Hi-Way Electric Co. v. Pathman Construction Co.

404 F. Supp. 398, 1971 U.S. Dist. LEXIS 14486
CourtDistrict Court, E.D. Michigan
DecidedFebruary 23, 1971
DocketCiv. A. 36098
StatusPublished
Cited by6 cases

This text of 404 F. Supp. 398 (Hi-Way Electric Co. v. Pathman Construction Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hi-Way Electric Co. v. Pathman Construction Co., 404 F. Supp. 398, 1971 U.S. Dist. LEXIS 14486 (E.D. Mich. 1971).

Opinion

MEMORANDUM OPINION AND ORDER

KEITH, District Judge.

This is an action brought under the Miller Act, 40 U.S.C. §§ 270a-270e. On April 26, 1968, defendant and counterclaimant 1 Pathman Construction (“Pathman”) entered into a contract with the United States of America, through its agent, the United States Navy Department, Naval Facilities Engineering Command, known as Contract No. N 62465-68-C0183, for construction work to be done at Selfridge Air Force Base, Mt. Clemens, Michigan. This contract called for the construction of three new buildings, and remodeling work to be done in seven other buildings, four of which were hangars and three were office buildings.

Plaintiff, Hi-Way Electric Company (“HiWay”), is an electrical contractor. On July 1, 1968, Pathman contracted with HiWay for HiWay to do the electrical work specified in the prime contract and which concerned the new buildings and the remodeled buildings at the Selfridge Air Force Base project. Under the terms of the subcontract, HiWay was to be paid a base price of $270,000. According to the terms of defendant Pathman’s contract with the Navy, all work was to be completed by July 26, 1969. The Navy granted Path-man five time extensions, making the final date for completion, January 8, 1970. The project was accepted by the Navy on February 28, 1970.

This matter was submitted to the Court in a bench trial upon the issues of Count One of the Complaint filed on February 23, 1971; the Answers of defendants filed April 19, 1971, as amended on April 19, 1972; upon the issues of the Counterclaim filed by the defendants on April 19, 1972; and upon the issues as they were joined by the Reply to said Counterclaim which plaintiff filed on May 3, 1972.

The evidence was heard by this Court over a protracted period of time commencing July 31, 1973 and concluding, after a year intermission, on September 25, 1974. In all, the Court listened to almost ten weeks of testimony and received approximately 155 exhibits.

In Count One of its complaint, HiWay seeks damages against defendant Path-man, the prime contractor, and against The Home Indemnity Company (“Home”), as surety, in the amount of $49,237.32 for electrical work allegedly performed by HiWay under the prime contract and for certain additional extra *400 work allegedly performed by HiWay during the construction. This amount was subsequently reduced to $48,653.04 by amendment. In its Counterclaim, defendant Pathman seeks damages allegedly incurred by HiWay’s breach of its subcontract, which breach was the alleged cause of the delays which occurred throughout all major phases of the construction process and in the final completion. In addition, defendant denies that it owes the plaintiff anything further on the contract because of this breach. As a result of these delays, Pathman claims it was forced to make expenditures of $159,631.31. This amount was subsequently reduced to $144,610.45.

FINDINGS OF FACT

A. HiWay’s Claim for Balance Due

1. HiWay, the electrical subcontractor of defendant, the prime contractor, is suing the prime contractor and its bonding company for the balance due under the subcontract and also for extra services and materials provided which were not included in the contract price. The aggregate claim for balance due is $48,653.04.

2. HiWay’s claimed balance is based on the original contract price as modified by five change orders, plus three claimed extras. The change orders were authorized by Pathman and carry the signature of its president, William J. Pathman. (Plaintiff’s Exhibit C2). The evidence established that in addition to the $270,000 due under the subcontract as originally executed, a total of $1,569.91 is due to the plaintiffs under the change orders as follows:

Order No. 4083 $1378.25
Order No. 4089 245.66
Order No. 4117 (683.00) credit
Order No. 4190 139.85
Order No. 4240 489.15
Net Total $1569.91

3. Under Change Order No. 1 (No. 4083, supra), plaintiff claims and the evidence establishes the defendant owes plaintiff $1,378.25. This claim is for the premium time paid to a night shift which worked to provide the electrical needs of the masonry night shift. Path-man denies liability for Change Order No. 1, asserting that, inter alia, Change Order No. 1 is not legally binding because it was signed under duress, and that payment of premium time is a contractual obligation of HiWay under the subcontract agreement. Through the testimony of Andrew Leer, president and accountant, and through the introduction of its business records (Plaintiff’s exhibit C-2), HiWay established by a preponderance of the evidence that it is entitled to recovery in the amount of $1,378.25 under Change Order No. 1. The Court does not find that Change Order No. 1 was signed under duress, nor does it find that it was the intent of the parties that payment for premium time be included in the contract price. 2

4. During the course of construction, certain extra work orders were issued by Pathman to HiWay which HiWay claims represent work performed by HiWay which was not included in the original contract price. HiWay claims *401 an aggregate of $2,440.48 is due for this further electrical work, as follows:

Invoice No. 4259 $ 257.38
Invoice No. 4293 252.99
Invoice No. 4411 1260.73 (premium time)
Invoice No. 4639 218.87
Invoice No. 5056 450.91 (disconnect _ switches)
Total $2440.88

5. HiWay’s claim of $1260.73 and $252.99 (Invoice Nos. 4411 and 4259, su pra) is for the cost of the labor and material for temporary lighting for the masons working on the Barracks Building (Plaintiff’s exhibit C-3). Included in plaintiff’s exhibit C-3 is a letter dated March 13, 1969 addressed to Mr. Williams of HiWay and signed by Mr. Etling, General Superintendent of Path-man. The letter states, on its face, that it will serve as authority for HiWay to proceed with the temporary electric power and lighting as required for the masonry work in the Barracks Building. Attached to each of the two invoices are the respective work orders which all bear the signature of Jerry Linden as representative for Pathman. On March 31, 1969, Pathman appeared to reject HiWay’s claim of $252.99 on the grounds that temporary lighting was already being paid for under HiWay’s subcontract (Defendant’s exhibit 22). Nevertheless, this Court finds that the temporary wiring described in Invoice No. 4293 and No. 4411 was not part of HiWay’s original contractual obligation. Rather, this work was performed by HiWay in accordance with authorization from Pathman’s field superintendent due to the requirement of the mason contractor.

6. HiWay’s claim of $450.91 (Invoice No. 5056, supra)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Empire Enterprises JKB, Inc. v. Union City Contractors, Inc.
660 F. Supp. 2d 492 (W.D. New York, 2009)
Jones v. Jackson National Life Insurance
819 F. Supp. 1382 (W.D. Michigan, 1993)
Gordon Sel-Way, Inc. v. Spence Bros.
475 N.W.2d 704 (Michigan Supreme Court, 1991)
DiRusso v. United States
409 F. Supp. 1055 (D. Massachusetts, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
404 F. Supp. 398, 1971 U.S. Dist. LEXIS 14486, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hi-way-electric-co-v-pathman-construction-co-mied-1971.