United States Ex Rel. Mobile Premix Concrete, Inc. v. Santa Fe Engineers, Inc.

515 F. Supp. 512, 29 Cont. Cas. Fed. 81,753, 1981 U.S. Dist. LEXIS 9597
CourtDistrict Court, D. Colorado
DecidedMay 29, 1981
DocketCiv. A. 79-K-404
StatusPublished
Cited by20 cases

This text of 515 F. Supp. 512 (United States Ex Rel. Mobile Premix Concrete, Inc. v. Santa Fe Engineers, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Mobile Premix Concrete, Inc. v. Santa Fe Engineers, Inc., 515 F. Supp. 512, 29 Cont. Cas. Fed. 81,753, 1981 U.S. Dist. LEXIS 9597 (D. Colo. 1981).

Opinion

ORDER

KANE, District Judge.

This is an action to recover the balance for materials supplied by use plaintiff for construction of barracks complex in Port Carson, Colorado. Jurisdiction is grounded in 40 U.S.C. §§ 270a-c, commonly known as the Miller Act. Defendant Garcia Concrete, Inc., has cross-claimed against defendant Santa Fe Engineers, Inc., and its surety The Travelers Indemnity Co. for any amounts it may be found liable to use plaintiff for and for other labor and materials supplied. It is before me on motions for summary judgment by defendant Garcia and defendants Santa Fe and Travelers.

The undisputed facts are as follows. Use plaintiff seeks to recover sums owed pursuant to a November 17, 1975 subcontract with Garcia for the supply of concrete. Garcia has paid all amounts due under the terms of this contract. However use plaintiff claims the contract prices were based on the assumption that the concrete would be delivered in 1976 and the very beginning of 1977, and the project completed in January or February of 1977. The bulk of the concrete was actually delivered in 1977 and 1978, and the project was not completed until April 20, 1978. Use plaintiff attempted to raise the price in a letter to Garcia dated February 23, 1977. Garcia responded by letter on March 15, 1977, that it would not be able to pay the higher prices unless it could obtain the additional amounts from Santa Fe, the contractor on the project. Delivery began and continued until the project was completed. The additional amounts were billed, but not paid, and upon completion of the project this litigation ensued.

Summary judgment, pursuant to Fed.R.Civ.P. 56(c) is a drastic remedy, Jones v. Nelson, 484 F.2d 1165, 1168 (10th Cir. 1973), by which movants are given the opportunity to pierce the allegations in the pleadings. However, “[t]he power to pierce the flimsy transparent factual veil should be temperately and cautiously used lest abuse reap nullification.” Avrick v. Rockmont Envelope Co., 155 F.2d 568, 571 (10th Cir. 1946). Summary judgment is appropriate only where there exists no genuine issue of material fact. Adickes v. S. H. Kress & Co., 398 U.S. 144, 157-59, 90 S.Ct. 1598, 1608-09, 26 L.Ed.2d 142 (1970); Luckett v. Bethlehem Steel Corp., 618 F.2d 1373, 1383 (10th Cir. 1980). As a matter of law, the movant must show entitlement to summary disposition beyond all reasonable doubt. Norton v. Liddel, 620 F.2d 1375, 1381 (10th Cir. 1980).

In order to determine the propriety of summary judgment I must construe all pleadings, affidavits, and depositions liberally in favor of the party against whom the motion is made. Id.; Accord, Otteson v. United States, 622 F.2d 516, 519 (10th Cir. 1980); Commercial Iron & Metal Co. v. Bache & Co., 478 F.2d 39 (10th Cir. 1973). Summary judgment is not a substitute trial by affidavit. Ando v. Great Western Sugar Co., 475 F.2d 531 (10th Cir. 1973). Under the rule, no margin exists for disposition of factual issues, and it does not serve as a substitute trial of the case nor require the parties to dispose of the litigation through affidavits. Commercial Iron & Metal Co. v. Bache & Co., 478 F.2d at 41. Where different inferences can be drawn from conflicting affidavits, depositions and pleadings, summary judgment should not be granted. United States v. Diebold, Inc., 369 U.S. 654, 82 S.Ct. 993, 8 L.Ed.2d 176 (1962); Romero v. Union Pac. Railroad, 615 F.2d 1303, 1309 (10th Cir. 1980).

For the reasons that follow, I hold that there are no genuine issues of fact and defendants are entitled to judgment against use plaintiff as a matter of law. Therefore, summary judgment is granted.

The most interesting question presented is whether federal law controls over state law in Miller Act cases. Some circuits have held that as to subcontracts, state law controls when construction of the Miller Act is not in issue and the United States is not a party to the subcontract. *515 Other circuits have held that federal law controls in all actions under the Miller Act. These cases are collected in U. S. for the Use of Building Rentals Corp. v. Western Casualty & Surety Co., 498 F.2d 335, 338 (9th Cir. 1974). The tenth circuit has not decided either way. See, Burgess Const. Co. v. M. Morrin & Son Co., Inc., 526 F.2d 108 (10th Cir. 1975), cert. denied, 429 U.S. 866, 97 S.Ct. 176, 50 L.Ed.2d 146 (1976). However, it seems clear that when there is a distinction between federal and state substantive law, federal law controls and the interstices may be filled by incorporating state law. U. S. v. Algernon Blair, Inc., 479 F.2d 638 (4th Cir. 1973), 26 ALR Fed 741; U. S. for the Use of Astro Cleaning & Packaging Corp. v. Jamison Co., 425 F.2d 1281 (6th Cir. 1970).

In the instant case Colorado law determines the terms of the contract, while federal law determines whether, and to what extent, the claim is cognizable under the Miller Act. See, U. S. for the Use of Aucoin Electric Supply Co. v. Safeco Ins. Co. of America, 555 F.2d 535 (5th Cir. 1977).

Defendants contend that any modification of the agreement to supply concrete must be in writing to satisfy the provision of the Uniform Commercial Code, 1973 C.R.S., § 4-1-101 et seq. C.R.S. § 4-2-209 requires modification of a written contract to be in writing if the contract as modified falls within the provision of the statute of frauds, at C.R.S. § 4r-2-201. The statute of frauds requires contracts for the sale of goods for $500 or more to be in writing and signed by the party against whom enforcement is sought. However, § 4-2-201(3)(c) provides that a contract which does not satisfy the formal requirements of the statute, but is valid in other respects, is enforceable with respect to goods for which payment has been made and accepted or which have been received and accepted. Therefore, the formal requirements of the statute do not apply to the goods in this case and neither the contract nor its modification need be in writing. It still must be decided whether the parties agreed to a change in price.

Under Colorado law, use plaintiff cannot unilaterally modify the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lenon v. St. Paul Mercury Insurance
136 F.3d 1365 (Tenth Circuit, 1998)
United States v. Sun Engineering Enterprises, Inc.
817 F. Supp. 1009 (D. Puerto Rico, 1993)
Jelen and Son, Inc. v. Bandimere
801 P.2d 1182 (Supreme Court of Colorado, 1990)
W.S.A. Inc. v. Stratton
680 F. Supp. 375 (S.D. Florida, 1988)
Alvarez v. Insurance Co. of North America
667 F. Supp. 689 (N.D. California, 1987)
Guilford Pattern Works, Inc. v. United Bank of Boulder
655 F. Supp. 378 (D. Colorado, 1987)
Dargon v. Kirk
650 F. Supp. 737 (D. Colorado, 1986)
Northwest Central Pipeline Corp. v. Mesa Petroleum Co.
643 F. Supp. 280 (D. Colorado, 1986)
Simmons v. Prudential Insurance Co. of America
641 F. Supp. 675 (D. Colorado, 1986)
Luna v. Bowen
641 F. Supp. 1109 (D. Colorado, 1986)
Munoz v. Prudential Insurance Co. of America
633 F. Supp. 564 (D. Colorado, 1986)
United States v. Excellair, Inc.
637 F. Supp. 1377 (D. Colorado, 1986)
City of Northglenn v. Chevron U.S.A., Inc.
634 F. Supp. 217 (D. Colorado, 1986)
United States v. Insurance Company Of North America
695 F.2d 455 (Tenth Circuit, 1982)
General Federal Construction, Inc. v. D. R. Thomas, Inc.
451 A.2d 1250 (Court of Special Appeals of Maryland, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
515 F. Supp. 512, 29 Cont. Cas. Fed. 81,753, 1981 U.S. Dist. LEXIS 9597, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-mobile-premix-concrete-inc-v-santa-fe-engineers-cod-1981.