United States ex rel. Yardley Drilling Co. v. Erickson Paving Co.

465 F.2d 396
CourtCourt of Appeals for the Ninth Circuit
DecidedJune 26, 1972
DocketNo. 71-2656
StatusPublished
Cited by7 cases

This text of 465 F.2d 396 (United States ex rel. Yardley Drilling Co. v. Erickson Paving Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Yardley Drilling Co. v. Erickson Paving Co., 465 F.2d 396 (9th Cir. 1972).

Opinion

HAMLEY, Circuit Judge:

This Miller Act (40 U.S.C. §§ 270a-270e) case involves a controversy between a prime contractor and its subcontractor as to the compensation the subcontractor is entitled to under a subcontract item covering drilling and shooting of solid rock, including all line drilling required.

The subcontractor, and use plaintiff, is Yardley Drilling Company, Inc., (Yard-ley). The principal defendants are Erickson Paving Company and Associated Engineers & Contractors, Inc., acting as joint venturers under the name and style of Stewart-Erickson.1 The prime contract was between Stewart-Erickson and the United States Government, through the Department of the Army, Corps of Engineers. The prime contract covers “Grading of Camas Prairie Railroad; Purrington to Schultz Bar, Whitman County, Washington.”

Under its contract with the Government, Stewart-Erickson undertook, among other things, to excavate an estimated 1,610,000 cubic yards of “unclassified” material for a unit price of eighty-four cents a cubic yard. Under Technical Provision 2-02 of the prime contract, “unclassified” included all materials regardless of their nature, including both bedrock and common materials. The quantity — 1,610,000 cubic yards — ■ was the Government’s estimate of the amount of unclassified materials to be excavated within the design prism of the prime contract drawings, based upon the Government’s exploratory data. In Technical Provision 2-01 of the prime contract, however, the Government gave notice that actual quantities for individual reaches might vary widely from the quantities indicated by the exploratory data and the design cross-sections.

In addition to the unclassified excavation within the design prism, paragraph 3 of the General Provisions of the prime contract, entitled “Changes,” obligated Stewart-Erickson to do any additional excavation of unclassified material, within the general scope of the contract, required of it by the Government’s Contracting Officer. Subparagraph (d) of paragraph 3 provided that if any change thereunder caused an increase or decrease in the contractor’s cost, an equitable adjustment would be made.

Stewart-Erickson wished to subcontract out the rock work which might be encountered in excavating the unclassified materials. Preparatory to submitting its bid to the Government, Stewart-Erickson solicited a bid for this rock work from Yardley. On the basis of his examination of the project site and the contract documents including design cross-sections, Virgil N. .Messenger, President of Yardley, gave Stewart-Erickson a telephoned bid of four hundred and ninety thousand dollars. This was on the assumption that, within the design prism, there would be some two hundred and forty-eight thousand lineal feet of line drilling (at one dollar per cubic yard), and about four hundred thousand cubic yards of solid rock to drill and shoot (for two hundred and forty-two thousand dollars). Some twenty minutes after this telephone call, Messenger again telephoned Stewart-Erickson and reduced his proposal to four hundred and fifty thousand dollars plus six thousand dollars for a D-6 bulldozer to be used in the work.

Yardley’s telephoned proposal was neither accepted nor rejected by Stewart-Erickson at that time, but was utilized by it in preparing its bid on the prime contract. After the Government awarded the contract to Stewart-Erickson the latter and Yardley entered into negotia[398]*398tions for the subcontract. Since there was no provision in the prime contract for unit prices on drilling and shooting of solid rock, or on line drilling, it was necessary to relate Yardley’s compensation to the progress payments to be received by Stewart-Erickson on unclassified excavation.

Yardley’s four-hundred-and-fifty-six-thousand-dollar figure would be substantially realized if Stewart-Erickson paid Yardley twenty-eight cents per cubic yard on the estimated 1,610,000 cubic yards within the design prism, and Yard-ley first quoted a twenty-eight cent unit price. After negotiation Yardley reduced this to twenty-seven and a half cents. Thus if there turned out to be exactly 1,610,000 cubic yards of unclassified excavation within the design prism, as estimated, Yardley’s compensation for such rock work would have been $442,750. The negotiated agreement as to Yardley’s compensation was stated as follows in the subcontract:

“Item 1 Excavation, unclassified— Drilling and shooting of solid rock including all line drilling required at TWENTY-SEVEN and ONE-HALF CENTS ($0.275) per cubic yard.”

The unclassified excavation within the design prism exceeded the estimated 1,610,000 cubic yards by thirty-seven cubic yards. This meant that, for its rock work within the design prism, Yardley received $442,760.18, or slightly more than its estimate of $442,750. The actual rock work performed by Yardley within that area, however, was substantially below its estimate of rock work required, upon which Yardley’s bid was based. Only 129,679 lineal feet of line drilling was required, as compared to the two hundred and forty-eight thousand lineal feet Yardley had estimated. Only 331,508 cubic yards of rock were drilled and shot, as compared to Yard-ley’s estimate of four hundred thousand cubic yards.

In addition to the 1,610,037 cubic yards of unclassified excavation Stewart-Erickson did within the design prism, it was ordered by the Corps of Engineers to excavate 377,365 cubic yards of unclassified material outside that area. This additional excavation consisted of: (1) removal of materials below the grades indicated in the contract drawings and design cross-sections, due to encountering unsuitable materials at original excavation depth; (2) the addition of certain drainage ditching ordered by the Corps of Engineers; and (3) removal of materials outside the prism in the course of achieving stability by flattening the slopes shown in the design prism, made necessary because rock was not encountered as close to the surface as expected.

The Corps of Engineers paid Stewart-Erickson at the rate of eighty-four cents per cubic yard for this additional excavation, the price being arrived at as the result of negotiation between the Corps of Engineers and Stewart-Erickson. Yardley did no rock work in connection with this additional excavation. Nor did Stewart-Erickson pay Yardley twenty-seven and one-half cents per cubic yard, or at all, on this additional unclassified excavation. Stewart-Erickson’s position was that this additional excavation was performed outside the scope of the subcontract, and since it did not involve any rock work by Yardley, the subcontract did not contemplate that Yardley would be compensated therefor.

Yardley has not quarreled with this construction of the subcontract insofar as the first two kinds of additional excavation described above are concerned. But, after the subcontract had been completed, Yardley took the position, which it still maintains, that it was entitled to twenty-seven and one-half cents per cubic yard on the 307,376 cubic yards of unclassified excavation involved in the third kind of additional excavation described above (flattening the slopes outside the design prism). Since Yardley did no rock work in connection with this slope flattening, this additional compensation, amounting to $84,528.40 would, [399]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
465 F.2d 396, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-yardley-drilling-co-v-erickson-paving-co-ca9-1972.