Paired Pay Inc v. Clearobject Inc

CourtDistrict Court, D. South Carolina
DecidedSeptember 19, 2024
Docket2:22-cv-01013
StatusUnknown

This text of Paired Pay Inc v. Clearobject Inc (Paired Pay Inc v. Clearobject Inc) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paired Pay Inc v. Clearobject Inc, (D.S.C. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT DISTRICT OF SOUTH CAROLINA CHARLESTON DIVISION

PAIRED PAY, INC., ) Plaintiff, ) Counterclaim Defendant, ) Case No. 2:22-CV-1013-RMG ) v. ) ) ORDER AND OPINION CLEAROBJECT, INC., ) ) Defendant, ) Counterclaim Plaintiff, ) Third Party Plaintiff, ) ) v. ) ) BLACK INK TECHNOLOGIES CORP., ) f/k/a BLACK INK TECHNOLOGIES, LLC, ) and PAIRED, INC. ) ) Third Party Defendants. )

Before the Court is Plaintiff and Third-Party Defendants’ (the “Paired Entities”) motion to alter or amend the judgment and for a new trial on punitive damages. (Dkt. No. 193). Defendant ClearObject responded (Dkt. No. 195) and the Paired Entities replied (Dkt. No. 197). For the reasons set forth below, the Court denies the Paired Entities’ motion. I. Background On July 17, 2024, an eight-person jury returned a unanimous verdict finding Defendant ClearObject liable to the Paired Entities for breach of contract and breach of contract accompanied by a fraudulent act. (Dkt. No. 181). The jury awarded $502,420.00 in actual damages to the Paired Entities but declined to grant punitive damages. (Dkt. Nos. 181, 184). 1 II. Legal Standard Federal Rule of Civil Procedure 59 allows a party to move to alter or amend a judgment within twenty-eight days. Fed. R. Civ. P. 59(e). The Court may grant a motion for reconsideration only in limited circumstances: “(1) to accommodate an intervening change in controlling law; (2) to account for new evidence not available at trial; or (3) to correct a clear

error of law or prevent manifest injustice.” Pac. Ins. Co. v. Am. Nat'l Fire Ins. Co., 148 F.3d 396, 403 (4th Cir. 1998). A Rule 59 motion tests whether the Court's initial Order was “factually supported and legally justified.” Hutchinson v. Staton, 994 F.2d 1076, 1081-82 (4th Cir. 1993). Therefore, the Court may decline to reconsider a prior holding that “applied the correct legal standards” and made “factual findings [ ] supported by substantial evidence.” Harwley v. Comm'r of Soc. Sec. Admin., 714 Fed. Appx. 311, 312 (Mem.) (4th Cir. 2018). As a result, Rule 59(e) provides an “extraordinary remedy which should be used sparingly.” Pac. Ins. Co., 148 F.3d at 403. Rule 59 also provides that the Court may “grant a new trial on all or some of the issues”

“to any party” “for any reason for which a new trial has heretofore been granted in an action at law in federal court.” Fed. R. Civ. P. 49(a)(1). A district court must “set aside the verdict and grant a new trial[ ] if ... (1) the verdict is against the clear weight of the evidence, or (2) is based upon evidence which is false, or (3) will result in a miscarriage of justice, even though there may be substantial evidence which would prevent the direction of a verdict.” Minter v. Wells Fargo

2 Bank, N.A., 762 F.3d 339, 346 (4th Cir. 2014) (quoting Knussman v. Maryland, 272 F.3d 625, 639 (4th Cir. 2001)). III. Discussion A. Prejudgment Interest Paired Pay requests the Court amend the judgment to reflect $123,421.51 in prejudgment

interest. (Dkt. No. 193 at 3). ClearObject contends that Paired Pay is barred from recovering such interest where it failed to include a demand for prejudgment interest in its complaint and where the sum due was not ascertainable. (Dkt. No. 195 at 4-5). “The decision whether to award prejudgment interest lies in the discretion of the court.” Security Ins. Co. of Hartford v. Arcade Textiles, Inc., 40 F. App'x. 767, 770 (4th Cir. 2002) (citing Jacobs v. Am. Mut. Fire Ins. Co. of Charleston, 340 S.E.2d 142, 143 (S.C. 1986)). “The proper test for determining whether prejudgment interest may be awarded is whether or not the measure of recovery, not necessarily the amount of damages, is fixed by conditions existing at the time the claim arose.” APAC Carolina, Inc. v. Town of Allendale, S.C., 41 F.3d 157, 165 (4th

Cir. 1994) (quoting Babb v. Rothrock, 426 S.E.2d 789 (S.C.1993)). “Stated another way, prejudgment interest is allowed on a claim of liquidated damages; i.e., the sum is certain or capable of being reduced to certainty based on a mathematical calculation previously agreed to by the parties.” Butler Contracting, Inc. v. Ct. St., LLC, 631 S.E.2d 252, 259 (S.C. 2006). Federal Rule 54(c) does not require that a party include a demand for prejudgment interest in its pleadings. See Fed. R. Civ. P. 54(c) (providing that, aside from a default judgment, “every other final judgment should grant the relief to which each party is entitled, even if the party has not demanded that relief in its pleadings.”).

3 Paired Pay explains that “the amounts on which [it] seeks prejudgment interest are precisely measurable because they are the amounts that Paired Pay actually paid in connection with the ClearObject engagement that the jury found were not owed.” (Dkt. No. 193 at 4) (citing Dkt. No. 193-1 & Trial Ex. Nos. 29, 30, 37, 66, 199, 129)). ClearObject argues that because “the claim involves uncertainty about a contract term, the sum due is not ascertainable [and] pre-

judgment interest is not recoverable.” (Dkt. No. 195 at 5). Of the cases cited by the Parties, the Court finds Vaughn Development, Inc. v. Westvaco Development Corporation to be the most analogous. In that case, the South Carolina Court of Appeals reasoned that “[t]here was an intermediate question that had to be decided before the measure of damages could be ascertained” which precluded an award of prejudgment interest on the damages amount. 642 S.E.2d 757, 759 (S.C. Ct. App. 2007). By contrast, in Smith-Hunter Construction Company v. Hopson, “[t]he measure of recovery was fixed by conditions existing at the time the claim arose” where “[t]he cost of work completed by Builder at the time of Homeowners’ breach of contract were established via Builder’s invoices.” 616 S.E.2d 419, 421 (S.C. 2005). Similarly in Butler

Contracting, Inc. v. Court Street, LLC, “[t]he amount Contractor owed Subcontractor was a certain sum or capable of being reduced to a certainty based on contractual provisions regarding the amount of the original contract, the amount of change orders approved by Contractor, and payments made by Contractor.” 631 S.E.2d 252, 259 (S.C. 2006). That the jury granted damages to Paired Pay corresponding to the amounts paid by Paired Pay to ClearObject does not establish that the measure of recovery was ascertainable at the time Paired Pay’s breach claim arose. APAC Carolina, Inc., 41 F.3d at 165.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Wade
461 U.S. 30 (Supreme Court, 1983)
Security Insurance v. Arcade Textiles, Inc.
40 F. App'x 767 (Fourth Circuit, 2002)
Jacobs v. AMER. MUTUAL FIRE INS. CO. OF CHARLESTON
340 S.E.2d 142 (Supreme Court of South Carolina, 1986)
Babb v. Rothrock
426 S.E.2d 789 (Supreme Court of South Carolina, 1993)
Butler Contracting, Inc. v. Court Street, LLC
631 S.E.2d 252 (Supreme Court of South Carolina, 2006)
Vaughn Development, Inc. v. Westvaco Development Corp.
642 S.E.2d 757 (Court of Appeals of South Carolina, 2007)
Denise Minter v. Wells Fargo Bank, N.A.
762 F.3d 339 (Fourth Circuit, 2014)
Harris v. L & L Wings, Inc.
132 F.3d 978 (Fourth Circuit, 1997)
Knussman v. State of Maryland
272 F.3d 625 (Fourth Circuit, 2001)
APAC Carolina, Inc. v. Town of Allendale
41 F.3d 157 (Fourth Circuit, 1994)
Hutchinson v. Staton
994 F.2d 1076 (Fourth Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Paired Pay Inc v. Clearobject Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paired-pay-inc-v-clearobject-inc-scd-2024.