CC SMITH CO. INC. v. Frankini Construction Co.

135 N.E.2d 924, 334 Mass. 379, 1956 Mass. LEXIS 677
CourtMassachusetts Supreme Judicial Court
DecidedJune 29, 1956
StatusPublished
Cited by8 cases

This text of 135 N.E.2d 924 (CC SMITH CO. INC. v. Frankini Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CC SMITH CO. INC. v. Frankini Construction Co., 135 N.E.2d 924, 334 Mass. 379, 1956 Mass. LEXIS 677 (Mass. 1956).

Opinion

Spalding, J.

This is a petition brought by a subcontractor under G. L. (Ter. Ed.) c. 149, § 29, as appearing in St. 1938, c. 361, to reach the security retained by the defendant Medford Housing Authority (hereinafter called the authority) under a general contract with the defendant Frankini Construction Company, hereinafter called Frankini. Peerless Casualty Company, the surety on Frankini’s performance and payment bond, was also a defendant. Anchor Post Products, Inc., was allowed to intervene, and inasmuch as the present controversy has to do exclusively with its claim it will be referred to hereinafter as the petitioner. Its petition contains a prayer that such part of the-petitioner’s claim as may not be satisfied out of funds retained by the authority be enforced against Peerless. Frankini was adjudicated a bankrupt and its trustee in bankruptcy has appeared and answered and contends that he is entitled to the retained funds in controversy. He will be *381 referred tc hereinafter as the defendant. The petitioner’s claim, along with others, was referred to a master. With respect to the petitioner’s claim the master filed a report. A decree was entered confirming the report and adjudging that Frankini was indebted to the petitioner in the sum of $4,344 plus $484.36 and $17.50 for interest and costs respectively; the decree further provided that as to the authority and the Peerless Casualty Company the intervening petition be dismissed. The petitioner appealed.

Facts found by the master include the following: On July 31, 1952, Frankini and the authority entered into a contract for the construction of a “PHA Aided Housing Project” in Medford. Frankini was the general contractor and under the contract was to furnish all the labor and materials for the project for the price of $1,428,737.75. As required by the contract, Frankini, as principal, and Peerless Casualty Company, as surety, executed and delivered to the authority a statutory performance and payment bond. (See G. L. [Ter. Ed.] c. 149, § 29; G. L. [Ter. Ed.] c. 121, § 26V, as appearing in St. 1946, c. 574, § 1.) Thereafter Frankini entered into various subcontracts for the performance of certain portions of the work by others. One of these subcontracts was with the petitioner. Under its subcontract the petitioner, for the sum of $7,500, was to furnish and install the chain fink fencing and clothes posts at the project according to the plans and specifications and subject to the provisions of the general contract. Progress payments were to be made monthly within ten days of receipt by Frankini of payment from the authority. By December 8, 1953, the petitioner had “substantially completed” all of .the work under its subcontract. All of the work performed and materials furnished were “considered satisfactory and in accordance with the terms of the contract.” Some work, however, remained to be done, namely, “preening” the bolts which fasten parts of the clothes posts, and furnishing and installing metal caps on one hundred nine clothes posts. The fair value of the labor and material required to finish this work was $156.

*382 Down to December 8, 1953, the authority had made progress payments to Frankini totaling $6,547.28 on account of the work done by the petitioner, but only $3,000 was paid by Frankini to the petitioner. The petitioner informed Frankini that it would not complete the work unless it received the balance then due.

On July 29, 1954, the authority declared Frankini to be in default on the general contract and on August 5, 1954, notified Frankini that it was terminating the contract as of August 11, 1954. The reasons assigned for the termination were (1) repeated failure to supply enough properly skilled workmen, (2) failure to make prompt payment to subcontractors, (3) persistent disregard of instructions of the authority and the architect, and (4) failure to perform the provisions of the contract. Under the general contract a failure on the part of the contractor with respect to any of the foregoing matters gave the authority the right to terminate the contract. Frankini performed no work thereafter; nor did the petitioner ever complete the work which remained unfinished on December 8, 1953. Having learned that the authority had terminated the general contract, the petitioner on October 4, 1954, filed with the city clerk of Med-ford a sworn statement of its claim, which was sufficient as to both form and content.

The master found that Frankini was indebted to the petitioner in the sum of $4,344, representing the subcontract price of $7,500 less the payment of $3,000 and the fair value ($156) of the unfinished work. As to the right of the petitioner to reach the security in the hands of the authority, the master made no finding as he deemed that to be a question of law which depended on whether the claim was filed within the time required by G. L. (Ter. Ed.) c. 149, § 29.

By reason of G. L. (Ter. Ed.) c. 121, § 26V, the provisions of G. L. (Ter. Ed.) c. 149, § 29, 1 were made applicable to housing authorities. Philip Carey Manuf. Co. v. Peerless Casualty Co. 330 Mass. 319. The parties have argued the *383 case on the footing that the petitioner’s right to recover from the amount retained by the authority depends on proof of compliance with this statute by the petitioner, and we shall deal with the case accordingly. 1 The question, therefore, for decision is whether the petitioner complied with its provisions in filing its sworn statement of claim on October 4, 1954. The trial judge by dismissing the petition as to the authority and the Peerless Casualty Company evidently took the view that the requirements of § 29 as to the time of filing had not been satisfied. Section 29, so far as here material, reads: "... but in order to obtain the benefit of such security the claimant shall file in the office of the county treasurer or of the city or town clerk a sworn statement of his claim within sixty days after the claimant ceases to perform labor or furnish labor, materials, appliances and equipment as aforesaid . . ..”

The defendant contends that the petitioner by fifing its claim approximately ten months after it had ceased work on the project did not bring itself within the quoted provisions of the statute. The defendant recognizes that a claimant under § 29 ordinarily has no standing if he files his claim before he has completed his work under the contract. That principle is well settled by our decisions. Mario Pandolf Co. Inc. v. Commonwealth, 303 Mass. 251. International Business Machines Corp. v. Quinn Brothers Electrical Co. 321 Mass. 16, 19. And, as the case last cited holds, that principle applies even though the amount of work remaining to be done is comparatively slight. But, argues the defendant, the following two courses were open to the petitioner on the facts here and it pursued neither. On December 8, 1953, it could have terminated its contract with Frankini because of the latter’s default and sued for substantial performance on a quantum meruit, and could have reached the security, provided its claim was filed within sixty days; or it could have completed its work under the contract and by fifing *384

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Framingham Heavy Equipment Co. v. John T. Callahan & Sons, Inc.
807 N.E.2d 851 (Massachusetts Appeals Court, 2004)
D & P Equipment Corp. v. Harvey Construction Co.
363 N.E.2d 1369 (Massachusetts Appeals Court, 1977)
Ross v. Planet Insurance
279 N.E.2d 690 (Massachusetts Supreme Judicial Court, 1972)
AMERICAN AIR FILTER CO. INC. v. Innamorati Bros. Inc.
260 N.E.2d 718 (Massachusetts Supreme Judicial Court, 1970)
WARREN BROTHERS ROADS CO. v. Joseph Rugo, Inc.
245 N.E.2d 243 (Massachusetts Supreme Judicial Court, 1969)
Lawrence Plate & Window Glass Co. v. Varrasso Bros.
233 N.E.2d 897 (Massachusetts Supreme Judicial Court, 1968)
Mosaic Tile Co. v. Rusco Products of Massachusetts, Inc.
215 N.E.2d 171 (Massachusetts Supreme Judicial Court, 1966)
Drinkwater v. D. Guschov Co.
196 N.E.2d 863 (Massachusetts Supreme Judicial Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
135 N.E.2d 924, 334 Mass. 379, 1956 Mass. LEXIS 677, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cc-smith-co-inc-v-frankini-construction-co-mass-1956.