Child v. Blaser

727 P.2d 893, 111 Idaho 702, 1986 Ida. App. LEXIS 457
CourtIdaho Court of Appeals
DecidedSeptember 8, 1986
Docket15961
StatusPublished
Cited by13 cases

This text of 727 P.2d 893 (Child v. Blaser) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Child v. Blaser, 727 P.2d 893, 111 Idaho 702, 1986 Ida. App. LEXIS 457 (Idaho Ct. App. 1986).

Opinion

SWANSTROM, Judge.

This appeal arises from an action filed in 1984 by Barbara Child and Joe Chester against Albert Blaser. Child and Chester sought money damages alleging that Blaser had breached a written agreement made in 1979 by which Blaser was to complete a subdivision and to convey three parcels in the subdivision to Child and Chester. Fol *703 lowing trial, the district court awarded money damages to Child and Chester.

Blaser has appealed, raising numerous issues which we restate as whether the trial court erred in (1) ordering rescission; (2) finding mutual mistake and breach of contract; (3) failing to determine when the breach occurred; (4) denying Blaser’s motion for dismissal of the action; and (5) failing to exclude the testimony of several witnesses and other evidence asserted to be irrelevant to the issues framed in the pleadings. On cross-appeal, Child and Chester contend that the trial court erred in not awarding prejudgment interest as part of its remedy. For reasons stated below we modify and affirm the judgment.

Barbara Child and her son, Joe Chester, first filed a complaint against Albert Blaser in 1977. The essence of the action was to enforce a 1973 earnest money agreement between Blaser and Dalice Chester, Child's ex-husband, providing that in return for plumbing services performed by Dalice and Joe, Blaser would convey three one-acre parcels of land in a subdivision he was developing. Apparently, Joe Chester selected one of those parcels for himself with the agreement of his father. In a divorce settlement Barbara (Chester) Child received the rights to the two parcels chosen by Dalice Chester.

The 1977 action was settled in January 1979 when the parties signed a settlement agreement (the “Agreement”). The Agreement called for Blaser to convey three specific parcels of land — two to Barbara and one to Chester — in exchange for dismissal of the lawsuit. The Agreement also required Blaser to “diligently undertake and consummate such steps as are needed to complete the final approval of said plat and the establishment of said subdivision.” He agreed to furnish title insurance on the three parcels.

Blaser did convey the parcels to Child and Chester, but he encountered numerous difficulties in his attempt to obtain final approval of the subdivision. In 1980, the Ada County Board of Commissioners approved the preliminary plat, subject to several conditions. As of May 1981 all conditions for final approval were satisfied except the conditions relating to street improvements. At the date of the trial, in December 1984, Blaser was still disputing the Ada County Highway District’s condition requiring that the subdivision’s streets be paved. The failure to obtain approval from the highway district precluded filing of the final plat. Consequently, it remained unrecorded at the time of trial. Evidence was presented that the three parcels of land had no marketable value because no building permits could be issued and the parcels could not be sold until the plat is approved and filed.

Following trial the district court found that Child and Chester had fully performed their part of the Agreement, which was to surrender their then existing claims against Blaser. They had allowed the 1977 case to be dismissed for lack of prosecution, pursuant to I.R.C.P. 40(c). The court held that the parties entered into the Agreement under a mutual mistake, erroneously believing that Blaser was in the final stages of establishing the subdivision. The erroneous belief that the final plat soon would be approved and filed was said to be a material fact upon which the contract was based. The court further held that the failure of Blaser to complete and obtain final approval of the subdivision and provide title insurance was a material breach, destroying the entire purpose of the contract. The trial court determined that Child and Chester were entitled to damages — the remedy they sought — equivalent to the fair market value the lots would have had if the subdivision had been completed as promised. However, as a condition for such an award, Child and Chester were required to agree to reconvey the lots to Blaser. They did agree to this condition. Blaser was ordered to pay Child and Chester $41,354.98, representing $39,-000 as the fair market value of the parcels in 1979, assuming the subdivision had been platted and recorded, and $2,354.98 for accrued taxes and water assessments which Child and Chester had paid in the interim.

*704 Based upon his findings of “mutual mistake” the district judge fashioned an equitable remedy in part that could be characterized as a rescission with restitutionary relief. His announced purpose was to put the plaintiffs in as good a position as they would have been in but for the Agreement. This approach has generated many of the issues Blaser has raised on appeal. Basically, we agree with the relief fashioned by the trial judge. Contrary to many of the appellant’s arguments we also agree that the judge had the authority — even the duty — to grant the relief to which Child and Chester were shown to be entitled although they had not demanded such relief in their pleadings. I.R.C.P. 54(c); Barnard & Son, Inc., v. Akins, 109 Idaho 466, 708 P.2d 871 (1985); Cady v. Pitts, 102 Idaho 86, 625 P.2d 1089 (1981). Blaser has also attacked the district judge’s finding that there was a breach of contract. However, we believe that breach of contract— the theory relied on by plaintiffs — is a sufficient basis by itself to support the relief granted. Accordingly, we will bypass a discussion of mutual mistake. We will address the arguments made concerning breach of contract and discuss the remedy furnished for that breach.

I

Blaser’s argument, that the district court erred in finding there was a material breach of contract, has focused almost entirely on the failure to furnish title insurance. Blaser asserts there was no such failure and even if there was, the breach was minor and could be corrected easily by merely awarding Child and Chester the cost of the title insurance policy. We will return to this argument shortly.

Blaser’s narrow argument fails to adequately address the broader finding of the district court. It was Blaser’s failure “to complete and obtain final approval of the subdivision and provide title insurance” which the district court held destroyed the very purpose of the contract. This critical conclusion of the district court is properly based upon findings which are supported by substantial, though disputed, evidence in the record. Blaser expressly agreed to take all necessary steps to “complete the final approval of said plat and the establishment of said subdivision.” The court determined that a reasonable time “for subdividing” did not expire until June, 1982. Thus, contrary to Blaser’s assertions on appeal, the district court did implicitly find when the breach occurred. Blaser was given nearly three and one-half years to “diligently” perform the Agreement made in January, 1979. He has simply not shown that he should be excused from the obligations he expressly undertook in the Agreement.

Nor are we persuaded that Blaser’s failure to furnish title insurance can be excused.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arellano v. State
431 P.3d 828 (Idaho Court of Appeals, 2018)
Silver Creek Seed, LLC v. Sunrain Varieties, LLC
385 P.3d 448 (Idaho Supreme Court, 2016)
Ross v. Ross
178 P.3d 639 (Idaho Court of Appeals, 2007)
Bouten Construction Co. v. H.F. Magnuson Co.
992 P.2d 751 (Idaho Supreme Court, 1999)
Mountain Restaurant Corp. v. Parkcenter Mall Associates
833 P.2d 119 (Idaho Court of Appeals, 1992)
Stoor's Inc. v. Idaho Department of Parks & Recreation
803 P.2d 989 (Idaho Supreme Court, 1990)
Burt v. Clarendon Hot Springs Ranch, Inc.
793 P.2d 715 (Idaho Court of Appeals, 1990)
Schenk v. Smith
793 P.2d 231 (Idaho Court of Appeals, 1990)
Barber v. Honorof
780 P.2d 89 (Idaho Supreme Court, 1989)
Reynolds v. American Hardware Mutual Insurance
766 P.2d 1243 (Idaho Supreme Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
727 P.2d 893, 111 Idaho 702, 1986 Ida. App. LEXIS 457, Counsel Stack Legal Research, https://law.counselstack.com/opinion/child-v-blaser-idahoctapp-1986.