Drinkwater v. D. Guschov Co.

196 N.E.2d 863, 347 Mass. 136, 1964 Mass. LEXIS 730
CourtMassachusetts Supreme Judicial Court
DecidedMarch 4, 1964
StatusPublished
Cited by4 cases

This text of 196 N.E.2d 863 (Drinkwater v. D. Guschov Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Drinkwater v. D. Guschov Co., 196 N.E.2d 863, 347 Mass. 136, 1964 Mass. LEXIS 730 (Mass. 1964).

Opinion

Spalding, J.

On March 15, 1961, the city of Woburn (city) entered into a contract with D. Gusehov Company, Inc. (Gusehov), for the construction of a school. The plaintiff, a subcontractor, contracted to do the excavating and grading. New Amsterdam Casualty Company (Amsterdam) furnished the bond required under G. L. c. 149, § 29, securing payments by Gusehov for labor and materials. The plaintiff by this bill seeks to establish a lien under § 29 for sums alleged to be due him for labor and materials supplied pursuant to his subcontract with Gusehov.1 The evidence is reported and the judge made a report of the material facts.

Under his subcontract the plaintiff agreed to do the following work for the sum of $41,000: 1Clear and grub site; [138]*138stockpile loam; remove and dispose of stone walls and foundations; cut, grade and supply necessary borrow to bring site to proposed sub-grades; excavate and backfill foundations and utilities; furnish necessary fill for building to within 12" of finished floors; furnish suitable backfill over storm piping; supply equipment to install storm piping.” Work by “others” was described: “Engineering, hand labor and pumping. ’ ’ If ledge was encountered the following amounts were to be paid extra: “Ledge in open — $6.00 per cubic yard Ledge in trench — 9.00 per cubic yard.”

The subcontract also provided that Guschov would pay the plaintiff ninety per cent of all labor and materials which had been “placed in proper position,” and for which payment had been made to Guschov by the city within about ten days after receipt of payment by Guschov from the city.

The items of work included in the subcontract were encompassed by the following items in the general contract between Guschov and the city: “ [item] 4. Demolition, site clearing & stripping . . . [item] 5. Site excavation and rough grade . . . [item] 6. Building excavation and fill . . . [item] 7. Utility excavation, storm piping and structures. ’ ’ Guschov was to receive a total of $112,774 from the city for the completion of these items, payable in periodic instalments based on estimates of the value of the amount of work completed, furnished by Guschov, and verified by the architect and the city officials.

The plaintiff began work under the subcontract on April 3, 1961. At the end of April, Guschov made a requisition on the city for $29,755 for work done on items 4-7 of the general contract. At the end of May, Guschov requisitioned $24,200 for work on those items. The requisitions were paid by the city to Guschov respectively on the twentieth of May and the twentieth of June.

Guschov paid the plaintiff $6,000 on June 3, and $5,000 about July 10 for work done under the subcontract on items 4-7. The plaintiff informed Guschov that he was entitled to more than $11,000 for the work done by him during the months of April and May, and, after several unsuccessful [139]*139demands for increased payments, ceased to perform any further work under the subcontract.

The judge found that when the plaintiff left the job, Gus-chov owed him substantially more than the plaintiff had been paid for the months of April and May; and that the failure of Guschov to pay the amounts owed to the plaintiff constituted a breach of the subcontract on the part of Gus-chov which justified the plaintiff in discontinuing performance. He further found that the plaintiff had seasonably filed with the city a statement of his claim which met the requirements of G. L. c. 149, § 29, and was entitled to reach the funds retained by the city under the general contract and the security under Amsterdam’s bond. He ruled that the plaintiff was entitled to the contract price less the cost of completion and payments already made. He awarded the sum of $26,248. From a decree accordingly, Guschov and Amsterdam appealed.

1. Amsterdam argues that there was no evidence to support the finding that the plaintiff filed a sworn statement of his claim in accordance with the provisions of G. L. c. 149, § 29. It is true, as Amsterdam contends, that no sworn statement of the plaintiff’s claim was introduced in evidence. But we are of opinion that Amsterdam may not now raise this question. When Wall, the city’s superintendent of public works, was testifying, counsel for the plaintiff interrogated him with respect to the receipt of certain letters written on behalf of the plaintiff which included, presumably, the notice of claim. During this interrogation the judge observed that the city in its answer had admitted receipt of the claim. Counsel for the plaintiff agreed that that was so. The judge then remarked, ‘ ‘ They admit it. Yes. That is not in issue.” Counsel remained silent. The question of the claim was never thereafter inquired about or discussed. Of course, the city’s answer did not bind Amsterdam but, in the circumstances, counsel for the plaintiff and the court had the right to assume that questions as to the validity of the claim were no longer in issue. The city in its answer admitted that a sworn notice of claim [140]*140was properly filed. At the time the judge stated that the matter of the claim was not in issue, Amsterdam by its silence impliedly waived any defence based on its invalidity. “Where a party causes the judge to understand that certain facts are admitted or that certain issues are waived or abandoned he cannot object to the judge’s conducting the trial on the basis of that understanding.” Dalton v. Post Publishing Co. 328 Mass. 595, 599.

2. Guschov argues that there is no evidence to support the finding that the plaintiff was justified in ceasing performance about July 12. Unless Guschov was in default in his payments the plaintiff was not justified in leaving the job. The judge found that at the time the plaintiff quit there was due him for work done in April and May approximately $22,0001 less the amount ($11,000) which he had been paid. We are of opinion that the conclusion of the judge that Guschov was in default and that further performance by the plaintiff was excused was not plainly wrong.

The plaintiff testified that he had done $13,390 worth of work in April and $9,225 worth of work in May. There was evidence that Guschov requisitioned $53,955 from the city for work completed in April and May which was principally done by the plaintiff. Some of the work for which requisition was made under items 4-7 was done by others. But the judge developed a fraction to allocate the amounts requisitioned between the plaintiff and others. The fraction was composed of a numerator representing the subcontract price to the plaintiff (approximately $41,000) and a denominator representing the general contract price (approximately $81,000) for items 4 — 6. The denominator employed by the judge was erroneous, for it is now conceded that the general contract price should have included item 7 and was approximately $112,000. But this error does not materially affect the conclusion, for if the correct fraction had been used the plaintiff’s share of the $53,955 requisitioned would be in excess of $19,000. By any evaluation of the evidence the plaintiff was entitled to substantially more [141]*141than the $11,000 which he had received. This underpayment was a material breach of the contract and justified the plaintiff’s stopping work prior to the completion of the contract. C. C. Smith Co. Inc. v. Frankini Constr. Co. 334 Mass. 379, 384.

3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bouley v. Reisman
645 N.E.2d 708 (Massachusetts Appeals Court, 1995)
Nolan v. Parker
446 N.E.2d 722 (Massachusetts Appeals Court, 1983)
Lawrence Plate & Window Glass Co. v. Varrasso Bros.
233 N.E.2d 897 (Massachusetts Supreme Judicial Court, 1968)
Lamb v. Santos
35 Mass. App. Dec. 162 (Mass. Dist. Ct., App. Div., 1966)

Cite This Page — Counsel Stack

Bluebook (online)
196 N.E.2d 863, 347 Mass. 136, 1964 Mass. LEXIS 730, Counsel Stack Legal Research, https://law.counselstack.com/opinion/drinkwater-v-d-guschov-co-mass-1964.