David E. Boswell, an Individual, D/B/A Boswell Construction Company, and United Pacific Insurance Company v. G. F. Chapel

298 F.2d 502, 1961 U.S. App. LEXIS 2915
CourtCourt of Appeals for the Tenth Circuit
DecidedDecember 19, 1961
Docket6775_1
StatusPublished
Cited by15 cases

This text of 298 F.2d 502 (David E. Boswell, an Individual, D/B/A Boswell Construction Company, and United Pacific Insurance Company v. G. F. Chapel) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
David E. Boswell, an Individual, D/B/A Boswell Construction Company, and United Pacific Insurance Company v. G. F. Chapel, 298 F.2d 502, 1961 U.S. App. LEXIS 2915 (10th Cir. 1961).

Opinion

CHRISTENSON, District Judge.

In this Miller Act 1 case the sole question is the interpretation of a subcontract which the prime contractor, David E. Boswell, asserts obligated the subcontractor, G. F. Chapel, to pay for “protective services” furnished by the Atchison, Topeka, and Santa Fe Railway Company. The appellant Boswell 2 and the appellee Chapel hereinafter will be referred to by their surnames, and the railway company as such.

This action initially was brought against Boswell by the United States of America for the use and benefit of the railway company to recover the cost of protecting tracks and providing services of watchmen, flagmen, supervisors, and *504 other protective services made necessary by the tunneling and the laying of culverts underneath the railroad pursuant to the contract between Boswell and the Bureau of Reclamation for channelization work on the Rio Grande River in Socorro County, New Mexico. This contract included a provision that the contractor would enter into an agreement with the railway company for such protection of trains while work on the railroad right of way was being carried on.

The trial court entered judgment against Boswell and in favor of the railroad company for the sum of $17,550.34, which judgment is not here in dispute. Chapel had subcontracted with Boswell to furnish specified work and material in the tunneling for, and the installation of, the culverts. By third-party complaint Boswell sought judgment over against Chapel for any amount awarded to the railway company on the theory that Chapel by his subcontract had undertaken not only to do the actual construction and installation work under the railroad, but also to pay for the protective services. It is from the judgment of the trial court dismissing Boswell’s third-party complaint against Chapel that this appeal was taken.

The contract between Boswell and the Bureau of Reclamation required the clearing of trees and vegetation, and various excavation, construction and installations in the channelization of the river. Among the work to be accomplished was the installation of “tunnel liner plate culverts under the railroad tracks.” With respect to this work paragraph 31 of the specifications under the principal contract provided:

“31. Construction of railroad crossings. Crossings under the tracks of the Atchinson, (sic) Topeka, and Santa Fe Railroad * * * shall be constructed in accordance with these specifications and as shown on the drawings. The contractor shall furnish all labor, equipment, and materials; shall construct all necessary false work, cribbing, or temporary construction required for the support of the railroad tracks and embankment during the construction of the crossings, and shall provide-the services of any watchmen or flagmen required by the railroad company during the period of time required for the construction of the portion of the work on railroad right-of-way. All of the operations of the-contractor in constructing the portion of the work under the tracks of' the railroad shall be subject to the approval of the railroad company. Before beginning work on railroad right-of-way, the contractor shall enter into any agreements required and shall furnish any bonds and/or public liability and property damage-insurance required by the railroad company for its protection * * *
“All operations and payments for constructing the crossings shall be in accordance with the provisions of' paragraph 61. No direct payment will be made for furnishing bonds and/or insurance or for providing the services of watchmen or flagmen, and the cost thereof shall be included in the price bid for constructing the crossings.”

The subcontract between Boswell and Chapel is dated December 10, 1957, about a month after execution of the principal contract. Chapel agreed to, “do and perform for the Party of the Second Part. (Boswell) the work as required by principal contract to complete the following-items listed in ‘Bid Schedule’ of the principal contract at the- prices listed below opposite each item.” Then followed a. specification of twelve items, with the price to be paid for each. These items-referred to such things as the furnishings, placing and installation of described materials and equipment for the construction of the conduits under the railroad.. The subcontract recited that Chapel had' read and was familiar with, “the terms- and conditions of said principal contract and is willing to undertake the work of' constructing bid items 1, 12, 13, 14, 15,. 16, 17, 23, 24, 25, 26, and 38 of principal contract as Subcontractor * * and *505 it was agreed among other things between Boswell and Chapel:

“Second, that Party of the First Part (Chapel) will be and is hereby bound by each and every term, condition, and penalty of said principal contract in the performance of its portion of said work outlined above, and for that purpose the parties hereto agree that such terms, conditions, and penalties are made a part hereof;
“Third, that the Party of the First Part (Chapel) will forthwith at its own sole cost and expense furnish to and for the full protection of the Party of the Second Part (Boswell) and for the protection also of the Party of the First Part, and all other subcontractors (sic) engaged in the work of construction of said principal contract, full insurance in an acceptable insurance company for and against the penalties imposed under the Workmen’s Compensation Act of the State of New Mexico, and under any statute or by common law for personal injuries and property damage in connection with the performance of the work to be performed hereunder;
“Fourth, that the Party of the First Part will not sublet or contract any of the work outlined above without written consent and approval of the Party of the Second Part;
“Fifth, that the Party of the Second Part will furnish all insurance required by the Santa Fe Railroad in performance of this contract;”

No mention was made in the subcontract of the services of watchmen and flagmen or other protective services to be furnished under the direction of the railroad company in accordance with the terms of the principal contract.

About ten days after the date of Chapel’s subcontract, without any consultation with Chapel or any negotiations between Chapel and the railway company, Boswell entered into another contract directly with the railway company, delegating the furnishing of the protective services to the railway company itself in the following terms:

“G. Protective Services. Contractor (Boswell) shall bear and pay all costs of protecting Santa Fe property and traffic made necessary or occasioned by Contractor’s operations under this contract. Santa Fe will furnish, at the sole cost and expense of Contractor, such flagmen, supervisors, section or bridge workmen as, in the judgment of Santa Fe, are required to insure the safety and continuity of rail traffic during Contractor’s operations on or about Santa Fe property. Santa Fe personnel while assigned to such protective services at the project shall be and remain the sole employees of Contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vidal v. Head (In Re Vidal)
234 B.R. 114 (D. New Mexico, 1999)
Roth v. American Hospital Supply Corp.
965 F.2d 862 (Tenth Circuit, 1992)
Leo Roth v. American Hospital Supply Corporation
965 F.2d 862 (Tenth Circuit, 1992)
KWIK-LOK CORPORATION v. Pulse
702 P.2d 1226 (Court of Appeals of Washington, 1985)
Mobile Investors v. Spratte
605 P.2d 1151 (New Mexico Supreme Court, 1980)
United States v. Erickson Paving Company
465 F.2d 396 (Ninth Circuit, 1972)
Schultz & Lindsay Construction Co. v. State
494 P.2d 612 (New Mexico Supreme Court, 1972)
United States v. Richard H. Ramsdell
450 F.2d 130 (Tenth Circuit, 1971)
C. H. Codding & Sons v. Armour And Company
404 F.2d 1 (Tenth Circuit, 1968)
C. H. Codding & Sons v. Armour & Co.
404 F.2d 1 (Tenth Circuit, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
298 F.2d 502, 1961 U.S. App. LEXIS 2915, Counsel Stack Legal Research, https://law.counselstack.com/opinion/david-e-boswell-an-individual-dba-boswell-construction-company-and-ca10-1961.