Action Heating & Air Conditioning, Inc. v. Petersen

429 N.W.2d 1, 229 Neb. 796, 1988 Neb. LEXIS 336
CourtNebraska Supreme Court
DecidedSeptember 16, 1988
Docket86-1031, 86-1032
StatusPublished
Cited by8 cases

This text of 429 N.W.2d 1 (Action Heating & Air Conditioning, Inc. v. Petersen) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Action Heating & Air Conditioning, Inc. v. Petersen, 429 N.W.2d 1, 229 Neb. 796, 1988 Neb. LEXIS 336 (Neb. 1988).

Opinion

Boslaugh, J.

The plaintiffs, Action Heating & Air Conditioning, Inc., and Action Plumbing, Inc. (hereafter Action), have appealed from the orders of the district court affirming judgments of the county court finding that the garnishees, Mohammed H. Siddiq and Hayat Y. Hanafi, were not indebted to the defendant, Ken Petersen, doing business as Ken Petersen, Builder (hereafter Petersen), and that the garnishees be discharged from further proceedings.

On April 10, 1984, garnishees entered into a contract with Petersen in which Petersen, as prime contractor, agreed to construct a residential duplex on real estate owned by garnishees in Lincoln, Nebraska, for $124,000. Petersen completed construction of the duplex in December 1984. On December 11, 1984, Siddiq issued a check to Petersen in the amount of $6,000.

In late December 1984, Pella Products, a subcontractor, informed Siddiq that it had not been paid by Petersen. Siddiq then contacted Petersen, who confirmed that Pella had not been paid. Siddiq contacted one or two other suppliers and discovered that they also had not been paid by Petersen. Siddiq contacted his attorney, who advised him to stop payment on the check. Siddiq issued a stop payment order, which was effective. At the time he issued the stop payment order, Siddiq had not received any notice of lien liability. There was a balance of $9,600 unpaid on the contract, including the $6,000 not paid under the stop payment order.

Garnishees then notified all subcontractors that $9,600 remained unpaid under the contract, and strongly urged each of them to contact an attorney. Thereafter, mechanics’ liens in the total sum of $37,211.81 were filed against the real estate, including liens filed on February 7, 1985, by Action Heating & Air Conditioning in the amount of $3,712.58 and by Action *798 Plumbing in the amount of $7,072.71.

On July 24, 1985, Action filed petitions in the county court for Lancaster County asking for judgments against Petersen in the amounts of $3,712.58 and $7,072.71. On August 19, 1985, Action obtained default judgments against Petersen for these amounts.

On October 3,1985, Action filed garnishment affidavits and interrogatories directed against garnishees, which were served on October 6, 1985. Garnishees responded that they had no liability to Petersen. Action filed petitions for determination of liability of garnishees on October 22, 1985. Garnishees filed answers admitting there was a contract between garnishees and Petersen and that $9,600 remained unpaid. The answers alleged that garnishees had discovered in mid-December 1984 that Petersen was not paying the subcontractors; that since January 4, 1985, construction liens totaling $37,311.81 had been filed against garnishees’ real estate; that garnishees were protected party contracting owners within the meaning of the Nebraska Construction Lien Act, Neb. Rev. Stat. §§ 52-125 to 52-159 (Reissue 1984); and that garnishees hold the $9,600 for the benefit of the subcontractors and not for the benefit of Petersen.

After a consolidated trial, the county court found that Petersen was not entitled to the money held by garnishees and that the claim of a judgment creditor (Action) against a garnishee can rise no higher than that of the principal debtor. The county court declined to base its decisions on the Nebraska Construction Lien Act and stated that “a good deal more evidence is necessary before any court can proceed to any kind of a just resolution under the Construction Lien Act.” Apparently, the court based its decisions on the fact that Petersen agreed to pay all labor and material costs and had failed to complete the structure on or before September 15, 1984, as provided in the contract.

Action appealed to the district court, where the judgments were affirmed. The district court found that garnishees were protected party contracting owners within the meaning of §§ 52-128, 52-129, and 52-136 of the Nebraska Construction Lien Act. It further found that Petersen had failed to pay the *799 subcontractors; that subcontractors’ liens in excess of the remaining balance due Petersen from garnishees had been filed; and that under the Nebraska Construction Lien Act, Petersen could not recover the balance due from garnishees. Therefore, Action, having no greater rights than Petersen, was not entitled to garnish the funds held by garnishees.

Action has now appealed to this court, where the cases have been consolidated for briefing and argument. Garnishment is a legal, not an equitable, remedy. The factual findings of the trial court in a law action tried without a jury have the effect of a finding by a jury and, on appeal, will not be set aside unless clearly wrong. Boren v. State Farm Mut. Auto. Ins. Co., 225 Neb. 503, 406 N.W.2d 640 (1987).

Action’s first assignment of error relates to the sufficiency of the answers filed by garnishees. Action contends that since the answers of the garnishees did not plead any defense to a claim for damages for breach of contract by Petersen against them, the county court erred in basing its decisions on that ground.

The district court found that the Nebraska Construction Lien Act provided a defense to Action’s attempted garnishments. Action also contends that the answers did not properly raise this defense.

The answers alleged that garnishees were the record owners of the real estate in question, that they entered into a contract with Petersen for construction of a residential duplex which was completed on or about December 28, 1984; that they were protected party contracting owners within the meaning of the Nebraska Construction Lien Act; that they learned in mid-December of 1984 that Petersen had not paid the subcontractors; that at that time there remained $9,600 unpaid on the general contract; that since that date garnishees had made no further payment to Petersen or any of the subcontractors; that garnishees notified all subcontractors of Petersen’s default; that since January 4, 1985, construction liens totaling $37,211.81 had been filed against the real estate; that they held the sum of $9,600 for the benefit of subcontractors and not for the benefit of Petersen; and that by operation of law, the sum of $9,600 was not due Petersen.

“It is not necessary to state a defense in any particular form *800 so long as the facts supporting the assertion are stated.” Cass Constr. Co. v. Brennan, 222 Neb. 69, 73, 382 N.W.2d 313, 317 (1986). Although perhaps not a model of pleading, there were sufficient facts pleaded in the answers to show that the garnishees were not indebted to Petersen.

In their second assignment of error, Action contends that the provisions of the Nebraska Construction Lien Act do not provide garnishees with a defense for nonpayment of the balance due under their contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nore Electric v. S & H Holdings
316 Neb. 197 (Nebraska Supreme Court, 2024)
Lincoln Lumber Co. v. Lancaster
618 N.W.2d 676 (Nebraska Supreme Court, 2000)
Trew v. Trew
558 N.W.2d 314 (Nebraska Court of Appeals, 1996)
Davis Erection Co., Inc. v. Jorgensen
534 N.W.2d 746 (Nebraska Supreme Court, 1995)
Smith v. Smith
517 N.W.2d 394 (Nebraska Supreme Court, 1994)
Otoe County National Bank v. Froelich
448 N.W.2d 917 (Nebraska Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
429 N.W.2d 1, 229 Neb. 796, 1988 Neb. LEXIS 336, Counsel Stack Legal Research, https://law.counselstack.com/opinion/action-heating-air-conditioning-inc-v-petersen-neb-1988.