United States Ex Rel. W.W. Gay Mechanical Contractor, Inc. v. Walbridge Aldinger Co.

543 F. App'x 937
CourtCourt of Appeals for the Eleventh Circuit
DecidedNovember 1, 2013
Docket12-16220
StatusUnpublished

This text of 543 F. App'x 937 (United States Ex Rel. W.W. Gay Mechanical Contractor, Inc. v. Walbridge Aldinger Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. W.W. Gay Mechanical Contractor, Inc. v. Walbridge Aldinger Co., 543 F. App'x 937 (11th Cir. 2013).

Opinion

PER CURIAM:

The Walbridge Aldinger Company and its sureties (collectively, “Walbridge”) appeal the district court’s partial grant of summary judgment in favor of W.W. Gay Mechanical Contractor, Inc. (“W.W. Gay”) on W.W. Gay’s Miller Act and breach of contract claims. Walbridge also appeals the district court’s award of attorney’s fees under Fla. Stat. § 57.105(7). After review of the record and the parties’ briefs, we affirm.

I.

This case involves a dispute between a subcontractor and a general contractor, together with its sureties, over a construction project for the Navy. The subcontractor, W.W. Gay, asserted a Miller Act claim for unpaid amounts allegedly due under the subcontract, both for an unpaid retain-age of $251,937.92 and for extra work performed costing $109,177. The general contractor, Walbridge, claimed it was entitled to withhold payment from W.W. Gay because Walbridge was assessed around $1.5 million in liquidated damages by the Navy due to delays in project completion, for which W.W. Gay was allegedly at least partly responsible. Walbridge is still in the process of administratively appealing the liquidated damages assessment under the Contracts Disputes Act.

The district court partially granted W.W. Gay’s motion for summary judgment, ruling that W.W. Gay was entitled to payment for the full amount of the unpaid retainage and cost of extra work. The parties then entered into a stipulation on the remaining issues, in particular whether Walbridge was entitled to offset damages for W.W. Gay’s alleged delay in installing and completing the factory startup of a water softener. In its summary judgment order, the district court granted W.W. Gay attorney’s fees, based on a unilateral contract provision that gave Walbridge the right to seek attorney’s fees under certain conditions. The district court held that W.W. Gay could also seek attorney’s fees under Fla. Stat. § 57.105(7), which makes unilateral attorney’s fees provisions bilateral.

II.

We review a district court’s grant of summary judgment de novo, viewing the evidence in the light most favorable to the non-moving party. Thomas v. Cooper Lighting, Inc., 506 F.3d 1361, 1363 (11th Cir.2007). Summary judgment is proper if *939 “the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(a). The party opposing summary judgment must present more than “[t]he mere existence of a scintilla of evidence in support of [its] position ...; there must be evidence on which the jury could reasonably find for the [non-movant].” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 252, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

III.

We first consider whether Walbridge was entitled to withhold all payment to W.W. Gay because of the liquidated damages that the Navy assessed against Wal-bridge. The answer, we conclude, is no.

The Miller Act protects subcontractors on federal projects by requiring contractors to post a bond to ensure payment to their subcontractors. 40 U.S.C.A. § 3133. See also U.S. for Use & Benefit of Krupp Steel Products, Inc. v. Aetna Ins. Co., 831 F.2d 978, 980 (11th Cir.1987). To establish a Miller claim, W.W. Gay must show (1) that it supplied labor and materials for work in the particular contract at issue; (2) that it is unpaid; (3) that it had a good faith belief that the materials were for the specified work; and (4) that jurisdictional requisites are met. See Aetna Ins. Co., 831 F.2d at 980. To establish a breach of contract claim, W.W. Gay must show must show that (1) there was a valid contract; (2) Walbridge breached the contract; and (3) it suffered damages as a result of Wal-bridge’s breach. See Rollins Inc. v. But-land, 951 So.2d 860, 876 (Fla. 2d DCA 2006).

Walbridge argues that it did not breach its subcontract with W.W. Gay — and thus is not liable for any “amount unpaid” under the Miller Act, 40 U.S.C.A. § 3133— because W.W. Gay did not complete performance on time; this delay resulted in the Navy assessing liquidated damages against Walbridge; and Walbridge was entitled to offset these damages against the amount owed to W.W. Gay. Walbridge relies on Article III of the subcontract, which provides that Walbridge can withhold payment to W.W. Gay for any breach of the subcontract, and Article V, which provides that “time ... is of the essence” and that W.W. Gay may be liable for liquidated and other damages if it fails to “prosecute the Work as provided herein, thereby causing delay in the progress of the Project.” 1

The problem, however, is that Wal-bridge has failed to produce more than a “scintilla of evidence” that W.W. Gay’s alleged delays resulted in the liquidated damages assessed against it by the Navy. See Anderson, 477 U.S. at 252, 106 S.Ct. 2505. Walbridge cites the deposition testimony of its corporate representative Awadheshwari Prasad that “several correspondence [sic] exists that [W.W. Gay’s] activities have caused delay in the performance of the work affecting the critical activity,” D.E. 32-2, p. 12, 66:16-19, but the mere alleged existence of “correspondence” attributing delays to W.W. Gay is not proof that W.W. Gay caused any de *940 lays. Indeed, elsewhere in his deposition testimony, Mr. Prasad admits that it was the Navy that caused the delays and that these delays in turn affected W.W. Gay and the other subcontractors. See D.E. 32-2, p. 17, 71: 12-20. Significantly, the subcontract provides that W.W. Gay is only liable for liquidated damages if its “failure to prosecute the Work ... caus[es] delay in the progress of the Project” (emphasis added). Prasad’s testimony only suggests that W.W. Gay was delayed, not that it caused any delay, as required by the plain terms of the subcontract.

Walbridge also cites a letter from an alleged expert analyzing the project delays that lead to the liquidated damages. This letter, however, does not even mention W.W. Gay, much less attribute any delays to its work. Walbridge makes much of the fact that one of the six areas in which the expert identified delays was the “Comprehensive Interior Design,” or “CID,” and that W.W. Gay’s scope of work included the operating rooms, which were part of the CID. Yet Walbridge offers zero evidence that the CID delays stemmed from work on the operating rooms, much less from W.W. Gay’s work on the operating rooms. In fact, Walbridge’s expert attributes the CID delays to deficient drawings, which apparently had nothing to do with W.W. Gay.

The only other specific instance of delayed work that Walbridge attributes to W.W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. Cooper Lighting, Inc.
506 F.3d 1361 (Eleventh Circuit, 2007)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
United States v. Freeto Construction Company, Inc.
547 F.2d 537 (Tenth Circuit, 1977)
Placida Professional Center, LLC v. Federal Deposit Insurance
512 F. App'x 938 (Eleventh Circuit, 2013)
Sublime, Inc. v. Boardman's Inc.
849 So. 2d 470 (District Court of Appeal of Florida, 2003)
Escambia County v. UIL FAMILY LTD.
977 So. 2d 716 (District Court of Appeal of Florida, 2008)
PUBLIC HEALTH TRUST OF DADE CTY. v. Romart Const., Inc.
577 So. 2d 636 (District Court of Appeal of Florida, 1991)
Rollins, Inc. v. Butland
951 So. 2d 860 (District Court of Appeal of Florida, 2006)
Fernandez v. Vazquez
397 So. 2d 1171 (District Court of Appeal of Florida, 1981)
Southern Internet Systems, Inc. v. Pritula
856 So. 2d 1125 (District Court of Appeal of Florida, 2003)
Inland Dredging Co. v. Panama City Port Authority
406 F. Supp. 2d 1277 (N.D. Florida, 2005)
Bland v. FREIGHTLINER LLC
206 F. Supp. 2d 1202 (M.D. Florida, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
543 F. App'x 937, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-ww-gay-mechanical-contractor-inc-v-walbridge-ca11-2013.