Davis Erection Co., Inc. v. Jorgensen

534 N.W.2d 746, 248 Neb. 297, 1995 Neb. LEXIS 161
CourtNebraska Supreme Court
DecidedJune 30, 1995
DocketS-93-1073
StatusPublished
Cited by36 cases

This text of 534 N.W.2d 746 (Davis Erection Co., Inc. v. Jorgensen) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis Erection Co., Inc. v. Jorgensen, 534 N.W.2d 746, 248 Neb. 297, 1995 Neb. LEXIS 161 (Neb. 1995).

Opinions

Caporale, J.

I. STATEMENT OF CASE

This garnishment proceeding arises out of the interplay of three construction contracts, one entered into by and between the judgment creditor and garnishor, plaintiff-appellant Davis Erection Co., Inc., and its judgment debtor, defendant-appellee Dana Jorgensen, doing business as Jorgensen Grading; another entered into by and between Jorgensen and the garnishee-appellee Eriksen Construction Co., Inc.; and still another entered into by and between Eriksen Construction and the County of Douglas. Determining that Eriksen Construction was not then indebted to Jorgensen, the district court in effect dismissed the within proceeding. Davis Erection thereupon appealed to the Nebraska Court of Appeals, urging, in summary, that in so ruling, the district court erroneously [299]*299permitted Eriksen Construction to set off against its certain, liquidated, and mature indebtedness to Jorgensen the contingent, unliquidated, and immature claims Eriksen Construction asserts against Jorgensen.’We, on our own motion, removed the matter to this court in order to regulate our caseload and that of the Court of Appeals. We now reverse the judgment of the district court and remand the cause for further proceedings.

II. SCOPES OF REVIEW

Garnishment is a legal action; thus, to the extent factual issues are involved, the findings of the fact finder will not be set aside on appeal unless clearly wrong. See Action Heating & Air Cond. v. Petersen, 229 Neb. 796, 429 N.W.2d 1 (1988). However, to the extent issues of law are presented, we as an appellate court have an obligation to reach independent conclusions irrespective of the determinations made by the court below. See Sylvis v. Walling, ante p. 168, 532 N.W.2d 312 (1995).

m. FACTS

The county’s contract with Eriksen Construction obligated the latter to remove a bridge and build a box culvert under a road. Eriksen Construction contracted part of its obligation to Jorgensen under a document which required Jorgensen to dig the ditch in which Eriksen Construction was to build the culvert, after which Jorgensen was to backfill the ditch with earth, regrade the slopes, build the road, and do other related work. In exchange, Eriksen Construction agreed to pay Jorgensen the “approximate amount of contract $65,064.35 . . . [wjhen and as contract is paid by [the county] with 10% retained until project is accepted by” the county.

In September 1992, one of the slopes caved in during the course of Jorgensen’s work and slid into the excavated area because of the presence of a live spring. Jorgensen advised Eriksen Construction by letter that the unforeseen excavation problem resulted because of the effect the abnormal amounts of precipitation had on the ground water and recommended that additional time and cost be expended to remedy the situation, which it characterized as serious because the walls continued to slide.

[300]*300After Jorgensen found he could not excavate the cave-in, he contracted with Davis Erection to do so. Eriksen Construction then obtained the county’s oral approval for extra compensation and later wrote the county that Jorgensen had secured a contractor to excavate the area and that in accordance with the county’s verbal agreement, a claim for the costs incurred and time lost would be submitted.

Eriksen Construction thereafter billed the county $33,121.63 for the cave-in work, including charges made by Jorgensen in the sum of $1,400 and by Davis Erection in the amount of $13,637.

Following a series of negotiations, the county issued a change order on June 18, 1993, approving payment to Eriksen Construction of $25,967 for the cave-in work. In its view, the remaining portion of Eriksen Construction’s claim represented charges for work contemplated by its original contract with the county. On July 6, 1993, the county drew a warrant directing its bank to issue a $25,967 check to Eriksen Construction. However, Eriksen Construction paid neither Jorgensen nor Davis Erection for the work they did in connection with the change order.

In the meantime, Jorgensen had written Eriksen Construction on June 17, 1993, that the latter’s failure to pay and its failure to require the county to issue a change order constituted a breach of the contract between Jorgensen and Eriksen Construction and that Jorgensen would withdraw his equipment from the jobsite until the change order was executed and payment made.

That same day, Eriksen Construction wrote Jorgensen that all requests had been promptly presented to the county, that no one from Eriksen Construction had given verbal directives to perform extra work, and that Jorgensen had been paid all sums due to him to date. The letter further called Jorgensen’s attention to the provision in their contract providing that “ ‘no extra work shall be allowed or changes made ... or paid for by [Eriksen Construction] unless and until authorized by [Eriksen Construction] in writing before the work and/or changes are begun.’ ” The letter also advised Jorgensen that their contract required him “to be on the jobsite with sufficient [301]*301equipment and manpower to perform the balance of [the] contract . . .

Negotiations between Eriksen Construction and Jorgensen apparently continued, for by letter dated June 18, 1993, Jorgensen advised Eriksen Construction that payment under the change order of $12,437 was acceptable, $11,987 for Davis Erection and $450 for Jorgensen.

Jorgensen testified that he decided not to leave the job, returned to the site, and proceeded to work when the weather permitted. However, on or about June 21, 1993, the owner of the backhoe which Jorgensen had leased terminated the arrangement. Jorgensen needed a backhoe but could not rent one. As a result, Eriksen Construction rented a backhoe for him. Eriksen Construction’s witness testified that normally, an amount for the rental of the backhoe would be withheld from any payment due Jorgensen, but no written agreement regarding the matter was executed. However, Eriksen Construction estimated the total rental cost for the 5-week period Jorgensen kept it to be $9,000. In addition, there was a $3,467 charge for damages to the backhoe.

In the interim, on July 15, 1993, Davis Erection obtained a $15,137.79 default judgment against Jorgensen. Davis Erection thereafter caused issuance of its summons in garnishment, which Eriksen Construction received, along with the order of garnishment and garnishment interrogatories, on July 28, 1993.

During the evening of July 28, Eriksen Construction’s president placed a telephone call to Jorgensen and asked why Eriksen Construction had been served with a garnishment summons. Jorgensen told the president that he could not continue on the job because of the weather, nonpayment under the change order, and “a multitude of things,” including the garnishment. The president requested that Jorgensen put his intentions in a letter.

In a letter dated July 29, 1993, Jorgensen stated that he was not able to complete the remaining work because of the weather, untimely payment under the change order, financial problems, and the legal action instituted against him, and requested that he be released from the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

de Vries v. L & L Custom Builders
968 N.W.2d 64 (Nebraska Supreme Court, 2021)
Strasburg v. Union Pacific RR. Co.
286 Neb. 743 (Nebraska Supreme Court, 2013)
Myers v. Christensen
776 N.W.2d 201 (Nebraska Supreme Court, 2009)
Spaghetti Ltd. Partnership v. Wolfe
647 N.W.2d 615 (Nebraska Supreme Court, 2002)
Lee Sapp Leasing, Inc. v. Ciao Caffe & Espresso, Inc.
640 N.W.2d 677 (Nebraska Court of Appeals, 2002)
Becker v. Hobbs
590 N.W.2d 360 (Nebraska Supreme Court, 1999)
M & D MASONRY, INC. v. Universal Surety Co.
572 N.W.2d 408 (Nebraska Court of Appeals, 1997)
Maziarski v. Bair
924 P.2d 409 (Court of Appeals of Washington, 1996)
Watts v. Watts
547 N.W.2d 466 (Nebraska Supreme Court, 1996)
Koterzina v. Copple Chevrolet, Inc.
542 N.W.2d 696 (Nebraska Supreme Court, 1996)
Kropf v. Kropf
538 N.W.2d 496 (Nebraska Supreme Court, 1995)
Davis Erection Co., Inc. v. Jorgensen
534 N.W.2d 746 (Nebraska Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
534 N.W.2d 746, 248 Neb. 297, 1995 Neb. LEXIS 161, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-erection-co-inc-v-jorgensen-neb-1995.