Steel Dynamics Columbus, LLC v. Altech Environment

CourtCourt of Appeals for the Fifth Circuit
DecidedMay 18, 2018
Docket17-60298
StatusUnpublished

This text of Steel Dynamics Columbus, LLC v. Altech Environment (Steel Dynamics Columbus, LLC v. Altech Environment) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steel Dynamics Columbus, LLC v. Altech Environment, (5th Cir. 2018).

Opinion

Case: 17-60298 Document: 00514478140 Page: 1 Date Filed: 05/18/2018

IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT

United States Court of Appeals

No. 17-60298 Fifth Circuit

FILED May 18, 2018

STEEL DYNAMICS COLUMBUS, L.L.C., Lyle W. Cayce Clerk Plaintiff - Appellant Cross-Appellee

v.

ALTECH ENVIRONMENT USA CORPORATION,

Defendant - Appellee Cross-Appellant

Appeals from the United States District Court for the Northern District of Mississippi USDC No. 1:14-CV-124

Before REAVLEY, JONES, and GRAVES, Circuit Judges. PER CURIAM:* This case is about a buyer’s burden to prove damages under Mississippi’s enactment of the Uniform Commercial Code. Steel Dynamics Columbus, L.L.C., purchased two pollution monitoring systems from Altech Environment USA Corp. The systems did not function as expected and Steel sued. After a bench trial, the district court found that Altech breached its express warranty to Steel. The district court awarded some incidental damages

* Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4. Case: 17-60298 Document: 00514478140 Page: 2 Date Filed: 05/18/2018

No. 17-60298 but also found that Steel failed to prove its direct damages and attorneys’ fees. Steel appealed the denial of its direct damages and attorneys’ fees. Altech cross-appealed Steel’s award of incidental damages, arguing the district court should have enforced a contractual limitation on their recovery. We affirm. I. BACKGROUND As its name implies, Steel operates a steel mill in Columbus, Mississippi. The plant is regulated by the Mississippi Department of Environmental Quality (MDEQ). The MDEQ issued Steel a “Title V” permit under the Clean Air Act. 42 U.S.C. § 7401 et seq. To comply with the permit, Steel contracted with Altech for the purchase and installation of two continuous emissions monitoring systems, or “CEMS.” The two systems cost $447,610.20. Three provisions of the parties’ contract are relevant on appeal. First, Altech warranted the CEMS “shall be of good quality and free from defects, latent and patent, in design, materials and workmanship; [and] . . . shall be suitable and sufficient for their specified purpose.” Before trial, the parties stipulated that Altech “understood that [Steel] intended to use the CEMS units to monitor emissions in compliance with the Title V permit.” Second, the contract provided, “If [Altech] breaches its warranty . . . [Altech] shall, at its option, repair and/or replace . . . any of the Goods which breach this Warranty.” The “exclusive” remedy for breach of warranty was repair or replacement. Third, the contract limited damages: “[I]n no event shall [Altech] be liable for special, indirect, incidental, consequential, or punitive damages whether attributable to contract, warranty, tort (including negligence), strict liability or otherwise.” Altech installed the units in January and July of 2011, but they never functioned properly. In June of 2013, the MDEQ issued Steel a Notice of Violation (NOV) for both the inadequate CEMS and the failure to report malfunctions. Following the NOV, Steel self-reported 11 other violations, and 2 Case: 17-60298 Document: 00514478140 Page: 3 Date Filed: 05/18/2018

No. 17-60298 the MDEQ assessed a fine of $135,000. With the existing CEMS still unable to function properly, Steel contracted with a third party to install a different CEMS. Steel received over $23,000 in credit from the third party for equipment initially provided by Altech. Steel sued Altech for breach of express warranty (among other things) and sought damages for: (1) the full purchase price of the Altech CEMS (direct damages); (2) incidental costs sunk while trying to fix the Altech CEMS (incidental damages); (3) the $135,000 fine; and (4) attorneys’ fees incurred in dealing with environmental regulatory issues (consequential damages). 1 Following a three-day bench trial, the district court found that the “recurrent malfunctions” of Altech’s CEMS rendered them “unsuitable and insufficient for the specified purpose,” in breach of the contract’s express warranty. The district court found, however, that Steel could not recover its direct damages because it failed to prove the value of the CEMS as received. Further, the district court denied Steel its attorneys’ fees, finding that Steel failed to attribute its fees or the fine to Altech’s breach. Ultimately, the court awarded Steel $83,320.27 in incidental damages for Steel’s efforts to fix the CEMS. Steel appealed only from the district court’s denial of direct damages (the purchase price) and attorneys’ fees. Altech cross-appealed, arguing that the district court should have enforced the contract’s limitation on consequential and incidental damages. 2 II. DISCUSSION A. Standard of Review

1Importantly, Steel did not seek attorneys’ fees under a fee-shifting statute. Instead, Steel characterized its fees as consequential damages. 2 Altech also asserts two conditional issues in its cross-appeal. Because we affirm the district court’s judgment, we do not address those conditional issues. 3 Case: 17-60298 Document: 00514478140 Page: 4 Date Filed: 05/18/2018

No. 17-60298 Following a bench trial, “findings of fact are reviewed for clear error and legal issues are reviewed de novo.” In re Mid-S. Towing Co., 418 F.3d 526, 531 (5th Cir. 2005). “A finding is clearly erroneous if it is without substantial evidence to support it, the court misinterpreted the effect of the evidence, or this court is convinced that the findings are against the preponderance of credible testimony.” Becker v. Tidewater, Inc., 586 F.3d 358, 365 (5th Cir. 2009). B. The Purchase Price The general measure of damages for breach of warranty is “the difference at the time and place of acceptance between the value of the goods accepted and the value they would have had if they had been as warranted.” MISS. CODE ANN. § 75-2-714(2). This requires proof of the value as warranted and as accepted. See § 75-2-714(2). The burden of proof is on the buyer seeking damages. Gast v. Rogers-Dingus Chevrolet, 585 So. 2d 725, 731 (Miss. 1991) (“This burden cannot be met by mere conjecture or inferences unsupported by adequate evidence.”). The district court found that it was “far from clear that the CEMS were worthless.” However, Steel asserts that it proved the CEMS were worthless as accepted because they were unrepairable. Steel relies on Fedders Corp. v. Boatright, 493 So. 2d 301 (Miss. 1986), to argue that, under Mississippi law, proof that a good is unrepairable constitutes proof of worthlessness at the time of acceptance. Such an argument is contrary to the language of Fedders. Fedders dealt with a broken heating system. Id. at 303. There, the court stated, “If the heat pump could not be repaired and was worthless, the [plaintiff] under § 75-2-714 would have been entitled to a refund of the purchase price.” Id. at 309. Contrary to Steel’s assertion, “could not be repaired and was worthless” is not the same as “the goods were worthless because they could not be repaired.” (emphasis added). While it is true that an unrepairable 4 Case: 17-60298 Document: 00514478140 Page: 5 Date Filed: 05/18/2018

No. 17-60298 good may also be worthless, it does not follow that such a good is always worthless.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Becker v. Tidewater, Inc.
586 F.3d 358 (Fifth Circuit, 2009)
L. Glen Riley v. Ford Motor Company
442 F.2d 670 (Fifth Circuit, 1971)
In re Mid-South Towing Co.
418 F.3d 526 (Fifth Circuit, 2005)
Massey-Ferguson, Inc. v. Evans
406 So. 2d 15 (Mississippi Supreme Court, 1981)
Royal Lincoln-Mercury Sales v. Wallace
415 So. 2d 1024 (Mississippi Supreme Court, 1982)
Fedders Corp. v. Boatright
493 So. 2d 301 (Mississippi Supreme Court, 1986)
Wall v. Swilley
562 So. 2d 1252 (Mississippi Supreme Court, 1990)
Gast v. Rogers-Dingus Chevrolet
585 So. 2d 725 (Mississippi Supreme Court, 1991)
Frierson v. Delta Outdoor, Inc.
794 So. 2d 220 (Mississippi Supreme Court, 2001)
Ammons v. Wilson & Co.
170 So. 227 (Mississippi Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
Steel Dynamics Columbus, LLC v. Altech Environment, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steel-dynamics-columbus-llc-v-altech-environment-ca5-2018.