Transcontinental Gas Pipe Line Company, LLC v. Kibby Welding, LLC

CourtDistrict Court, N.D. Oklahoma
DecidedSeptember 27, 2021
Docket4:18-cv-00445
StatusUnknown

This text of Transcontinental Gas Pipe Line Company, LLC v. Kibby Welding, LLC (Transcontinental Gas Pipe Line Company, LLC v. Kibby Welding, LLC) is published on Counsel Stack Legal Research, covering District Court, N.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transcontinental Gas Pipe Line Company, LLC v. Kibby Welding, LLC, (N.D. Okla. 2021).

Opinion

UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF OKLAHOMA TRANSCONTINENTAL GAS PIPE LINE ) COMPANY, LLC, ) ) Plaintiff, ) ) v. ) Case No. 18-CV-0445-CVE-FHM ) KIBBY WELDING, LLC, ) ) Defendant. ) OPINION AND ORDER Before the Court are the following motions: Plaintiff Transcontinental Gas Pipe Line Company, LLC’s Renewed Motion to Strike Defendant’s Jury Demand and Brief in Support (Dkt. # 69); Plaintiff’s Motion for Summary Judgment and Brief in Support (Dkt. ## 70, 81); Plaintiff’s First Motion in Limine (Dkt. # 83); Plaintiff’s Second Motion in Limine (Dkt. # 84); Plaintiff’s Third Motion in Limine (Dkt. # 85); Plaintiff’s Fourth Motion in Limine (Dkt. # 86); and Plaintiff’s Fifth Motion in Limine (Dkt. # 87). Plaintiff Transcontinental Gas Pipe Line Company, LLC (Transco) requests summary judgment in its favor on all of its claims and as to defendant Kibby Welding, LLC’s (Kibby) counterclaims of breach of contract and interference with business relations. Dkt. ## 70, 81. Transco also asks the Court to strike Kibby’s demand for a jury trial, because the parties waived their right to a jury trial in their contract. Dkt. # 69. I. Transco is an interstate pipeline company and it solicited bids for a project identified as Spread 16. Transco states that it is a subsidiary of Williams Partners Operating, LLC, and The Williams Companies, Inc. (collectively Williams). Dkt. # 25, at 2. On November 30, 2017, Transco held a pre-job meeting for contractors to inspect the work site in Charlottesville, Virginia, and Louis Kibby, the owner of Kibby, attended the meeting.1 Dkt. # 70-2. Kibby submitted a lump sum bid of $4,058,500 for the Spread 16 project, and the bid stated that Kibby had applied for a Virginia contractor’s license. Dkt. # 71-4, at 1. However, Kibby did not actually apply for a Virginia

contractor’s license until February 14, 2018, and Kibby did not obtain a Virginia contractor’s license until April 11, 2018. Dkt. # 70-5, at 2; Dkt. # 71-5. On January 5, 2018, Transco accepted Kibby’s bid for the project after the parties exchanged e-mails clarifying certain matters relating to the contract. Dkt. # 71-6. Louis Kibby signed the contract with Transco after reviewing the scope of work provisions of the contract, and he admits that he did not attempt to read the entire contract. Dkt. # 71-7, at 3-4. The contract required Kibby to obtain a performance and payment bond before beginning

work on the project. Specifically, the contract provides: At [Transco’s] request, Contractor shall furnish, prior to commencement of the Work to be performed, a performance and payment bond in the amount of the total Contract compensation. Such bond shall be on a form satisfactory to Company for guaranteeing that Contractor will fully perform its obligations and assume its liability under this Contract. . . . Failure to furnish and maintain a requested performance and payment bond shall be considered a breach of the Contract. Dkt. # 71-1, at 29-30. The parties do not dispute that Transco requested that Kibby obtain a bond before beginning work on the project. Dkt. # 70-7, at 7; Dkt. # 70-8, at 1. On January 17, 2018, Transco asked for an update on the bond, and Louis Kibby responded that he should “have it today or tomorrow.” Dkt. # 70-8, at 9. By April 2018, Kibby had still not obtained a bond and Transco was still requesting a bond for the full amount of the contract. Id. at 16. Kibby affirmatively advised 1 Throughout this Opinion and Order, the Court will refer to the business entity Kibby Welding, LLC as “Kibby” and will refer to Louis Kibby by name. 2 Transco that “we did get a bond for this job” but, in fact, Louis Kibby admitted that Kibby had not obtained a bond. Id. at 16. Louis Kibby also told Transco that the bonding company would no longer issue a bond for the full amount of the contract due to the completion of some of the work, and he asked if Transco would accept a bond for a reduced amount. Id. Transco clearly advised

Kibby that this would not be acceptable. Id. Louis Kibby has submitted an affidavit stating that Kibby had a “firm quote” for a bond no later than January 19, 2018, and he provided this information to Transco. Louis Kibby claims that Transco allowed work to start on the project without a bond. Dkt. # 93-1, at 2. However, he offers no explanation for Kibby’s failure to actually obtain the bond as repeatedly requested by Transco. Work was scheduled to begin on the Spread 16 project near the end of January 2018 and there is no dispute that the work was delayed, but the parties dispute the cause for Kibby’s delay in

beginning work on the project. Transco’s expert, FTI Consulting, Inc. (FTI), states that Kibby did not submit an extra work request (EWR) for a delayed start of trenching work, and there is no evidence suggesting that Transco was responsible for a 21-day delay of work at the beginning of the project. Dkt. # 70-9, at 29. The delay in beginning excavation work led to subsequent delays of planned pipeline outages that further delayed completion of the project. Id. at 30. Kibby responds that it was mobilized and ready to work on January 29, 2018, and Transco’s delay in providing necessary materials to Kibby caused a delay in welding and pre-fabrication of the necessary valves and pipeline parts. Dkt. # 93-1, at 2. Kibby also claims that it discovered a bend in the pipeline that

was not disclosed in the drawings provided by Transco, and Transco’s delay in providing revisions to the scope of work further delayed work on the project. Id. By March 2018, Transco had become concerned about delays in completion of Kibby’s work, and Transco’s project manager, Mark 3 Wachowicz, reported that Kibby had significant turnover in its workforce and it was not field- verifying underground pipe configurations before pre-fabricating the valve assemblies. Dkt. # 94-3, at 1. In April 2018, Transco deleted 18 items from the scope of work included in the contract due to Kibby’s delays in completing work, but Kibby objected to the deletion of these items and it claims

that the reduction of the scope of work actually increased the cost for Kibby to complete its work. Dkt. # 70-11; Dkt. # 93-1, at 3. In June and July 2018, further delay resulted when Kibby was unable to complete the tie-in welds for the Mainline B Pipe Replacement, but the parties again dispute the cause of the delay. FTI determined that delays in the pipe replacement were due to poor welds by Kibby that had to be repaired, cut out, or repeated, and Kibby’s poor work resulted in additional outages and 23 days of delay in completion of the work. Dkt. # 70-9, at 34-39. Louis Kibby states that Transco personnel assumed authority over the welds for the Mainline B Pipe Replacement, and

the welds failed after Transco failed to follow the welding procedures recommended by Kibby. Dkt. # 93-1, at 3. The contract provided that the entire scope of work was intended to be completed in 145 days, but Kibby had completed only a reduced portion of the scope of work after 197 days. Dkt. # 70-9, at 34. The contract provided a process for additions or changes to the contract based on unforeseen events or delays as follows: Contractor shall make no additions, changes, alterations or omissions, perform extra work, or supply or use extra materials or equipment of any kind except in accordance with a prior approved “Extra Work Request” [EWR] in the form attached as Appendix C, or a written amendment to the Contract. Dkt. # 71-1, at 13. Kibby was required to submit EWRs to Transco at least 48 hours before starting any work that would require compensation that was not specifically authorized by the contract. Id. 4 Louis Kibby states that Transco personnel directed Kibby not to use the EWR process before proceeding with work outside the scope of the project, and he claims that Transco wanted Kibby to submit EWRs directly to the project manager for approval.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Whitmire v. Zolbe
1965 OK 97 (Supreme Court of Oklahoma, 1965)
Lewis v. Farmers Ins. Co., Inc.
681 P.2d 67 (Supreme Court of Oklahoma, 1983)
Robberson Steel Co. v. Harrell
177 F.2d 12 (Tenth Circuit, 1949)
Cramer v. Sabine Transportation Co.
141 F. Supp. 2d 727 (S.D. Texas, 2001)
Digital Design Group, Inc. v. Information Builders, Inc.
2001 OK 21 (Supreme Court of Oklahoma, 2001)
Tuffy's, Inc. v. City of Oklahoma City
2009 OK 4 (Supreme Court of Oklahoma, 2009)
Wilspec Technologies, Inc. v. DunAn Holding Group Co.
2009 OK 12 (Supreme Court of Oklahoma, 2009)
Antrim Lumber Co. v. Neal
1935 OK 378 (Supreme Court of Oklahoma, 1935)
Eason Oil Co. v. M. A. Swatek & Co.
1934 OK 509 (Supreme Court of Oklahoma, 1934)
Campbell v. Frye
1930 OK 453 (Supreme Court of Oklahoma, 1930)
Telum, Inc. v. E.F. Hutton Credit Corp.
859 F.2d 835 (Tenth Circuit, 1988)
Hulsey v. West
966 F.2d 579 (Tenth Circuit, 1992)
Kendall v. Watkins
998 F.2d 848 (Tenth Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Transcontinental Gas Pipe Line Company, LLC v. Kibby Welding, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transcontinental-gas-pipe-line-company-llc-v-kibby-welding-llc-oknd-2021.