Powell Electrical Systems, Inc. v. Hewlett Packard Co.

356 S.W.3d 113, 2011 WL 1598758
CourtCourt of Appeals of Texas
DecidedAugust 12, 2011
Docket01-09-00876-CV
StatusPublished
Cited by49 cases

This text of 356 S.W.3d 113 (Powell Electrical Systems, Inc. v. Hewlett Packard Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Powell Electrical Systems, Inc. v. Hewlett Packard Co., 356 S.W.3d 113, 2011 WL 1598758 (Tex. Ct. App. 2011).

Opinion

OPINION

JANE BLAND, Justice.

Crossed wires caused an on-site electrical transformer to blow, necessitating repairs and the use of a temporary trans *116 former while the blown transformer was out of commission. The manufacturing plant owner sued its electrical services company for breach of contract and breach of warranty. The trial court rendered judgment on the jury’s verdict favoring the owner. On appeal, Powell Electrical Systems, Inc. (“Powell”) asserts that (1) all of the damages awarded by the jury are contractually barred consequential damages, (2) because the damages are barred, Hewlett Packard Company (“HP”) is not entitled to attorney’s fees as a prevailing party, and (8) the liability questions that the trial court submitted erroneously conflate proper and improper theories of liability. In a cross-appeal, HP argues that the jury’s damages and attorney’s fees findings impermissibly reduce the awards to fifteen percent less than the amount conclusively established by the evidence and that it is entitled to appellate attorney’s fees.

We conclude that (1) most of the damages the jury awarded are direct damages, but the damages relating to loss of use are consequential damages, (2) the jury charge is proper, (3) HP did not establish the full amount of its damages as a matter of law and thus is not entitled to an increased award, (4) the jury’s take-nothing award for appellate attorney’s fees is not supported by legally sufficient evidence, and (5) in light of our reduction of HP’s damages, the jury’s award for attorney’s fees at trial must also be remanded. We therefore reverse the trial court’s judgment with respect to the award of damages pursuant to the jury findings on damage elements (d) and (e), relating to costs for loss of use, and reform the judgment accordingly. We reverse the trial court’s judgment with respect to the award of attorney’s fees at trial and on appeal and remand those issues. We affirm the trial court’s judgment in all other respects.

Background

HP owns a manufacturing facility in Houston with its own power substation. The substation uses a two-transformer system to power the facility. Powell designs, manufactures and installs electrical equipment. HP contracted with Powell to perform breaker retrofitting services at the substation. This process required Powell to remove breaker cables from the transformers’ breaker cabinets and then reconnect them when the work was completed. Powell failed to document how the breaker cables were placed before removing them and unintentionally crossed certain breaker cables when it reconnected them. The cross-phased breaker cables caused one of HP’s dual transformers, transformer B, to fail. As a result, HP incurred costs to repair transformer B and to obtain a temporary transformer for use while the repairs were made. HP brought this suit against Powell to recover for these costs.

After a trial on the merits, the jury found in favor of HP on its breach of contract and breach of express warranty claims against Powell, awarding HP $926,585.98 in damages and $163,526.24 for attorney’s fees. The damages awarded by the jury included the following elements:

(a) fault testing and removal of transformer B: $76,518.03;
(b) disposal of oil from transformer B: $17,067.80;
(c) repair of transformer B: $581,024.20;
(d) cost of temporary transformer less amount for which it was sold: $105,097.26;
(e) installation and testing of temporary transformer: $73,718.15; and
(f) reinstallation of transformer B: $73,160.54.

*117 The jury’s findings on damages and attorney’s fees are approximately fifteen percent less than the amount HP sought at trial, except that the jury refused to award any fees for an appeal. HP asked the trial court to enter judgment on the jury verdict in its favor but to award the full amount it sought. Powell asked the trial court to disregard the jury findings, asserting that the damages found are barred by the limitations of liability in the contract. The trial court denied both parties’ motions and rendered judgment on the verdict, reducing the total damages award to $876,810.61 to account for an offset and awarding pre- and post-judgment interest.

Contractual Limitation on Consequential Damages

Powell contends that the trial court erred in denying Powell’s motions to disregard the jury finding on damages. Powell argues that the damages found by the jury are consequential damages, which are barred under the terms of the parties’ contract. HP responds that the damages are direct damages, rather than consequential damages. The parties agree that their contract bars consequential damages but not direct damages. 1

A. Standard of Review

The dispute between the parties is whether the damages awarded in this case constitute direct or consequential damages under Texas law. We review such questions of law de novo. In re Humphreys, 880 S.W.2d 402, 404 (Tex.1994); Harris Cnty. Appraisal Dist. v. Wilkinson, 317 S.W.3d 763, 766 (Tex.App.-Houston [1st Dist.] 2010, pet. denied). Likewise the interpretation of unambiguous contracts is a legal question that we review de novo. MCI Telecomms. Corp. v. Tex. Utils. Elec. Co., 995 S.W.2d 647, 650-51 (Tex.1999); Atlantic Lloyds Ins. Co. v. Butler, 137 S.W.3d 199, 209 (Tex.App.-Houston [1st Dist.] 2004, pet. denied).

B. Applicable Law on Damages

1. Direct Damages

Direct damages are those damages that flow naturally and necessarily from the breach. Arthur Andersen & Co. v. Perry Equip. Corp., 945 S.W.2d 812, 816 (Tex.1997) (emphasis added). “Direct damages compensate for the loss, damage, or injury that is conclusively presumed to have been foreseen or contemplated by the party as a consequence of his breach of contract or wrongful act.” Id. “By definition, if particular damages are specifically accounted for in the contract, they are direct, not consequential, in nature.” McKinney & Moore, Inc. v. City of Longview, No. 14-08-00628-CV, 2009 WL 4577348, *5 (Tex.App.-Houston [14th Dist.] Dec. 8, 2009, pet. denied) (mem. op.) (citing Boyer, Inc. v. Trinity River Auth. of Tex., 279 S.W.3d 354, 358 (Tex.App.-Fort Worth 2008, pet. denied)); 2 see also Tennessee *118 Gas Pipeline Co. v. Technip USA Corp., No. 01-06-00535-CV, 2008 WL 3876141, at *8-9 (Tex.App.-Houston [1st Dist.] Aug. 21, 2008, pet. denied) (mem. op.).

Examples of direct damages can be found in our decision in Tennessee Gas Pipeline. In that case, a pipeline owner, Tennessee Gas Pipeline (“TGP”), sought to recover damages for Technip’s delayed and defective construction work on a pipeline.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SM Energy Co. v. Colgate Prod., LLC
New Mexico Court of Appeals, 2025
Amazon.com Services LLC v. Reginald Grant
Court of Appeals of Texas, 2024
Yue Qi v. Hanyang an and Ruolin Wang
Court of Appeals of Texas, 2021
Miranda Allen v. Ashlee Inman
Court of Appeals of Texas, 2020
in the Estate of Maria L. Raynes
Court of Appeals of Texas, 2019

Cite This Page — Counsel Stack

Bluebook (online)
356 S.W.3d 113, 2011 WL 1598758, Counsel Stack Legal Research, https://law.counselstack.com/opinion/powell-electrical-systems-inc-v-hewlett-packard-co-texapp-2011.