Mangiardi v. Dewey

2013 DNH 069
CourtDistrict Court, D. New Hampshire
DecidedApril 30, 2013
Docket12-CV-481-JD
StatusPublished
Cited by2 cases

This text of 2013 DNH 069 (Mangiardi v. Dewey) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mangiardi v. Dewey, 2013 DNH 069 (D.N.H. 2013).

Opinion

Mangiardi v . Dewey 12-CV-481-JD 04/30/13 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Mangiardi Brothers Trucking, Inc.

v. Civil N o . 12-cv-481-JD Opinion N o . 2013 DNH 069 Dewey Environmental, LLC, et a l .

O R D E R

Mangiardi Brothers Trucking, Inc. (“Mangiardi”) brought suit

against Dewey Environmental, LLC (“Dewey”); Francis Harvey and

Sons, Inc. (“Francis Harvey”); Babcock and Wilcox Construction

Co., Inc. (“Babcock”); and Berlin Station, LLC (“Berlin Station”)

alleging claims arising out of unpaid invoices for Mangiardi’s

services in hauling hazardous waste from a construction site.

Babcock and Berlin move to dismiss the complaint. Mangiardi

objects to the motions.

Background

In the fall of 2011, Berlin Station hired Babcock as its

general contractor for the construction of a “biomass energy

plant” (the “Project”). Berlin Station owns the property upon

which the Project was being constructed (the “Construction

Site”). In November 2011, Babcock entered into an agreement with

Francis Harvey, under which Francis Harvey agreed to perform

certain site work for the Project. Francis Harvey subcontracted

with Dewey to perform hazardous waste removal on the Project.

Dewey subsequently contacted and subcontracted with

Mangiardi to haul the hazardous waste materials from the

Construction Site. Dewey agreed to pay Mangiardi $115 per ton of

waste hauled and payment was due within fourteen days after the

date of an invoice. The terms of the agreement were confirmed

through an email between Dewey and Mangiardi. Mangiardi alleges

that Dewey discussed the terms of the agreement with Francis

Harvey.

Mangiardi began performing the services required under the

contract with Dewey on December 1 , 2011. On December 5 , 2011,

Mangiardi submitted its first invoice to Dewey in the amount of

$20,513.75. Mangiardi received a check from Francis Harvey for

the full amount of the invoice on December 1 2 , 2011.

Mangiardi continued to perform the services required under

the contract and submitted five more invoices to Dewey, totaling

$128,751.70. When payment for the first of the five invoices was

not made within fourteen days, Mangiardi contacted both Dewey and

Francis Harvey. Each promised that a payment would be made

shortly.

2 On January 9, 2012, Dewey wired $50,000 to Mangiardi.

Despite contacting Dewey and Francis Harvey on many occasions

since then, Mangiardi has not received any further payment from

either company.

After being unsuccessful in obtaining payment from Dewey and

Francis Harvey, Mangiardi contacted Babcock to request payment of

the outstanding invoices. Mangiardi alleges that Babcock stated

that it had paid Francis Harvey in full for the portion of work

performed by Mangiardi and, therefore, would not pay Mangiardi

the money Mangiardi alleged it was owed. Mangiardi subsequently contacted Cate Street Capital (“Cate Street”), which it believed to be the owner of the Construction Site, to request payment of its invoices. Cate Street said that it was not the owner of the Construction Site and refused to make any payments to Mangiardi.1

Standard of Review

When considering a motion to dismiss under Federal Rule of

Civil Procedure 12(b)(6), the court must determine whether the

facts alleged, when taken as true and in the light most favorable

1 Mangiardi alleges Cate Street formed and owned Berlin Station so that Berlin Station could take title to the Construction Site.

3 to the plaintiff, state a claim on which relief can be granted.

Rederford v . U.S. Airways, Inc., 589 F.3d 3 0 , 35 (1st Cir. 2009).

Under the notice pleading standard of Federal Rule of Civil

Procedure 8(a)(2), a plaintiff need provide only a short and

plain statement that provides enough facts “‘to raise a right to

relief above the speculative level . . . .’” Ocasio-Hernandez v .

Fortuno-Burset, 640 F.3d 1 , 12 (1st Cir. 2011) (quoting Bell Atl.

Corp. v . Twombly, 550 U.S. 5 4 4 , 555 (2007)). The court takes the

well-pled allegations as true, views all of the facts in the

light most favorable to the non-moving party, and determines

whether the complaint alleges facts to support a claim “that is

plausible on its face.” Downing v . Glove Direct LLC, 682 F.3d

1 8 , 22 (1st Cir. 2012) (internal citation and quotation marks

omitted); see also Ashcroft v . Iqbal, 556 U.S. 6 6 2 , 678-79

(2009).

Discussion

Mangiardi brings claims against Dewey and Francis Harvey for

breach of contract, breach of the covenant of good faith and fair

dealing, and violation of New Hampshire’s Consumer Protection

Act, RSA 358-A:2. It also brings claims for unjust enrichment,

quantum meruit, and restitution against all the defendants.

4 Berlin Station and Babcock move to dismiss the claims

against them. They argue that a third-tier subcontractor such as

Mangiardi (an entity who subcontracts with a sub-subcontractor)

cannot recover against an owner or a general contractor under a

quasi-contract theory. They also contend that Mangiardi’s claims

for unjust enrichment, quantum meruit, and restitution, should be

considered together as one claim.

“New Hampshire cases do not clearly differentiate between

theories of unjust enrichment and quantum meruit.” Eastern Elec.

Corp. v . FERD Const. Inc., 2005 WL 3447957, at *3 n.1 (D.N.H.

Dec. 1 5 , 2005)(citing cases). Certain New Hampshire cases,

however, appear to set forth slightly different elements for the

claims and address them separately. See, e.g., Gen. Insulation

C o . v . Eckman Constr., 159 N.H. 6 0 1 , 611-12 (2010) (analyzing

claims of unjust enrichment and quantum meruit). Therefore, the

court will assume, without deciding, that unjust enrichment and

quantum meruit are separate claims under New Hampshire law and

addresses them separately. Restitution, however, is not a

separate cause of action under New Hampshire law and is only a

remedy for unjust enrichment. See, e.g., Ellis v . Candia

Trailers and Snow Equip., Inc., 58 A.3d 1164, 1168 (2012) (“In

New Hampshire, a plaintiff is entitled to restitution for unjust

5 enrichment” if the plaintiff proves his claim.) (internal

citation and quotation marks omitted). 2

The New Hampshire Supreme Court has not specifically

addressed claims of unjust enrichment or quantum meruit asserted

by a third-tier subcontractor against a general contractor, or

addressed certain arguments advanced by Mangiardi in its claims

against Berlin Station. “Where no authoritative decision from

the state court of last resort resolves an issue of state

substantive law, [the court] must predict, as best [it] can, that

court’s resolution of the issue . . . .” Kunelius v . Town of

Stow, 588 F.3d 1 , 9 (1st Cir. 2009). “In that endeavor, the

federal court may seek guidance from a wide range of sources,

including but not limited to ‘analogous state court decisions,

persuasive adjudications by courts of sister states, learned

treatises, and public policy considerations identified in state

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2013 DNH 069, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mangiardi-v-dewey-nhd-2013.