United States of America, for the Use and Benefit of Weyerhaeuser Company v. Bucon Construction Company, Inc., and Travelers Indemnity Company

430 F.2d 420, 14 Fed. R. Serv. 2d 278, 1970 U.S. App. LEXIS 8704
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 15, 1970
Docket28192
StatusPublished
Cited by77 cases

This text of 430 F.2d 420 (United States of America, for the Use and Benefit of Weyerhaeuser Company v. Bucon Construction Company, Inc., and Travelers Indemnity Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, for the Use and Benefit of Weyerhaeuser Company v. Bucon Construction Company, Inc., and Travelers Indemnity Company, 430 F.2d 420, 14 Fed. R. Serv. 2d 278, 1970 U.S. App. LEXIS 8704 (5th Cir. 1970).

Opinion

ORIE L. PHILLIPS, Circuit Judge:

This is an action brought by the United States for the use and benefit of Weyerhaeuser Company 1 against Bucon Construction Company, Inc 2 and Travelers Indemnity Company. 3

Bucon was the prime contractor, under a contract entered into on April 18, 1962, between it and the United States, acting through C. A. Bird, Lt. Colonel, Corps of Engineers, as contracting officer, for the construction of a project known as Base Chapel, at the Air Force Missile Test Center, Patrick Air Force Base, Florida. Bucon, as principal, and Travelers, as surety, executed on April 18, 1962, the payment bond required by the Miller Act (40 U.S.C.A. § 270a) “for the protection of all persons supplying labor and material in the prosecution of the work provided for” in the prime contract.

On April 25, 1962, Bucon and Weyer-haeuser entered into a subcontract by which Weyerhaeuser agreed to furnish certain specified labor and materials in the prosecution of the work provided for in the prime contract.

By this action, Weyerhaeuser sought to recover on the subcontract and bond $65,550, the balance it claimed to be due it under the subcontract; $10,000 for extras furnished at Bucon’s request, and $1,596.34 for wind damage suffered by it.

• Bucon and Travelers filed an answer denying the liability to Weyerhaeuser and claiming affirmatively the right to setoff all damages resulting from Weyer-haeuser’s failure to substantially perform the subcontract.

Bucon also filed a counterclaim by which it sought to recover damages for Weyerhaeuser’s alleged failure to “properly perform” the subcontract and for alleged negligence and unskilled performance of its work under the subcontract. Weyerhaeuser filed an answer denying the allegations of the counterclaim.

The case was submitted to the jury by five special interrogatories.

*422 By its answer to Interrogatory No. 1, the jury found Weyerhaeuser had failed to substantially perform the subcontract.

By its answer to Interrogatory No. 3, the jury found that Bucon had incurred delay penalties assessed by the Corps of Engineers, of which $5,900 was attributable to Weyerhaeuser's failure to “strictly comply with the provisions of its subcontract with Bucon.”

By its answer to Interrogatory No. 4, the jury found that Bucon had incurred costs and expenses in furnishing labor and materials “to repair or replace items which were improperly installed or improperly furnished by Weyerhaeu-ser” in the amount of $2,400.

Interrogatory No. 5 and the jury’s answer thereto read:

“Other than penalties, if any, and costs and expenses, if any, found to have been incurred in the answers to interrogatories numbered 3 and 4, above, how much damage, if any, has defendant Bucon proved by a preponderance of the evidence that it sustained as a result of any delay caused by Wey-erhaeuser in failing to strictly comply with the provisions of the sub-contract with Bucon?
“Zero.”

The Corps of Engineers assessed delay penalties against Bucon, under the provisions of the prime contract, in the amount of $6,720.

On September 19, 1967, Weyerhaeuser filed a timely motion for a new trial, and set up as grounds therefor that the jury’s answer to Interrogatory No. 1 was contrary to the evidence, and that the court erred in refusing to give Instruction No. 4, requested by Weyerhaeuser. 4

On November 8, 1967, the court entered judgment on the jury’s answers,..adjudging that Weyerhaeuser take nothing and that its complaint be dismissed, and that Bucon recover $8,300 on its counterclaim, plus attorney’s fees and costs to be determined later.

Thereafter, on November 8,. 1967, the court granted the motion for a new trial on the issue of whether Weyerhaeuser had substantially performed its subcontract, on the ground that it was “contrary to the evidence,” and that the damages suffered by Bucon, due to Weyerhaeuser’s failure to strictly perform the subcontract, were small in relation to the subcontract price, and that Bucon “can, without injustice, be compensated for its damages by deductions from the contract price”; and ordered that the judgment of November 8, 1967, “shall stand to the extent that it awards damages” to Bucon “on its counterclaim, subject to any recovery to which” Weyerhaeuser “may be entitled.” 5

*423 Thereafter, the case was retried solely on the issue of whether Weyerhaeuser had substantially performed the subcontract. By its answer to a special interrogatory, the jury found Weyerhaeuser had substantially performed the subcontract.

Bucon made a motion for a directed verdict in its favor at the close of the evidence at the second trial.

After the verdict at the second trial was returned, Bucon filed a motion for judgment n.o.v. and in the alternative for a new trial, on the ground that the evidence, considered in a light most favorable to Weyerhaeuser, was insufficient to support a verdict in its favor, and as grounds for a new trial it further set up that the court erred in permitting counsel for Weyerhaeuser in his closing argument at the second trial to comment on the damages awarded by the jury at the first trial, and that the court erred in instructing the jury on the second trial as to the amount of damages awarded by the jury at the first trial. The motion was denied. Bucon and Travelers have appealed.

Bucon contends that the court erred in granting Weyerhaeuser’s motion for a new trial solely on the ground that Weyerhaeuser had not moved the court for a directed verdict at the first trial.

There is an important distinction between a motion for a directed ver-diet or a motion for a judgment n.o.v. on the one hand and a motion for a new trial on the other. In passing on a motion for a directed verdict, or for a judgment n.o.v., the court does not exercise discretion, but decides a pure question of law, that is, whether the evidence, considered in the light most favorable to the party against whom the motion is directed, affords substantial support for a verdict in his favor. 6

If a motion for a directed verdict or for a judgment n.o.v. is sustained, judgment is entered for the movant and the case is ended in the trial court, 7 but the sustaining of a motion for a new trial does not result in a final judgment; it only grants another trial by a different jury 8

In passing on a motion for a new trial, the court may and should exercise a sound discretion, 9 and its ruling thereon will not be reviewed in an appellate court in the absence of a clear abuse of discretion. 10

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooper v. Milliman, Inc.
M.D. Florida, 2025
Berry v. Sanders
M.D. Louisiana, 2022
Babin v. Plaquemines Parish
E.D. Louisiana, 2020
Jennifer Jenkins v. S. David Anton, PA
922 F.3d 1257 (Eleventh Circuit, 2019)
Colman v. Home Depot USA, Inc.
705 F. App'x 949 (Eleventh Circuit, 2017)
Jane McGinnis v. American Home Mortgage Servicing, Inc.
817 F.3d 1241 (Eleventh Circuit, 2016)
in Re Wyatt Field Service Company
454 S.W.3d 145 (Court of Appeals of Texas, 2014)
Fleming, Ingram & Floyd, P.C. v. Clarendon National Insurance
850 F. Supp. 2d 1367 (S.D. Georgia, 2011)
Johnson v. FFE Transportation Services, Inc.
227 F. App'x 780 (Eleventh Circuit, 2007)
Cates v. Creamer
431 F.3d 456 (Fifth Circuit, 2005)
Whitehead v. Food Max of Mississippi, Inc.
163 F.3d 265 (Fifth Circuit, 1999)
United States v. Jonathan Logan
861 F.2d 859 (Fifth Circuit, 1988)
Lewis R. Daniel v. Wayne Ferguson
839 F.2d 1124 (Fifth Circuit, 1988)
Standard Fire Insurance v. Mitchell
666 F. Supp. 950 (E.D. Texas, 1987)
Whipple v. Jackson Marine Corp.
650 F. Supp. 649 (E.D. Texas, 1986)
Herrmann v. Nicor Marine, Inc.
664 F. Supp. 241 (E.D. Louisiana, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
430 F.2d 420, 14 Fed. R. Serv. 2d 278, 1970 U.S. App. LEXIS 8704, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-weyerhaeuser-company-ca5-1970.