Hendry Corporation v. American Dredging Company and Federal Insurance Company

318 F.2d 299
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 22, 1963
Docket19791
StatusPublished
Cited by8 cases

This text of 318 F.2d 299 (Hendry Corporation v. American Dredging Company and Federal Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hendry Corporation v. American Dredging Company and Federal Insurance Company, 318 F.2d 299 (5th Cir. 1963).

Opinion

WOODBURY, Chief Judge *

Hendry Corporation, Hendry hereinafter, a Florida corporation, in its own name and in the name of the United States for its use and benefit, brought an action in the United States District Court for the Southern District of Florida in four counts against American Dredging Company and its insurer, Federal Insurance Company, American and Federal [hereinafter, Pennsylvania and New Jersey corporations respectively, on a dredging contract. Counts I and III are predicated on the Miller Act. 40 U.S.C. § 270a et seq. Jurisdiction over the other two counts in which Federal was not named as a defendant is alleged to rest upon diversity of citizenship and amount in controversy, Title 28 U.S.C. § 1332(a) (1), and are to recover for breach of contract and in quantum meruit. After trial without a jury the court below entered judgment for Hendry and for the United States for Hendry’s benefit against both defendants for an amount they admitted that they owed but not for the amount Hendry claimed, and Hendry in its own name filed timely notice of appeal.

At this point we come face to face with the appellees’ motion to dismiss the appeal for lack of appellate jurisdiction for the reason that Hendry appealed in its own name instead of in the name of *301 the United States for Hendry’s use and benefit. The argument is that since actions under the Miller Act must be brought in the name of the United States for the use of the person suing, so also must every appeal by an aggrieved plaintiff below be brought in the name of the United States for his use. Wherefore it is said that failure to appeal in that form requires dismissal for lack of appellate jurisdiction.

It is, of course, true that under § 270b (b) of 40 U.S.C. every suit instituted under the Miller Act must be brought in the name of the United States for the use of the person suing. The statute is silent, however, as to the form required for taking appeals and no authority on that point has been cited to us or otherwise come to our attention. We must embark on our own analysis.

While the statute requires that suits under the Act must be brought in the name of the United States for the use of the person suing, there is no requirement that leave to sue must first be obtained from the United States or even that it must be given notice of suit. Therefore counsel for Hendry properly acted on his own initiative in instituting the present action in which counsel for the United States entered no appearance, signed no papers and in no way participated, and the costs and expenses of which Hendry would have to bear if unsuccessful, for the statute expressly provides that the United States shall not be held liable for the payment of any costs or expenses of suit. Moreover the notice of appeal is captioned in the same terms as the complaint and, like the complaint, is signed only by counsel for Hendry. The only defect is the failure to describe Hendry as a use plaintiff in the body of the notice of appeal. This impresses us as merely a formal irregularity which, in the absence of any suggestion of prejudice, ought not to affect appellate jurisdiction. The appellees’ motion to dismiss is denied.

The appellant says that it has no major quarrel with the district court’s findings of fact which are as follows.

In February 1959 American entered into a direct or prime contract with the United States Army Corps of Engineers for the enlargement by dredging of the Alafia River channel and turning basin in Tampa Harbor, Florida. In connection with that contract it, as principal, and Federal, as surety, furnished the bond required by the Miller Act conditioned upon the payment by American of all persons supplying labor and materials in the prosecution of the work provided for in the contract.

At the time American submitted its bid for the prime contract its dredge “Philadelphia,” with which it hoped to do the work, was engaged in dredging operations in Pensacola, Florida, and would not be available to start the Alafia River project within the time required. Wherefore, before American submitted its bid for the prime contract, it approached Hendry, which had a dredge immediately available, and the two tentatively agreed that if American should be the successful bidder Hendry would immediately undertake part of the job as a subcontractor, and they also tentatively agreed as to how the work should be divided between them. The court found, it said on uncontradicted evidence, “that it was the expressed intention of the parties that the work to be performed by each under the subcontract should be so divided as to give each party an opportunity to earn 50% of the total estimated price which was to be paid under the prime contract.” And, in furtherance of this understanding, American and Hendry agreed to submit a proposed line or station to serve as the dividing line of the work to be performed by each under the prime contract. 1 Hendry submitted Station 137 as its proposed dividing line and American as its proposed dividing line submitted Station 132 plus 22 feet.

*302 The court below found that neither of the proposed stations would divide the work equally on the basis of the dollar value of the work to be done. 2 It found that under American’s proposal the dollar value of the work to be done in the eastern section was $151,514 greater than the work to be done in the western section and that under Hendry’s proposal the dollar value of the work to be done in the western section was $22,414 greater than the work to be done in the eastern section. 3 However, the court below found: “The parties, in spite of this discrepancy in the dollar value of the work then known to be available on each side of the dividing line proposed by them, respectively, expressed their willingness to do the work on either side for one-half of the money which could be earned under the prime contract.”

We are somewhat at a loss to understand the pertinence of this finding, for undoubtedly neither party held out for its position. The court below found that after discussion the parties agreed to make the dividing line the mid-point between the two proposed stations, which were 476 feet apart, that is to say, at Station 134 plus 61 feet, and then drew lots to determine which side of the line each would dredge. Hendry drew the easterly side and American drew the westerly side. The court found that this line also did not divide the dollar value of the work equally inasmuch as the work east of the line was worth $66,548.80 more than the work west of it. Nevertheless the court found that each party agreed to do the portion of the work it had selected by lot for one-half of the total money to be earned under the contract.

At this juncture, on May 8, 1959, American and Hendry entered into the written contract which is the subject matter of this litigation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
318 F.2d 299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hendry-corporation-v-american-dredging-company-and-federal-insurance-ca5-1963.