Quality Lawn Care and Landscaping, Inc. v. Coogler Construction Company, Inc.

CourtCourt of Appeals of South Carolina
DecidedJune 2, 2021
Docket2018-001156
StatusUnpublished

This text of Quality Lawn Care and Landscaping, Inc. v. Coogler Construction Company, Inc. (Quality Lawn Care and Landscaping, Inc. v. Coogler Construction Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quality Lawn Care and Landscaping, Inc. v. Coogler Construction Company, Inc., (S.C. Ct. App. 2021).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 268(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA In The Court of Appeals

Quality Lawn Care and Landscaping, Inc. d/b/a Design South Landscape Co., Appellant,

v.

Coogler Construction Company, Inc., Respondent.

Appellate Case No. 2018-001156

Appeal From Richland County Joseph M. Strickland, Master-in-Equity

Unpublished Opinion No. 2021-UP-191 Heard February 11, 2021 – Filed June 2, 2021

AFFIRMED

Thomas Jefferson Goodwyn, Jr., of Goodwyn Law Firm, LLC, of Columbia, for Appellant.

Edward Wade Mullins, III, of Bruner Powell Wall & Mullins, LLC, of Columbia, Respondent.

PER CURIAM: Quality Lawn Care and Landscaping, Inc. d/b/a Design South Landscape Company (Quality) appeals the master-in-equity's order finding it breached its contract with Coogler Construction Company, Inc. (Coogler) by building a retaining wall in the wrong location. Quality also asserts that even if it did breach the contract, the master erred in ordering it to pay for the removal and reconstruction of the entire wall. We affirm.

FACTS/PROCEDURAL HISTORY

This action deals with the construction of a retaining wall for an apartment complex. Edward Rose Development Company, LLC (Rose) was the owner and the general contractor of the overall project, and Coogler was one of Rose's subcontractors. Coogler subcontracted with Quality for the construction of certain retaining walls. Quality and Coogler entered into a contract after Quality submitted a construction bid to build the walls and Coogler accepted the bid.1 Quality built two segmental retaining walls, one of which (Wall H) is the subject of this dispute.

Rose hired a surveyor, and the surveyor used a Computer Assisted Drawing (CAD) to mark Wall H's location by placing stakes that told Quality how far away the top of the wall was supposed to be from the stake. The bid submitted by Quality and accepted by Coogler did not provide the terms for how Quality would build Wall H. However, the parties agreed that Quality was responsible for placing Wall H based off of the surveyor's stakes. After Quality finished building Wall H, workers building an adjacent parking lot discovered Wall H was too close to the lot and consequently, the lot could not be placed in its designed location. The surveyor determined the coordinates of Wall H and created an as-built drawing comparing Wall H's actual location to its designed location on the CAD file. The as-built drawing showed Wall H deviated from the design for the majority of its length, and was between 1.3 feet to 3.8 feet closer to the parking lot at various points.

Rose refused to accept Wall H because it was not in the correct location. Rose demanded that Coogler tear the wall down and rebuild it in the correct location, or it would hire another subcontractor and charge Coogler. Coogler informed Quality that Wall H had to be removed and rebuilt, and Quality refused. Coogler then removed Wall H and hired another subcontractor to rebuild it. Coogler did not pay Quality for the original construction of Wall H.

Quality filed a complaint alleging Coogler breached their contract by failing to pay Quality for building Wall H. Coogler answered and counterclaimed, asserting Quality breached the contract by building Wall H in the wrong place and refusing

1 Quality subsequently amended the bid to increase the contract price after the parties agreed to expand Quality's obligations regarding the retaining walls. to rebuild it. The master found Quality breached the contract and entered a judgment in Coogler's favor in the amount of $64,752.55.2 This appeal followed.

STANDARD OF REVIEW

"An action for a breach of contract is an action at law." Palmetto Mortuary Transp., Inc. v. Knight Sys., Inc., 424 S.C. 444, 452, 818 S.E.2d 724, 729 (2018). When such an action "is tried without a jury, the [master's] findings of fact will be upheld on appeal . . . unless [they are] wholly unsupported by the evidence or unless it clearly appears the findings were influenced or controlled by an error of law." Butler Contracting, Inc. v. Court St., LLC, 369 S.C. 121, 127, 631 S.E.2d 252, 255–56 (2006). "In a law case tried without a jury, questions regarding the credibility and the weight of evidence are exclusively for the [master]." In re Est. of Anderson, 381 S.C. 568, 573, 674 S.E.2d 176, 179 (Ct. App. 2009) (quoting Golini v. Bolton, 326 S.C. 333, 342, 482 S.E.2d 784, 789 (Ct. App. 1997)). The appellant bears the burden of showing the master erred. Ehlke v. Nemec Constr. Co., 298 S.C. 477, 481, 381 S.E.2d 508, 510 (Ct. App. 1989).

LAW/ANALYSIS

"The elements for a breach of contract are the existence of a contract, its breach, and damages caused by such breach." Johnson v. Little, 426 S.C. 423, 428, 827 S.E.2d 207, 210 (Ct. App. 2019) (quoting Hotel & Motel Holdings, LLC v. BJC Enters., LLC, 414 S.C. 635, 652, 780 S.E.2d 263, 272 (Ct. App. 2015)).

The parties did not dispute the existence of a contract. Quality submitted a bid to build retaining walls and Coogler accepted that bid. The parties agreed that Quality would build Wall H based on the surveyor's stakes, and Quality built Wall H. See Miller v. Dillon, 432 S.C. 197, 208, 851 S.E.2d 462, 468 (Ct. App. 2020) ("The necessary elements of a contract are an offer, acceptance, and valuable consideration." (quoting S. Glass & Plastics Co. v. Kemper, 399 S.C. 483, 491, 732 S.E.2d 205, 209 (Ct. App. 2012))). Therefore, the only issues are breach and damages.

2 This amount is the difference between the cost Coogler incurred in removing Wall H and paying another subcontractor to reconstruct it and its contract price with Quality, plus other charges irrelevant to this appeal. I. Breach of Contract

Quality argues the master erred in finding it breached the contract, asserting the surveyor erred in marking the location of Wall H. We disagree. Relying on the as-built drawing, the master found Wall H was between 1.3 feet and 3.8 feet closer to the parking lot than designed. The parties offered conflicting evidence as to whether the error was the result of work done by Quality or the surveyor. After hearing and reviewing all the evidence, the master found the wall being built in the wrong location was due to mistakes made by Quality. The record supports the master's finding. The surveyor testified he correctly marked Wall H's location. Photographs showed the wall was not placed in accordance with the surveyor's stakes, which caused the deviation from its designed location. See Butler Contracting, 369 S.C. at 127, 631 S.E.2d at 255–56 ("In an action at law, when a case is tried without a jury, the [master's] findings of fact will be upheld on appeal . . . unless [they are] wholly unsupported by the evidence or unless it clearly appears the findings were influenced or controlled by an error of law."); Est. of Anderson, 381 S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Branche Builders, Inc. v. Coggins
686 S.E.2d 200 (Court of Appeals of South Carolina, 2009)
In Re Estate of Anderson
674 S.E.2d 176 (Court of Appeals of South Carolina, 2009)
Stanley Smith & Sons v. Limestone College
322 S.E.2d 474 (Court of Appeals of South Carolina, 1984)
Butler Contracting, Inc. v. Court Street, LLC
631 S.E.2d 252 (Supreme Court of South Carolina, 2006)
Ehlke v. NEMEC CONSTRUCTION COMPANY, INC.
381 S.E.2d 508 (Court of Appeals of South Carolina, 1989)
Golini v. Bolton
482 S.E.2d 784 (Court of Appeals of South Carolina, 1997)
Johnson v. Little
827 S.E.2d 207 (Court of Appeals of South Carolina, 2019)
Southern Glass & Plastics Co. v. Kemper
732 S.E.2d 205 (Court of Appeals of South Carolina, 2012)
Hotel & Motel Holdings, LLC v. BJC Enterprises, LLC
780 S.E.2d 263 (Court of Appeals of South Carolina, 2015)
Palmetto Mortuary Transp., Inc. v. Knight Sys., Inc.
818 S.E.2d 724 (Supreme Court of South Carolina, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Quality Lawn Care and Landscaping, Inc. v. Coogler Construction Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/quality-lawn-care-and-landscaping-inc-v-coogler-construction-company-scctapp-2021.