waive a subcontractor’s right to make a claim on the surety bond, but instead only prevents it from attaching a hen to the property or project at issue. Second, PDM argues that it is the customary practice in the Chicago construction industry for lien waivers to apply only to the work actuahy stated in the waiver. In other words, although the waivers typically state that the subcontractor is giving up its right to obtain a lien for any work performed prior to the waiver’s date, PDM argues that the subcontractor in fact only gives up its right to seek a lien for any amount for the work listed in the wavier. Thus, according to PDM’s position, a subcontractor executing such waivers retains the right to pursue compensation for any work performed prior to the waiver’s date but not stated in the waiver itself, and consequently PDM’s waivers did not apply to any additional or extra work that PDM had performed prior to the date of each waiver, but which had not been described or paid for at the time of the waiver.

The lien waivers that PDM executed on a monthly basis state:

[PDM] waive[s] and release[s] any and all hen or claim of, or right to, hen, under the statutes of the State of Illinois, relating to the mechanics’ hens, with respect to and on said above-described premises, and the improvements thereon, and on the material, fixtures, apparatus or machinery furnished, and on the moneys, funds or other considerations due or to become due from the owner, on account of labor, services, material, fixtures, apparatus or machinery, furnished to this date by the undersigned for the above-described premises.

The contractor’s affidavits provide in part:

[PDM affirms:] That all waivers are true, correct and genuine and delivered unconditionally and that there is no claim either legal or equitable to defeat the validity of said waivers .... [A]nd that the items mentioned include all labor and material required to complete said work according to plans and specifications ....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fraser Engineering v IPS-Integrated
2018 DNH 067 (D. New Hampshire, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
56 F. Supp. 2d 984, 1999 U.S. Dist. LEXIS 1979, 1999 WL 102787, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metropolitan-pier-exhibition-authority-ex-rel-pitt-des-moines-inc-v-ilnd-1999.