Gravett v. Covenant Life Church

841 A.2d 342, 154 Md. App. 640, 2004 Md. App. LEXIS 7
CourtCourt of Special Appeals of Maryland
DecidedFebruary 2, 2004
Docket1430, Sept. Term, 2002
StatusPublished
Cited by2 cases

This text of 841 A.2d 342 (Gravett v. Covenant Life Church) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gravett v. Covenant Life Church, 841 A.2d 342, 154 Md. App. 640, 2004 Md. App. LEXIS 7 (Md. Ct. App. 2004).

Opinion

KRAUSER, J.

Appellant, Benjamin Gravett, individually and trading as Ben Gravett Enterprises, appeals from two orders of the Circuit Court for Montgomery County, one dismissing his petition to establish a mechanic’s lien 1 on property owned by appellee, Covenant Life Church, and the other denying his subsequent “Motion to Reopen the Case to Permit Introduction of Additional Documentary Evidence.”

Gravett is in the business of erecting steel structures for commercial businesses. In June 2001, Gravett contracted with Structural Steel Fabricators, LLC, to assist in the building of an addition to Covenant Life Church. Six months into this subcontract, Gravett sent Covenant Life a notice of his intention to claim a mechanic’s lien, pursuant to Md.Code (1974, Repl.Vol.2003), § 9-104(b) of the Real Property Article (“RP”), asserting that Structural Steel had failed to pay for the work he had performed and the equipment and materials he had supplied in connection with the construction of the Church’s addition. That notice was followed by another, which made essentially the same allegations but reduced the amount owed. Following those two notices, Gravett filed a petition to establish a mechanic’s lien in the circuit court. The petition was dismissed, however, on the grounds that the notices sent by Gravett did not state when Gravett had *642 performed the work or supplied the materials and equipment for the addition, as required by RP § 9-104(b).

In response to the dismissal of his petition, Gravett filed a motion to reopen the case so that he could supply additional information. When that motion was denied, he noted this appeal, presenting the following issues for our review:

I. Did the trial judge abuse his discretion in denying Appellant’s Motion to Reopen the Case, filed solely to admit certified mail receipts, when such additional evidence would have supplemented Appellant’s Affidavit and Notice of Intent to Claim a Lien dated October 31, 2001, already admitted, and which directly addressed the question whether the Notice was actually received by the Appellee?
II. Was the Appellant’s Notice of Intent to Claim a Lien dated December 27, 200[1], 2 together with Appellee’s actual knowledge of prior notice dated October 31, 200[1], legally sufficient under Md. Real Prop. Code Ann., Section 9-104 to require that the Appellee’s Motion to Dismiss be denied?

For the reasons that follow we shall affirm the judgment of the circuit court.

Facts

Covenant Life Church contracted with Hitt Contracting, a general contractor, to build an addition to the church. Hitt then entered into a contract with subcontractor, Structural Steel Fabricators, LLC, to fabricate and erect structural steel, steel joists, and metal decking for that addition. Structural Steel then entered into a subcontract agreement with Gravett to erect the “structural steel” for the project.

On October 31, 2001, Gravett sent, by certified mail, a “Notice of Intention to Claim a Lien” to Covenant Life. That notice stated, in part:

*643 The total amounts earned under the subcontractor’s undertaking to the date hereof is $35^,327.57, of which $163,087.57 is due and unpaid as of the date hereof. The work done or materials provided under the subcontract were as follows: Provide steel for erection of structural steel, joists and deck; furnish and install studs; provide lifting unit with crane; contract extras per work orders.

About two months later, on December 27, 2001, Gravett sent another notice of intention to claim a lien to Covenant Life. That notice stated that “[t]he total amount earned under the subcontractor’s undertaking to the date hereof is $359,530.57, of which $108,290.57 is due and unpaid as of the date hereof.”

Having received no response to either letter, on February 26, 2002, Gravett filed a petition to establish a mechanic’s lien, claiming that “[o]n December 27, 2001, [he] complied with the requirement of Section 9-104 of the Real Property Article by giving Notice upon [Covenant Life Church] of [his] Intention to File Mechanic’s Lien.” The petition stated that the “initial contract price was for $228,650.00,” that he “performed 97 percent of the work contemplated thereby,” and that he “ha[d] billed [Structural Steel] $221,790.50.” It further stated that “written change orders approved by [Structural Steel] for additional work, labor and/or materials total $137,740.07” and that “[t]he total earned under [Gravett]’s subcontract with [Structural Steel] is $359,530.57, of which $108,290.57 is due and unpaid ... for services performed, materials and equipment furnished from July 19, 2001 through December 17, 2001.” It concluded by requesting, among other things, an order establishing a lien against Covenant Life’s property in the amount of $108,290.57.

On May 24, 2002, Covenant Life filed a motion to dismiss Gravett’s petition, asserting that Gravett’s notices 3 were defective because they did “not comply with § 9-104 of the Real Property Article.” It pointed out that Gravett’s notices did *644 not provide “the time when the work was done or the materials furnished” as required by § 9-104(b). 4 About a month later, on July 1, 2002, Covenant Life filed a “Supplemental Motion To Dismiss,” claiming that, in consideration of a $60,000 payment from Hitt Contracting on November 9, 2001, Gravett had “waived and released all claims, which may have existed as of November 9, 2001” against Hitt. “$5,203.00 is the maximum lien amount which Gravett can possibly claim,” Covenant Life stated, because only Gravett’s “$4,573.00 invoice # 6456 dated December 19, 2001 and Gravett’s $630.00 change order request dated December 10, 2001, came after the November 9, 2001 Waiver and Release was signed.”

On July 3, 2002, the circuit court held a hearing on Covenant Life’s motion to dismiss. During argument, the circuit court admitted into evidence Gravett’s sworn affidavit and the October notice. The affidavit stated:

On October 31, 2001, I mailed by certified mail and by first class mail, postage prepaid, a Notice of Intention to Claim a Lien to the Covenant Life Church, at 7501 Muncaster Mill Road, Gaithersburg, Maryland, ... stating an unpaid account due and owing for materials supplied and work performed at the Covenant Life Church ... in the amount of $163,087.57, and copies of which were mailed to each Hitt Contracting, Inc. and Structural Steel Fabricators, LLC.

After hearing argument, the circuit court found that the December 27, 2001 notice was defective and that Gravett was not entitled to a mechanic’s lien. The circuit court explained: “This notice was totally devoid of time, and so there is no basis in looking in the notice to determine when this work was done or materials furnished to see or ascertain from the notice that the property was lienable.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jacksonville MacHine and Repair, Inc. v. Kent Sand and Gravel, LLC
923 A.2d 1023 (Court of Special Appeals of Maryland, 2007)
Martino v. Arfaa
906 A.2d 945 (Court of Special Appeals of Maryland, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
841 A.2d 342, 154 Md. App. 640, 2004 Md. App. LEXIS 7, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gravett-v-covenant-life-church-mdctspecapp-2004.