M & D MASONRY, INC. v. Universal Surety Co.

572 N.W.2d 408, 6 Neb. Ct. App. 215, 1997 Neb. App. LEXIS 168
CourtNebraska Court of Appeals
DecidedDecember 2, 1997
DocketA-96-433
StatusPublished
Cited by3 cases

This text of 572 N.W.2d 408 (M & D MASONRY, INC. v. Universal Surety Co.) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M & D MASONRY, INC. v. Universal Surety Co., 572 N.W.2d 408, 6 Neb. Ct. App. 215, 1997 Neb. App. LEXIS 168 (Neb. Ct. App. 1997).

Opinion

Miller-Lerman, Chief Judge.

Universal Surety Company (Universal) and L.E. Weaver Construction, Inc. (Weaver), defendants below, appeal from an April 11, 1996, order of the district court for Buffalo County, granting summary judgment in favor of M & D Masonry, Inc. (M & D), a Nebraska corporation. Universal and Weaver claim that the trial court erred in granting M & D’s motion for sum *217 mary judgment, seeking judgment in the amount of $33,504.60, and in overruling Universal and Weaver’s motion for summary judgment, asking the trial court to enter judgment in favor of M & D limited to the amount of $11,468. Universal and Weaver claim that M & D’s $33,504.60 claim should be set off by $22,036 and that the trial court erred in striking the $22,036 setoff raised in their joint answer. For the reasons recited below, we reverse, and remand for treatment consistent with this opinion.

BACKGROUND

On July 14, 1995, M & D filed an amended petition against Universal, alleging that Universal was Weaver’s surety on a labor and material payment bond given in connection with a construction subcontract entered into between M & D and Weaver. M & D alleged that it entered into the subcontract with Weaver in August 1993 and that it agreed to perform masonry work for Weaver in connection with a construction project for the Pleasanton Public Schools. M & D alleged that it had properly completed the work at Pleasanton and that Weaver had failed to pay it $33,504.60, the subcontract price. In its petition, M & D prayed for judgment against Universal in this amount.

In its answer filed August 30, 1995, Universal admitted that it had executed a labor and material payment bond as surety for Weaver but denied that Weaver owed M & D $33,504.60. Universal alleged that Weaver had tendered payment in full by issuing to M & D a check for $11,468 and that Weaver had exercised its right to set off $22,036 from the $33,504.60 balance. The alleged setoff arose from another subcontract between M & D and Weaver in connection with a construction project for the Holdrege Public Schools. Universal stated that M & D failed to complete the masonry work under the subcontract for the Holdrege Public Schools in a “workmanlike manner,” that M & D failed to repair the defects after several requests, and that Weaver incurred damages in the amount of $22,036, fixing these defects. Universal alleged that as surety on the bond, it is entitled to all defenses and/or setoffs available to Weaver and prayed that the court allow the setoff and enter judgment in favor of M & D limited to $11,468.

*218 On September 5, 1995, Weaver filed a motion for leave to intervene in which Weaver asked for an order allowing it to enter its appearance and become a party by way of intervention. Weaver requested that the court allow it to assert all defenses and setoffs available at law or in equity and attached a petition of intervention to its motion, setting forth the facts of the alleged setoff and praying that the court allow the setoff and enter judgment in favor of M & D limited to $11,468.

On September 21, 1995, M & D filed a motion to strike the setoff allegations from Universal’s answer, since the setoff did not arise out of or relate to the facts set forth in its petition concerning the Pleasanton Public Schools and because Universal purported to allege a setoff in favor of Weaver, a party other than Universal.

On September 29,1995, M & D filed an objection to Weaver’s motion for leave to intervene, stating that Weaver’s petition for intervention alleged a setoff arising from a separate contract or transaction. In the alternative, M & D moved to strike the setoff allegations from Weaver’s petition in intervention, since those allegations related to a separate and distinct contract or transaction.

In a journal entry filed November 9, 1995, the trial court sustained M & D’s motion to strike, stating that generally a surety, such as Universal, is not allowed to plead a setoff based on a dispute between its principal and the plaintiff and arising from a separate and distinct contract. The court also stated that an intevenor, such as Weaver, was also prohibited from alleging a setoff.

On December 21, 1995, Universal and Weaver filed a motion to join Weaver as a defendant pursuant to Neb. Rev. Stat. § 25-317 (Reissue 1995). In a journal entry filed on January 9, 1996, the trial court granted the motion, and Weaver became an additional defendant. The court granted Weaver 10 days to file an answer. On January 16, Universal and Weaver (hereinafter referred to as the “defendants”) filed a joint answer, alleging that they had a right in the present suit to set off $22,036 of damages arising out of the Holdrege Public Schools subcontract. Additionally, Weaver alleged that it had assigned and transferred to itself and Universal jointly all the rights attached *219 to the $22,036 setoff. The defendants prayed that the court order judgment in favor of M & D limited to the amount of $11,468.

On January 22, 1996, M & D filed a new motion to strike, asking the court to strike the setoff allegations in the defendants’ joint answer. In its motion, M & D claimed that the defendants’ alleged setoff did not refer in an intelligible manner to the claim set forth in M & D’s amended petition and arose from a set of facts unrelated to the facts in its petition.

In a journal entry filed February 23, 1996, the trial court sustained M & D’s motion, striking the portions of the defendants’ joint answer relating to the setoff. The court held that Nebraska has refused to recognize a distinction between a counterclaim and a setoff and further held that a setoff is a form of counterclaim arising in contract and is controlled by Neb. Rev. Stat. § 25-813 (Reissue 1995), which limits counterclaims to actions arising out of the contract or transaction set forth in the plaintiff’s petition. The court also referred to Neb. Rev. Stat. § 25-812 (Reissue 1995), which states that defenses, counterclaims, setoffs, and cross-claims must “refer in an intelligible manner to the cause of action which they are intended to answer.” The trial court further stated that the foregoing language of § 25-812 suggests that a setoff must have a relationship with the plaintiff’s cause of action. The court stated that the defendants’ setoff is not allowable, since it is based upon a separate and distinct contract.

In a reply filed February 29, 1996, M & D denied each and every affirmative allegation in the defendants’ joint answer except those constituting admissions against Universal’s interests.

On February 29, M & D filed a motion for summary judgment, stating that there was no longer a genuine issue of material fact and praying that the court enter a judgment for M & D.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Opinion No. (2000)
Nebraska Attorney General Reports, 2000
County of Cherry v. Tetherow
601 N.W.2d 804 (Nebraska Court of Appeals, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
572 N.W.2d 408, 6 Neb. Ct. App. 215, 1997 Neb. App. LEXIS 168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-d-masonry-inc-v-universal-surety-co-nebctapp-1997.