Cerny Pickas & Co. v. Dallach

249 Ill. App. 424, 1928 Ill. App. LEXIS 76
CourtAppellate Court of Illinois
DecidedJune 20, 1928
DocketGen. No. 32,565
StatusPublished
Cited by2 cases

This text of 249 Ill. App. 424 (Cerny Pickas & Co. v. Dallach) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cerny Pickas & Co. v. Dallach, 249 Ill. App. 424, 1928 Ill. App. LEXIS 76 (Ill. Ct. App. 1928).

Opinion

Mr. Presiding Justice Holdom

delivered the opinion of the court.

The complainant corporation filed its bill in equity against the defendants seeking an accounting and also a mechanic’s lien for the amount claimed to be due by complainant under the contract entered into by it with the defendant Alexander C. Dallach, which involved the furnishing of iron, etc., for defendant Dallach’s theatre at La Grange, Illinois. The items claimed in the bill totalled $15,000 and were claimed to be due for iron work under the contract, overtime work by agreement $1,500, extra or additional work as per account rendered totalling $3,986.34, and defendants are given a credit payment of $12,000 and a credit memorandum for $340, making a total credit of $12,340, leaving the balance due as claimed by complainant of $8,246.34.

Defendants answered the bill denying every item of complainant’s claim. On issues joined the cause was referred to a master who sustained the complainant’s contentions and found that there was due from defendants to complainant the sum of $8,796.09 with interest at the statutory rate from March 1, 1925. Objections to the master’s report were filed before the master, and were overruled. There were exceptions filed before the chancellor to the master’s report, which upon a hearing before the chancellor were all overruled and a decree entered against defendants in favor of complainant for the sum of $9,566.96. From that decree defendants prosecute this appeal.

In this appeal defendants contend and argue for reversal that they are entitled to a deduction from the claim of complainant of the following accounts:

Bonus for prompt delivery............$1,500.00
Allowance for paint on steel after erection ............ 800.00
Allowance for metal doors not furnished 645.00 Allowance for 17,897 pounds of material
at 8%c per pound................... 1,521.25
Allowance for overcharge of 6,545 pounds
of steel at 3c....................... 196.35
•Extras not authorized or ordered by
Dallaeh ............................ 1,021.94
The total of the foregoing items is $5,684.54

and they request that this court reverse the decree and modify it by allowing the credit claimed of $5,684.54. None of the rulings of the master or the court on the remainder of the account is challenged. We shall therefore confine our review to the correctness or not of the foregoing items in the account.

It appears from the master’s report that Alexander C. Dallaeh acted as his own general contractor; that one Edward M. Kralovee, the treasurer of complainant, was in charge of the work for it, and superintended the fabrication and erection of all of said work, both in the shop of complainant and upon the theatre premises; that William J. Sloan was foreman of complainant in charge of installing the iron and steel work upon the theatre building; that by reason of delays caused by Kline, defendants’ structural engineer, in approving shop drawings, delivery by complainant under the contract was delayed; that defendant Alexander C. Dallaeh volunteered to pay an additional sum of $1,500 provided the steel was on the premises on August 27, 1924, and the master further found that the steel work was completed on August 25, 1924, but was not delivered immediately because there was not sufficient unloading space upon the theatre premises to make such deliveries, and for that reason defendant, Alexander C. Dallaeh, waived the actual delivery at that time; that by reason of the excavation having been made “rather early” the setting of° the trusses was delayed until the making of a certain support, and that there was no substantial or further delay in setting the steel work; that complainant kept a sufficient force upon the building as conditions would warrant; and further funds that complainant began work on the contract during the week ending August 2, 1924, and finished the same during the week of November 14, 1924, and that the work was all completed on the last-mentioned date, but that the architectural and ornamental iron work and certain extras were not completed on November 14, 1924, but that the contract work and all extras were furnished by January 7, 1925; that by reason of the change of the elevation of the second floor, the fire escape was necessarily raised and that such necessary adjustment was made by complainant; that this adjustment was completed by complainant on January 30, 1925, and that on that date all of the contract work and extras had been completed by complainant.

And the master further found that complainant had substantially complied with and completed the contract and extras in accordance with the plans and specifications; that the testimony shows inter alia that neither Rupert, defendants’ architect, nor Dallaeh ever made any complaint about the work or material, and that Dallaeh was at the building almost every day; and also found that the $12,000 payment made to complainant on November 15, 1924, was the only payment that was made after completion; and further found that Kralovee requested Rupert to give a final certificate; that Rupert refused to issue a final certificate without the defendant Alexander O. Dallaeh’s consent, and that such consent not being forthcoming no certificate was issued; further found from the evidence that defendant Alexander C. Dallach had arranged with the architect not to issue any certificate or certificates, but to pay out money as authorized by him.

The master also found that the contention of Dallach that the $1,500 additional was not earned because deliveries were not promptly made by complainant, was not well taken; and further found that complaint was not warranted on the facts, and that deliveries were promptly made so far as consistent with conditions created by defendant Alexander C. Dallach or his agents; that as to defendants ’ contention that the steel was not painted after erection, it was not well taken, but on the contrary found that the preponderance of the evidence showed that in the interest of time saving and for the purpose of expedition, it was agreed that certain structural steel was to be painted twice in the shop, thereby eliminating the painting after erection; and further found that in that connection there was no evidence that defendant Alexander C, Dallach had the steel in question painted since erection, but on the contrary the evidence showed that Dallach used the same ever since its erection as prepared and furnished by complainant.

And the master further found that defendant Alexander C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sarnoff v. De Graf Brothers, Inc.
554 N.E.2d 335 (Appellate Court of Illinois, 1990)
Allied Contracting Co. v. Bennett
442 N.E.2d 326 (Appellate Court of Illinois, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
249 Ill. App. 424, 1928 Ill. App. LEXIS 76, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cerny-pickas-co-v-dallach-illappct-1928.