Fairfax v. Ramirez

982 P.2d 375, 133 Idaho 72, 1999 Ida. App. LEXIS 69
CourtIdaho Court of Appeals
DecidedAugust 9, 1999
Docket23888
StatusPublished
Cited by8 cases

This text of 982 P.2d 375 (Fairfax v. Ramirez) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fairfax v. Ramirez, 982 P.2d 375, 133 Idaho 72, 1999 Ida. App. LEXIS 69 (Idaho Ct. App. 1999).

Opinion

SCHWARTZMAN, J.

I.

FACTS AND PROCEDURE

In the spring of 1995, Larry Fairfax performed work on property, as well as on a private road leading to the property, of Timothy and Christine Ramirez. The road, located upon an easement owned by the Ramirezes, crosses a number of neighboring parcels. Fairfax graded and placed gravel on this easement road in order to improve access and enable him to perform the requested work on the property. On the property itself, Fairfax installed a septic tank system, removed rocks and tree stumps, placed gravel on the driveway and dug out and shaped an existing holding pond. The Ramirezes paid for the septic tank system installation in full. However, they refused to pay the charges for work done on the easement road, driveway and holding pond, asserting that they did not have a contract with Fairfax for that work. Instead, they asserted that a neighbor had contracted for the work on the road, that the work on the driveway was done in exchange for labor provided by Tim Ramirez, and that the work on the pond was unauthorized.

Not having been paid, Fairfax filed a lien on the Ramirezes’ property and later filed a foreclosure action on the lien. The attorney hired by Fairfax to represent him in this matter was the same attorney who had previously helped the Ramirezes’ file a declaration of homestead on their property in 1990 in preparation for a bankruptcy filing. The Ramirezes filed an answer pro se, later amended by counsel, which denied that they had a contract with Fairfax for the roadwork. They also filed a cross-complaint which asserted that: 1) the septic tank was improperly installed resulting in damage to the Ramirezes; and 2) Fairfax entered the Ramirezes’ property without permission and damaged their holding pond. Following a bench trial, the district court held that the parties had orally contracted for all of the work performed by Fairfax, and that the septic tank had been properly installed in the location chosen by Tim Ramirez. However, the court found that neither I.C. § 45-501 nor § 45-505 conferred a right to subject the Ramirezes’ property to a lien for any work done on the easement road. Accordingly, although the court awarded Fairfax a judgment for the full amount still owing, 1 the court allowed a lien on the property only for the amount reflecting work done within the bounds of the property, including the driveway loop and pond repair. With respect to the remaining counter-claim, the court found that Fairfax had competently worked on the pond according to an oral contract made with the Ramirezes, thereby denying the Ramirezes any recovery. Finally, the court awarded Fairfax attorney fees pursuant to I.C. §§ 45-513 and 12-120(3).

The Ramirezes filed pro se a notice of appeal from the memorandum decision on the bench trial. Counsel for the Ramirezes also filed a motion for reconsideration and clarification, for which a hearing was held. Following this hearing the district court filed a supplemental opinion in which it found that Fairfax was the trial’s prevailing party and awarded pre-judgment interest on the princi *75 pal judgment pursuant to I.C. § 28-22-104. In a later hearing, the court modified the award of attorney fees, disallowing $603, which was the amount attributable to Fair-fax’s attorney’s time for legal work done on the lien issue. The final judgment reflects an award of $600, plus interest, for work done on the property which is secured by a lien on the property; $3,236, plus interest, for work done on the easement road and not secured by a lien; and $4,886 in attorney fees. 2 Fairfax filed a notice of cross-appeal from this judgment. Counsel for the Ramirezes’ withdrew from the case, and the Ramirezes filed pro se an amended notice of appeal.

II.

STANDARD OF REVIEW

A trial court’s findings of fact “which are supported by substantial and competent, although conflicting, evidence will not be set aside on appeal.” Kootenai Elec. Coop. v. Washington Water Power Co., 127 Idaho 432, 434, 901 P.2d 1333, 1335 (1995). This Court will liberally construe the lower court’s findings of fact in favor of the judgment entered. Id. at 434-35, 901 P.2d at 1335-36. The credibility and weight given to the evidence is in the province of the trial judge as the trier of fact, and the findings made by the trial judge will not be set aside unless clearly erroneous. Id. at 435, 901 P.2d at 1336. With respect to the trial court’s conclusions of law, this Court “is not bound by the legal conclusions of the district court and is free to draw its own conclusions from the facts presented.” Id.

The Highlands, Inc. v. Hosac, 130 Idaho 67, 69, 936 P.2d 1309, 1311 (1997).

III.

ANALYSIS

A. The Ramirezes’ Claims On Appeal

The Ramirezes assert that the district court erred when it found that they had orally contracted with Fairfax for the work done on the easement road, driveway and holding pond. Notwithstanding this assertion, the record reveals substantial and competent evidence to support the trial court’s findings of fact.

Although the Ramirezes dispute the veracity of witnesses who testified that Tim Ramirez agreed to pay for the work completed on the easement road and driveway, the district court disagreed, finding that Fairfax’s “factual presentation is the more believable .” Larry Fairfax and two other men who had worked on the project testified that they heard Tim Ramirez state that he would be responsible for the entire cost of the road work. Furthermore, the district court noted that although Tim Ramirez admitted being told the septic tank would cost only $1,400, he originally attempted to raise $4,000 to fund the project. Finally, in a video tape made by Tim Ramirez, he stated that he “would have paid for it” if more gravel had been placed on the driveway. This substantial and competent evidence supports the district court’s determination that Tim Ramirez contracted with Larry Fairfax for the work done on the driveway and easement road.

The district court also found that the Ramirezes orally contracted with Fairfax for the work done on the holding pond. At trial, Fairfax testified that Tim Ramirez requested that he make the existing holding pond deeper and that he refrain from including a culvert in the pond. On the other hand, Tim Ramirez testified that he never discussed the pond with Fairfax. Instead, he asserted, Fairfax had entered the Ramirez property without permission and destroyed the existing pond, later fixed the damage and then sneaked back onto the property and again destroyed the pond. The district court properly considered the conflicting evidence and found that the credible evidence established that the parties had an oral contract for the work on the pond. It further found that Tim Ramirez’s testimony was “implausible” at best. These findings are also supported by substantial and competent evidence.

*76

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matanky Realty Group, Inc. v. Katris
Appellate Court of Illinois, 2006
Moore v. Omnicare, Inc.
118 P.3d 141 (Idaho Supreme Court, 2005)
Franklin Building Supply Co. v. Sumpter
87 P.3d 955 (Idaho Supreme Court, 2004)
Merrill v. Gibson
87 P.3d 949 (Idaho Supreme Court, 2004)
Roark v. Bentley
86 P.3d 507 (Idaho Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
982 P.2d 375, 133 Idaho 72, 1999 Ida. App. LEXIS 69, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fairfax-v-ramirez-idahoctapp-1999.