Reynolds Metals Company v. Westinghouse Electric Corporation

758 F.2d 1073, 40 U.C.C. Rep. Serv. (West) 1702, 1985 U.S. App. LEXIS 29178
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 29, 1985
Docket83-2689
StatusPublished
Cited by27 cases

This text of 758 F.2d 1073 (Reynolds Metals Company v. Westinghouse Electric Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reynolds Metals Company v. Westinghouse Electric Corporation, 758 F.2d 1073, 40 U.C.C. Rep. Serv. (West) 1702, 1985 U.S. App. LEXIS 29178 (5th Cir. 1985).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

Westinghouse Electric Corporation challenges a judgment for damages entered following a jury’s determination that Westinghouse breached a contract with Reynolds Metals Company. Westinghouse argues that Reynolds’ contract claim was barred by disclaimers of warranty, that in any event there was no breach, and that Reynolds failed to give the required notice before suing on its claim. We reject these arguments but conclude that Westinghouse’s challenge to the damage award itself is well-founded because the amounts awarded included consequential damages not recoverable under the parties’ agreement. We therefore affirm the jury’s finding of breach but remand for a new trial on the issue of damages.

I

-1-

In early 1970, Reynolds solicited bids for the sale of certain electrical equipment needed by its San Patricio plant in Corpus Christi, Texas. Westinghouse responded to the solicitation with a series of bids that were finalized in a full proposal to Reynolds offering to manufacture the desired equipment — a large electric transformer unit — for approximately $250,000.00. This price included not only the machinery itself, but also a “competent Westinghouse service engineer” who was to be present “for two full days ... during equipment check or startup.” The proposal warranted the machinery for one year from the date of shipment and made those warranty terms the exclusive remedy of the purchaser; that is, Westinghouse disclaimed all warranties not expressed in its proposal and excluded any liability to Reynolds for “special, indirect, incidental or consequential damages” that might be sustained in the event of a breach of the sales contract or warranty. 1

Reynolds accepted the Westinghouse proposal with a purchase order whose warranty terms conflicted to some extent with those offered by Westinghouse. The proposal and purchase order were in all other respects compatible, however, and Westinghouse acknowledged the order and began work.

*1075 The only significant addition to the parties’ agreement was made in January of 1971, while manufacture of the transformer unit was still in progress. Reynolds determined that the equipment would not be put into operation until well after shipment and therefore requested an extension of the one-year warranty. Westinghouse agreed and extended the warranty for an additional twelve months “based upon storage during the first twelve months, ... [for] a net total price of $2,637.00.” The warranty extension at this price was made dependent upon several conditions, including “inspection of all equipment prior to start-up, and start-up supervision by the Westinghouse Industrial Systems Department.” The cost of such supervision was to be borne by Reynolds in addition to the warranty extension price, with credit to be given Reynolds for cost of the two days of start-up assistance provided for in the original agreement.

The equipment was shipped in July of 1971 and was stored in a protected location at the San Patricio plant until its installation in the spring of 1973. Reynolds hired a local electrical contractor to perform most of this work under the supervision of a Reynolds engineer, Ken Younger, and installation was substantially completed by late February. At that point Westinghouse engineer David Reindl arrived at the plant for final inspection and start-up of the equipment. Reindl had a degree in electrical engineering, but apparently lacked extensive experience with transformer units of the type being installed, and more importantly, considered it his responsibility to “technically assist” rather than to “supervise” Reynolds in the installation of the purchased equipment. Despite the alleged confusion over his responsibilities, Reindl worked with Younger over the following two months until most problems with the unit were resolved, and the equipment was placed in service in late April.

Although no deficiencies in Reindl’s performance of his duties were evident at the time he rendered his services, he apparently failed to install properly the system for detection of ground current in the transformer. Both grounding pads on the transformer were connected to the grounding grid, but only one of the grounding cables was routed through the alarm system that was supposed to alert the equipment operator when significant amounts of current were being grounded from the transformer. So connected, according to Reynolds’ experts, internal problems in the equipment that might otherwise be made apparent by the ground alarm system could go undetected. This error was compounded when Reindl followed Westinghouse guidelines in setting the sensitivity on the alarm for detection of ground current. Given the configuration of the grounding pads, that setting was assertedly too low to detect amounts of ground current that might otherwise indicate a problem with the transformer.

The equipment had an expected life-span of twenty to thirty years, but on April 11, 1974, less than a year after it was put into service, the transformer unit failed. The problem, according to Reynolds’ experts, was two-fold. The failure itself was the result of the assertedly improper design of a compression ring in the transformer. That design allegedly caused continuous burning in the transformer from the time of installation and somewhat more serious burning on April 11, when excessive power demands were allegedly made on the transformer. The ground detection system described above contributed to the problem, according to Reynolds’ experts, in that some of the low-level burning, and certainly the high-level burning on April 11, should have been detected by a properly installed ground alarm system before significant damage was done.

The transformer was shipped to Westinghouse’s repair facility in Houston immediately after the April 11 incident, and at about the same time Reynolds made a warranty claim to Westinghouse based on the failure of the equipment. Westinghouse denied the claim on the ground that its *1076 warranty had expired, 2 and Reynolds paid the repair bill on the equipment, which totalled $109,284.82. Reynolds did not otherwise level a claim against Westinghouse on the basis of this incident until it filed suit in state court in April 1976. Westinghouse timely removed to federal court based on diversity of citizenship.

-2-

Reynolds alleged causes of action in negligence, strict liability, contract, and warranty, but because the negligence and strict liability claims were barred by the applicable statutes of limitation, the case proceeded to trial under theories of warranty and contract. The primary dispute was whether Westinghouse’s warranty disclaimers and limitations on liability, see supra n. 1, applied, 3 and in the event that they did, whether warranty protection commenced on the date of shipment of the equipment in 1971 or upon completion of the installation of the equipment in 1973. See supra n. 2.

At the close of all the evidence the district court granted an instructed verdict in favor of Westinghouse on nearly all issues. The court substantially agreed with Westinghouse’s version of the formation of the contract, and applied Tex.Bus.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baker Hughes Proc & Pipel Svc v. UE Compression, L
938 F.3d 661 (Fifth Circuit, 2019)
BCC Merchant Solutions, Inc. v. Jet Pay, LLC
129 F. Supp. 3d 440 (N.D. Texas, 2015)
Spectro Alloys Corp. v. Fire Brick Engineers Co.
52 F. Supp. 3d 918 (D. Minnesota, 2014)
In re Heartland Payment Systems, Inc.
834 F. Supp. 2d 566 (S.D. Texas, 2011)
Berge Helene Ltd. v. GE Oil & Gas, Inc.
830 F. Supp. 2d 235 (S.D. Texas, 2011)
Powell Electrical Systems, Inc. v. Hewlett Packard Co.
356 S.W.3d 113 (Court of Appeals of Texas, 2011)
Enpro Systems, Ltd. v. Namasco Corp.
382 F. Supp. 2d 874 (S.D. Texas, 2005)
RA MACKIE & CO., LP v. Petrocorp Inc.
329 F. Supp. 2d 477 (S.D. New York, 2004)
Metro National Corp. v. Dunham-Bush, Inc.
984 F. Supp. 538 (S.D. Texas, 1997)
Ganz v. Lyons Partnership, L.P.
961 F. Supp. 981 (N.D. Texas, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
758 F.2d 1073, 40 U.C.C. Rep. Serv. (West) 1702, 1985 U.S. App. LEXIS 29178, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reynolds-metals-company-v-westinghouse-electric-corporation-ca5-1985.