Early v. Atchison, Topeka & Santa Fe Railway Co.

149 S.W. 1170, 167 Mo. App. 252, 1912 Mo. App. LEXIS 640
CourtMissouri Court of Appeals
DecidedJuly 19, 1912
StatusPublished
Cited by4 cases

This text of 149 S.W. 1170 (Early v. Atchison, Topeka & Santa Fe Railway Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Early v. Atchison, Topeka & Santa Fe Railway Co., 149 S.W. 1170, 167 Mo. App. 252, 1912 Mo. App. LEXIS 640 (Mo. Ct. App. 1912).

Opinion

NORTONI, J.

This is a suit for money had and received.. Plaintiff recovered and defendant prosecutes the appeal. The theory declared upon and pursued is to the effect that defendant obtained-possession of $100', money of plaintiff, through and by means of certain false and fraudulent representations and under such circumstances as affords a promise, by implication of law, to pay the same to plaintiff on demand.

It appears defendant was engaged in reconstructing its railroad dump, and let a considerable portion of the work to Cook & Devine by virtue of a written contract in evidence. This contract authorized a subletting of the work by Cook & Devine, and they in turn let a portion of the grading to plaintiff Thomas F. Early, under a written contract, which is. also in evidence. In both of these contracts — that is, the con[257]*257tract between defendant and Cook & Devine, original contractors, and between Cook & Devine and plaintiff, snb-contractor — it was stipulated that, in event defendant railroad company should be required to pay or compensate any claim asserted against it, which accrued on account of the negligence of such contractor, the railroad company should deduct the same from the amount to be paid to such contractor for the work done. But though such agreement is contained in both contracts, defendant railroad company was authorized to make such deductions only from the amount due the original contractors, Cook & Devine, and it was for them to assert the right against plaintiff, subcontractor, under a like provision in their contract with him.

Some one made an opening in the fence inclosing the railroad right of way immediately adjacent to that portion of the work included in plaintiff’s contract, and a horse owned by one Wilson passed through and came to his death by means of a collision with defendant’s train. It seems the horse was killed about January .26, 1908. On March 31 of that year, plaintiff had completed the work undertaken under his contract, and the final payment due him thereon was estimated by the engineer to be $558,56. Under the contract, it was the duty of defendant to settle with Cook & Devine, the original contractors, for work done, and it was for them in turn to settle with plaintiff subcontractor. Defendant refused to settle with Cook & Devine on the last estimate made March 31, 1908, of $558.56, until there was first deducted therefrom the amount of $100, which it was required to pay for Wilson’s horse killed upon its tracks. Under date of April 20, defendant’s engineer in charge wrote the contractors the following letter, asserting the claim of $100 against plaintiff Early:

[258]*258“Claim of $100 v. Subcontractor Early, April 20, 1908.
“Messrs. Cook and Devine,
“Junction City, Kansas.
“(xentlemen: — Our company has paid a claim of $100 for settlement of stock claim No. 86634 favor of ¥m. Wilson of Hurdland, Mo., which we are positive should he paid by Mr. Early as the animal gained access to the track through a gap in our fence made by Mr. Early and his employees. We, of course, have no contract with .them, and we have to make bill against you. I will be pleased to know if you have made full settlement with Mr. Early and can protect in this matter by our making the bill as above outlined.
“Yours truly,
“ J. W. Meade, Engineer F. G-. D.”

Cook & Devine presented this letter to plaintiff and he declined to accede to the dedtiction of $100 from the amount due him, for the reason, as he asserted, that he was not responsible for the gap in the railroad fence through which the horse entered upon the track. Plaintiff stoutly insisted that the opening in the fence was made by another contractor and that, too, before he came upon the work. It appears that the matter was in dispute between the parties for some time, and, in the interim, defendant’s claim agent called upon and interviewed plaintiff thereabout. During this time plaintiff persistently refused to accede to the request of the contractors, Cook & Devine, and permit them to deduct the $100' demand by defendant, but, finally, in the early part of June, defendant’s claim agent assured him that if he would make such settlement, defendant would pay to him direct the additional $100' if, on thorough investigation, it was revealed that he was not responsible for the opening in the fence. Plaintiff says that upon this assurance he settled with Cook & Devine on June 18, 1908, for $458.56, in full of all claims against them for [259]*259work and labor performed under his contract. Though plaintiff forwarded affidavits by several different parties to defendant to the effect that the gap in the fence was present before he went upon the work and that he was in no way responsible therefor, it nevertheless declined and refused to pay him the remaining $100 due under the final estimate of March 31. After several demands and refusals, plaintiff instituted this suit against defendant for $100, as for money had and received to his use.

Though the petition contains much that is irrelevant to the implied promise raised by the law, it counts, in part, upon the facts above stated, and avers that defendant came into and retained possession of $100 of plaintiff’s means, by and through certain false and fraudulent representations with respect to the fact that he caused the opening in the railroad fence and'thus occasioned the killing of Wilson’s horse, and thereafter induced him to settle with Cook & Devine on a promise that it would pay him the remaining $100 in its hands, if, upon investigation, it appeared that he was not responsible for the gap in the fence.

Manifestly defendant misconceives the theory of the suit and the form of the action, for it earnestly argues that it proceeds entirely as for false and fraudulent representations, and, it is said, the evidence is wholly insufficient to sustain a judgment as for damages accrued on account of fraud and deceit. We are not persuaded to that view, for the suit is obviously one for money had and received. No one can doubt that the action of money had and received is of equitable origin, proceeding from the maxim ex aequo et bono, to the end of affording a remedy for the' recovery of money in the possession of one which in good conscience belongs to another. Because of this the action is favored in the law and it is said the tendency is to widen its scope, for it is recognized to be a flexible form of procedure commingling and ad[260]*260ministering equitable doctrines as well as those of the law. [Houts v. Dunham, 162 Mo. App. 477, 142 S. W. 806, 809; Clifford Banking Co. v. Donovan Com. Co., 195 Mo. 262, 288, 94 S. W. 527; Crigler v. Duncan, 121 Mo. App. 381, 99 S. W. 61; Jenkins v. Clopton, 141 Mo. App. 74, 121 S. W. 759; Moses v. Mcferlan, 2 Burr. 1005.]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

EC Robinson Lumber Co. v. Ladman
255 S.W.2d 72 (Missouri Court of Appeals, 1953)
Walker v. Collins Construction Co.
236 N.W. 334 (Nebraska Supreme Court, 1931)
Lipman, Wolfe & Co. v. Phœnix Assur. Co.
258 F. 544 (Ninth Circuit, 1919)
Heywood v. Northern Assurance Co.
158 N.W. 632 (Supreme Court of Minnesota, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
149 S.W. 1170, 167 Mo. App. 252, 1912 Mo. App. LEXIS 640, Counsel Stack Legal Research, https://law.counselstack.com/opinion/early-v-atchison-topeka-santa-fe-railway-co-moctapp-1912.