United States v. Randall & Blake

817 F.2d 1188
Court of Appeals for the Fifth Circuit·Decided June 25, 1987·No. 85-1663·Published·Cited by 44 cases

Opinion

817 F.2d 1188

10 Fed.R.Serv.3d 863, 34 Cont.Cas.Fed. (CCH) 75,295

UNITED STATES of America, for the Use and Benefit of J.R.
CANION, et al., Plaintiffs,
and
Odell Geer Construction Co., Inc., Intervening Plaintiff-Appellee,
v.
RANDALL & BLAKE, and United States Fidelity & Guaranty Co.,
Defendants- Appellants

No. 85-1663.

United States Court of Appeals,
Fifth Circuit.

May 29, 1987.
Rehearing Denied June 25, 1987.

C. Thomas Wesner, Jr., Wesner, Coke, Boyd & Clymer, Dallas, Tex., for Randall & Blake

Clifford F. Altekruse, Christopher J. Simpson, Dallas, Tex., for U.S. Fidelity & Guar. Co.

Stubbeman, McRae, Sealy, Laughlin & Browder, Karen Parker, Rodney W. Satterwhite, Austin, Tex., for Odell Geer Const. Co., Inc.

Appeals from the United States District Court for the Western District of Texas.

Before WISDOM, JOHNSON, and GARWOOD, Circuit Judges.

WISDOM, Circuit Judge:

This appeal involves a suit brought under the Miller Act, 40 U.S.C. Secs. 270a-270d. A supplier for a government construction project brought suit against the general contractor and its surety because the supplier was never paid in full. The district court granted summary judgment in favor of the supplier. The general contractor and its surety appeal on several grounds. We affirm in part and remand in part.

I.

The Miller Act provides protection for subcontractors and their suppliers engaged in federal construction projects. Ordinarily, these persons would be protected by state liens. State liens cannot attach, however, to federal property. To give protection to these persons, the Miller Act requires general contractors engaged on federal projects to furnish a payment bond.1 The Act gives unpaid laborers and materialmen a cause of action on this bond to recover the amounts due them.2

In 1979, the Army Corps of Engineers hired Randall & Blake, Inc. to construct recreational facilities at Granger Lake, Texas. As required by the Miller Act, Randall & Blake secured a payment bond from United States Fidelity & Guaranty Company (USF & G). Randall & Blake subcontracted the paving work to Austin Paving Company. Austin Paving, in turn, contracted with Geer Construction Company to supply asphalt. Between April 23, 1980 and July 22, 1980, Geer Construction supplied 6,202 tons of hot-mix asphalt to Austin Paving for use on the Granger Lake project. Austin Paving paid only some of Geer's invoices, leaving Geer with two unpaid invoices totalling $63,634. On September 9, 1980, Geer Construction sent letter notices to Randall & Blake and USF & G informing them of Geer's potential claim under the Miller Act.

On December 3, 1980, Austin Paving brought a Miller Act suit against Randall & Blake and USF & G, alleging that it had not been paid in full under its contract.3 On May 11, 1981, Geer Construction filed a motion to intervene in the action and to file its complaint seeking recovery on its unpaid invoices. The court did not grant the motion until July 14, 1982. Randall & Blake and USF & G answered the complaint with general denials. On July 19, 1984, the court allowed Geer Construction to file an amended complaint, which set forth more articulately the elements of Geer's Miller Act claim. Randall & Blake and USF & G moved the court to reconsider, arguing that the amended complaint came too late to assert a Miller Act claim. The court denied their motion to reconsider. Geer Construction then filed a motion for summary judgment with supporting affidavits and documentary evidence. The court granted the motion, severed Geer's claim from the remaining claims in the litigation, and entered a final judgment in favor of Geer Construction against Randall & Blake and USF & G for the sum of $63,634 plus prejudgment and postjudgment interest. Randall & Blake and USF & G appeal, alleging numerous errors.4

II.

The appellants, Randall & Blake and USF & G, challenge the timeliness of Geer Construction's Miller Act claim. An action brought under the Act must be commenced within one year from the last day on which the claimant supplied labor or materials for the project.5 We have described the one-year limitation period as a "substantive limitation of the rights conferred by the Act."6 Geer Construction delivered its last load of asphalt on July 22, 1980. The deadline, therefore, for commencing its Miller Act claim passed one year later on July 23, 1981.

Geer Construction filed its motion to intervene on May 11, 1981, within the one year limitation period. Its original complaint was not filed until the court granted the intervention on July 14, 1982, well after the one year period had expired. Another two years passed until Geer filed its amended complaint. The appellants argue that the filing of the amended complaint marked the commencement of Geer's Miller Act claim, because it was the first time that Geer properly pleaded the elements of a Miller Act claim. Specifically, they point out several alleged deficiencies in the original complaint: (1) the failure to bring the action in the name of the United States, (2) the failure to name USF & G as a defendant, (3) the failure to seek recovery on the payment bond, and (4) the failure to allege that the action was based on the Miller Act. The district court held that because the amended complaint set forth no new claims and only corrected technical defects in the original complaint, it related back to the filing of the original complaint under Rule 15(c) of the Federal Rules of Civil Procedure. We agree.

Rule 15(c) provides, in part:

Whenever the claim or defense asserted in the amended pleading arose out of the conduct, transaction, or occurrence set forth or attempted to be set forth in the original pleading, the amendment relates back to the date of the original pleading.

Thus, Geer's amended complaint relates back if it asserts the same claim "set forth or attempted to be set forth " in the original complaint. We find that Geer's original complaint sufficiently set forth a Miller Act claim against Randall & Blake and USF & G to allow the amended complaint to relate back under Rule 15(c).

In its first complaint, Geer Construction specifically alleged that (1) it had provided asphalt to Austin Paving for use on the government project identified in Austin Paving's complaint; (2) it had not been paid on invoices totalling $63,634; and (3) it had complied with the 90-day notice requirements of 40 U.S.C. Sec. 270b (the Miller Act). The complaint did not specifically name USF & G as a defendant nor specifically request relief under the Miller Act. The complaint did, however, incorporate by reference the first five paragraphs of Austin Paving's complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Randall & Blake, 817 F.2d 1188 (5th Cir. 1987).

817 F.2d 1188 (United States v. Randall & Blake) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Yadav v. Agrawal
2025 Tex. Bus. 7 (Texas Business Court, 2025)
Ker'sean Ramey v. Lorie Davis, Director
942 F.3d 241 (Fifth Circuit, 2019)
New Image Glob., Inc. v. United States
2019 CIT 90 (Court of International Trade, 2019)
Handshoe v. Perret
270 F. Supp. 3d 915 (S.D. Mississippi, 2017)
Moore v. Rees
138 F. Supp. 3d 860 (E.D. Kentucky, 2015)
Lynn Noble Hawthorne A/K/A Lynn Hawthorne v. Jack Guenther
461 S.W.3d 218 (Court of Appeals of Texas, 2015)
Vallejo v. Garda CL Southwest, Inc.
56 F. Supp. 3d 862 (S.D. Texas, 2014)
Steven Gerhardson v. Gopher News Company
698 F.3d 1052 (Eighth Circuit, 2012)
Liberty Lincoln-Mercury, Inc. v. Ford Motor Co.
676 F.3d 318 (Third Circuit, 2012)
In Re IFC Credit Corp.
663 F.3d 315 (Seventh Circuit, 2011)
United States v. P. Browne & Associates, Inc.
751 F. Supp. 2d 813 (M.D. North Carolina, 2010)
Miles-Hickman v. David Powers Homes, Inc.
589 F. Supp. 2d 849 (S.D. Texas, 2008)
US Ex Rel. King Mountain v. Rb Constructors, LLC.
556 F. Supp. 2d 1250 (D. Colorado, 2008)
Weber v. Mobil Oil Corp.
506 F.3d 1311 (Tenth Circuit, 2007)
Ahmad v. Furlong
435 F.3d 1196 (Tenth Circuit, 2006)
Handzlik v. United States
93 F. App'x 15 (Fifth Circuit, 2004)
BTA Oil Producers v. MDU Resources Group, Inc.
2002 ND 55 (North Dakota Supreme Court, 2002)