Chamberlain v. City of Lewiston

129 P. 1069, 23 Idaho 154, 1912 Ida. LEXIS 96
CourtIdaho Supreme Court
DecidedDecember 21, 1912
StatusPublished
Cited by32 cases

This text of 129 P. 1069 (Chamberlain v. City of Lewiston) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chamberlain v. City of Lewiston, 129 P. 1069, 23 Idaho 154, 1912 Ida. LEXIS 96 (Idaho 1912).

Opinion

AILSHIE, J.

— This action was instituted for the foreclosure of a mechanic’s lien against the property of the city of Lewiston for labor performed and material furnished to J. O. Maxon and C. Henry Payne, original contractors with the city of Lewiston. Maxon and Payne entered into a contract with the city, of Lewiston on the 7th day of September, 1910, wherein and whereby they agreed to construct an extension to the intake pipe to the pumping plant of the water system of the city of Lewiston for a stipulated sum. It appears that the city was the owner of and maintained a waterworks sys[160]*160tern and a pumping plant in the city of Lewiston, the pumping plant being located on the Clearwater river, about one and one-half miles above the point where the Clearwater river flows into the Snake river, and that the city was desirous of extending its pipe-line farther out into the bed of the stream, and for that purpose of laying a new intake pipe and properly guarding and protecting the same. Maxon and Payne gave a bond to the city of Lewiston in the sum of $5,000, executed by sureties, and thereafter entered upon the discharge of their work. In carrying out the contract, they found it necessary to build a coffer-dam in the river, and about the time this dam was completed a freshet occurred in the Clearwater river and the dam and all the work and material was carried away by the flood. The contractors thereupon abandoned the work, and nothing further was done thereafter, and the persons who had performed labor and furnished material in connection with this work or for the completion of this work filed their liens, and in due time actions were prosecuted in the district court, and judgment and decrees were entered in favor of the several parties for the amounts due and appeals have been prosecuted. Four appeals are pending, but the cases were consolidated for the purposes of argument, and one opinion will serve to dispose of all the cases.

In this case the claim is for labor done and performed in the construction of the coffer-dam. The other cases are for materials furnished. A number of questions are presented, and we will deal with them briefly in the order in which they arise.

(1) This action was prosecuted under the provisions of sec. 5111 of the Rev. Codes, which provides as follows:

“Every subcontractor, laborer or other person, who performs labor, or furnishes material, for any original contractor or subcontractor, to be used in the construction, alteration or repair of any building, machinery or other structure, for any county, city, town or school district, has a lien upon such building, machinery or structure, and all the provisions of this [161]*161chapter respecting the securing and enforcing of mechanics’ liens shall apply thereto, so far as applicable.”

See. 5110 of the Rev. Codes defines the right to a lien, and names the persons and conditions under which liens may be had, while see. 5111, as above set out, extends the right of lien to buildings, machinery or structures owned by any “county, city, town or school district.” Appellant contends, however, that the foregoing section was repealed by implication by act of March 13,1909 (1909 Sess. Laws, p. 165), which act provides that where any person enters into a contract with the state, any county, city, town, school or irrigation district, or any quasi-public corporation in the state, for the construction, alteration or repair of any public building, public work or quasi-public work, the contract price of which exceeds the sum of $200, he shall be required before commencing such work to execute the usual penal bond in a sum equaling sixty per cent 'at least of the contract price, etc. Then follows the detail of procedure and order of preference and payment of any claim or judgment obtained on such bond.

It is contended by counsel for appellant that this latter act providing another remedy necessarily repeals the provisions of see. 5111. The contention, however, does not appear sound. The statute of 1909 in no way conflicts with the former statute. It rather seems to be a mere additional and cumulative remedy, and was especially intended to protect the state, city or other municipal corporation. We are bound to assume that when the legislature passed the act of March 13, 1909, they were aware of the provisions of sec. 5111 of the Rev. Codes. Notwithstanding this fact, they embodied no repealing clause in the act of 1909. There is no difficulty about construing the two provisions harmoniously and giving force and effect to both. In such case, the court is not justified in holding the former act invalid or repealed.

The supreme court of California dealt with a somewhat kindred question in Bates v. Santa Barbara County, 90 Cal. 543, 27 Pac. 438, and French v. Powell, 135 Cal. 636, 68 Pac. 92, and held the acts thereunder considered to be merely additional and cumulative remedies.

[162]*162(2) It is next contended that the description contained in the liens, complaints and decrees in these cases is insufficient. The general description used is as follows: “The pumping plant and waterworks system of the city of Lewiston, said waterworks system being located on the south bank of the Clearwater river about iy2 miles above the point where the Clearwater river flows into the Snake river.” It seems to us that there will be no difficulty about locating the waterworks system of the city of Lewiston, and that the description herein would enable an officer to very readily locate and point out the property. This court is presumed to know the geography and political subdivisions of the state (sec. 5950, Rev. Codes), and we are likewise at liberty to take notice of the size and location of the city of Lewiston. It is hardly to be presumed that the city itself owns more than one waterworks system, and so there can be no confusion or uncertainty about locating the system here described and intended. .

In Phillips v. Salmon River etc. Co., 9 Ida. 149, 72 Pac. 886, it was held that a description of the mining claim contained in-a notice of lien in the following language was sufficient: “The mining claim known as the ‘Salem Bar,’ situated on the Idaho side of the main channel of the Snake river one-half mile north or down the river from the mouth of the Grande Ronde, in Nez Perce county, Idaho.” The authorities abundantly sustain us in this view. (Hotaling v. Cronise, 2 Cal. 60; Tibbetts v. Moore, 23 Cal. 208; Tredinnick v. Red Cloud Con. Min. Co., 72 Cal. 78, 13 Pac. 152; Emerson v. Gainey, 26 Fla. 133, 7 So. 526; Durling v. Gould, 83 Me. 134, 21 Atl. 833; Phillips on Mechanics’ Liens, sec. 379; Bloom on Mechanics’ Liens, sec. 404.)

(3) It is contended that since all the work that was done and all the material that was furnished were swept away by the flood or' freshet in the Clearwater river, and there is nothing left either of the work or material, that no lien claim can be sustained. In this connection it is also contended that materials furnished and labor performed in preparatory work, such as false works and a coffer-dam, as was done in this case, and which do not constitute a part of the real work or [163]*163structure as it is intended to stand in the completed form, are not lienable and cannot furnish a basis for liens upon the real estate or the property which it was intended to improve, alter or repair.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Electrical Wholesale Supply Co. v. Nielson
41 P.3d 242 (Idaho Supreme Court, 2001)
Fairfax v. Ramirez
982 P.2d 375 (Idaho Court of Appeals, 1999)
Great Plains Equipment, Inc. v. Northwest Pipeline Corp.
979 P.2d 627 (Idaho Supreme Court, 1999)
Beall Pipe & Tank Corp. v. Tumac Intermountain, Inc.
700 P.2d 109 (Idaho Court of Appeals, 1985)
Chief Industries, Inc. v. Schwendiman
587 P.2d 823 (Idaho Supreme Court, 1978)
Rowen & Blair Electric Co. v. Flushing Operating Corp.
239 N.W.2d 633 (Michigan Court of Appeals, 1976)
Pierson v. Sewell
539 P.2d 590 (Idaho Supreme Court, 1975)
Guyman v. Anderson
271 P.2d 1020 (Idaho Supreme Court, 1954)
Rexburg Lumber Co. v. Purrington
113 P.2d 511 (Idaho Supreme Court, 1941)
Rexburg L. Co. v. Purrington
113 P.2d 511 (Idaho Supreme Court, 1941)
Idaho Lumber & Hardware Co. v. DiGiacomo
102 P.2d 637 (Idaho Supreme Court, 1940)
White v. Constitution Mining & Milling Co.
55 P.2d 152 (Idaho Supreme Court, 1936)
American Tank & Equipment Co. v. T. E. Wiggins, Inc.
1934 OK 661 (Supreme Court of Oklahoma, 1934)
Albuquerque Lumber Co. v. Montevista Co.
38 P.2d 77 (New Mexico Supreme Court, 1934)
Nichols v. Levy
32 P.2d 120 (Nevada Supreme Court, 1934)
People Ex Rel. White v. Storm
287 P. 689 (Idaho Supreme Court, 1930)
Poynter v. Fargo
281 P. 1111 (Idaho Supreme Court, 1929)
Continental Supply Co. v. Geo. H. Greenan Co.
1928 OK 519 (Supreme Court of Oklahoma, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
129 P. 1069, 23 Idaho 154, 1912 Ida. LEXIS 96, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chamberlain-v-city-of-lewiston-idaho-1912.