Mangiardi v. Dewey

2013 DNH 069
District Court, D. New Hampshire·Decided April 30, 2013·No. 12-CV-481-JD·Published·Cited by 2 cases

Opinion

Mangiardi v . Dewey 12-CV-481-JD 04/30/13 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Mangiardi Brothers Trucking, Inc.

v. Civil N o . 12-cv-481-JD Opinion N o . 2013 DNH 069 Dewey Environmental, LLC, et a l .

O R D E R

Mangiardi Brothers Trucking, Inc. (“Mangiardi”) brought suit against Dewey Environmental, LLC (“Dewey”); Francis Harvey and Sons, Inc. (“Francis Harvey”); Babcock and Wilcox Construction Co., Inc. (“Babcock”); and Berlin Station, LLC (“Berlin Station”) alleging claims arising out of unpaid invoices for Mangiardi’s services in hauling hazardous waste from a construction site. Babcock and Berlin move to dismiss the complaint. Mangiardi objects to the motions.

Background

In the fall of 2011, Berlin Station hired Babcock as its general contractor for the construction of a “biomass energy plant” (the “Project”). Berlin Station owns the property upon which the Project was being constructed (the “Construction Site”).

In November 2011, Babcock entered into an agreement with Francis Harvey, under which Francis Harvey agreed to perform certain site work for the Project. Francis Harvey subcontracted with Dewey to perform hazardous waste removal on the Project.

Dewey subsequently contacted and subcontracted with Mangiardi to haul the hazardous waste materials from the Construction Site. Dewey agreed to pay Mangiardi $115 per ton of waste hauled and payment was due within fourteen days after the date of an invoice. The terms of the agreement were confirmed through an email between Dewey and Mangiardi. Mangiardi alleges that Dewey discussed the terms of the agreement with Francis Harvey.

Mangiardi began performing the services required under the contract with Dewey on December 1 , 2011. On December 5 , 2011, Mangiardi submitted its first invoice to Dewey in the amount of $20,513.75. Mangiardi received a check from Francis Harvey for the full amount of the invoice on December 1 2 , 2011.

Mangiardi continued to perform the services required under the contract and submitted five more invoices to Dewey, totaling $128,751.70. When payment for the first of the five invoices was not made within fourteen days, Mangiardi contacted both Dewey and Francis Harvey. Each promised that a payment would be made shortly.

On January 9, 2012, Dewey wired $50,000 to Mangiardi.

Despite contacting Dewey and Francis Harvey on many occasions since then, Mangiardi has not received any further payment from either company.

After being unsuccessful in obtaining payment from Dewey and Francis Harvey, Mangiardi contacted Babcock to request payment of the outstanding invoices. Mangiardi alleges that Babcock stated that it had paid Francis Harvey in full for the portion of work performed by Mangiardi and, therefore, would not pay Mangiardi

the money Mangiardi alleged it was owed.

Mangiardi subsequently contacted Cate Street Capital (“Cate Street”), which it believed to be the owner of the Construction Site, to request payment of its invoices. Cate Street said that it was not the owner of the Construction Site and refused to make any payments to Mangiardi.1

Standard of Review

When considering a motion to dismiss under Federal Rule of Civil Procedure 12(b)(6), the court must determine whether the facts alleged, when taken as true and in the light most favorable

1 Mangiardi alleges Cate Street formed and owned Berlin Station so that Berlin Station could take title to the Construction Site.

to the plaintiff, state a claim on which relief can be granted. Rederford v . U.S. Airways, Inc., 589 F.3d 3 0 , 35 (1st Cir. 2009). Under the notice pleading standard of Federal Rule of Civil Procedure 8(a)(2), a plaintiff need provide only a short and plain statement that provides enough facts “‘to raise a right to relief above the speculative level . . . .’” Ocasio-Hernandez v . Fortuno-Burset, 640 F.3d 1 , 12 (1st Cir. 2011) (quoting Bell Atl. Corp. v . Twombly, 550 U.S. 5 4 4 , 555 (2007)). The court takes the well-pled allegations as true, views all of the facts in the light most favorable to the non-moving party, and determines whether the complaint alleges facts to support a claim “that is plausible on its face.” Downing v . Glove Direct LLC, 682 F.3d 1 8 , 22 (1st Cir. 2012) (internal citation and quotation marks omitted); see also Ashcroft v . Iqbal, 556 U.S. 6 6 2 , 678-79 (2009).

Discussion

Mangiardi brings claims against Dewey and Francis Harvey for breach of contract, breach of the covenant of good faith and fair dealing, and violation of New Hampshire’s Consumer Protection Act, RSA 358-A:2. It also brings claims for unjust enrichment, quantum meruit, and restitution against all the defendants.

Berlin Station and Babcock move to dismiss the claims against them. They argue that a third-tier subcontractor such as Mangiardi (an entity who subcontracts with a sub-subcontractor) cannot recover against an owner or a general contractor under a quasi-contract theory. They also contend that Mangiardi’s claims for unjust enrichment, quantum meruit, and restitution, should be considered together as one claim.

“New Hampshire cases do not clearly differentiate between theories of unjust enrichment and quantum meruit.” Eastern Elec. Corp. v . FERD Const. Inc., 2005 WL 3447957, at *3 n.1 (D.N.H. Dec. 1 5 , 2005)(citing cases). Certain New Hampshire cases, however, appear to set forth slightly different elements for the claims and address them separately. See, e.g., Gen. Insulation C o . v . Eckman Constr., 159 N.H. 6 0 1 , 611-12 (2010) (analyzing claims of unjust enrichment and quantum meruit). Therefore, the court will assume, without deciding, that unjust enrichment and quantum meruit are separate claims under New Hampshire law and addresses them separately. Restitution, however, is not a separate cause of action under New Hampshire law and is only a remedy for unjust enrichment. See, e.g., Ellis v . Candia Trailers and Snow Equip., Inc., 58 A.3d 1164, 1168 (2012) (“In New Hampshire, a plaintiff is entitled to restitution for unjust

enrichment” if the plaintiff proves his claim.) (internal citation and quotation marks omitted). 2 The New Hampshire Supreme Court has not specifically addressed claims of unjust enrichment or quantum meruit asserted by a third-tier subcontractor against a general contractor, or addressed certain arguments advanced by Mangiardi in its claims against Berlin Station. “Where no authoritative decision from the state court of last resort resolves an issue of state substantive law, [the court] must predict, as best [it] can, that court’s resolution of the issue . . . .” Kunelius v . Town of Stow, 588 F.3d 1 , 9 (1st Cir. 2009). “In that endeavor, the federal court may seek guidance from a wide range of sources, including but not limited to ‘analogous state court decisions, persuasive adjudications by courts of sister states, learned treatises, and public policy considerations identified in state decisional law.’” Rathbun v . Autozone, Inc., 361 F.3d 6 2 , 66

2 Mangiardi contends that the court should deny Berlin Station’s and Babcock’s motions because they repeat the arguments made in their motions to dismiss the original complaint, which the court denied. The court, however, denied Berlin Station’s and Babcock’s motions to dismiss the original complaint as moot because Mangiardi filed an amended complaint under Federal Rule of Civil Procedure 15(a). The court did not consider the merits of the arguments in Berlin Station’s and Babcock’s motions to dismiss the original complaint. The motions which are the subject of this order address the allegations in the amended complaint, which is the operative complaint, and the court considers those arguments below.

(1st Cir. 2004) (quoting Blinzler v . Marriott Int’l, Inc., 81 F.3d 1148, 1151 (1st Cir. 1996)).

Free access — add to your briefcase to read the full text and ask questions with AI

Mangiardi v. Dewey, 2013 DNH 069 (D.N.H. 2013).

2013 DNH 069 (Mangiardi v. Dewey) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related