George Ainslie & Co. v. Bertha Kohn & Thompson, De Hart & Co.

19 P. 97, 16 Or. 363, 1888 Ore. LEXIS 62
CourtOregon Supreme Court
DecidedJune 7, 1888
StatusPublished
Cited by28 cases

This text of 19 P. 97 (George Ainslie & Co. v. Bertha Kohn & Thompson, De Hart & Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George Ainslie & Co. v. Bertha Kohn & Thompson, De Hart & Co., 19 P. 97, 16 Or. 363, 1888 Ore. LEXIS 62 (Or. 1888).

Opinions

Thayer, J.

This appeal is from a decree of the Circuit Court for the county of Multnomah, rendered in a suit in which said George Ainslie & Co. were plaintiffs, and James Loynachan, Bertha Kohn, Thompson, De Hart & Co., J. C. Bayer, and John Turnbull were defendants. The suit was brought to foreclose a mechanic’s lien which the plaintiffs claimed to have upon certain premises, situated in the city of Portland, owned by said Bertha Kohn. '

They alleged in their complaint in the suit in substance that during the month of June, 1885, the defendant Loynachan was building and constructing a double-tenement house for said Bertha upon the premises referred to, and that during such times, including the time between the first and eighteenth days of said month, and while said house was in course of construction, they furnished, sold, and delivered to said Loynachan, upon a contract they made with him, doors, sash, and other material, and did certain glazing and mill work for the completion of the said house, amounting in value to the aggregate sum of $683; that the said material was furnished and said work done, from time to time, as required in the construction of the house, up to and including the eighteenth day of June, 1885, at which time said Loynachan completed said building; that the said material so furnished and work done were used and entered into the construction of the said house, and became a part of it; that the plaintiffs, on the seventh day of July, 1885, and within thirty days after the completion of said building, and within thirty days after they had ceased to furnish said material and do said work therefor, duly filed with the clerk of Multnomah County a claim containing a true statement of their said demand, after deducting all just credits and offsets, and containing the other matters required by law to be stated, which claim was duly verified, and which the said clerk duly recorded in the proper book kept by him in his office for that purpose. They also alleged in the complaint that the defendants, Thompson, De Hart & Co., Bayer, and Turnbull, had, or claimed to have, some claim or lien upon said premises.

[365]*365The latter defendants severally filed answers in said suit, setting forth the nature of the liens claimed by them respectively. Said Thompson, He Hart & Co. alleged in their answer in substance that on and between the sixteenth day of March and the seventeenth day of June, 1885, and while said defendant Loynachan was building and constructing the house mentioned and referred to in said complaint, they furnished, sold, and delivered to said Loynachan, to be used in the construction and creation of said building,«certain material, of the reasonable and agreed value of $263.53, which sum he promised and agreed to pay them upon the delivery thereof; that said material was furnished from time to time as required in the construction of the building, up to and including the seventeenth day of June, 1885, at which time it was completed; that the said material was used and entered into the construction of the building and became a part of it; that no part of said $263.53 had been paid; that said defendants, on the twenty-fifth day of June, 1885, filed with the clerk of Multnomah County, in due form, a claim for said amount, with a statement containing a notice of intention to hold a lien upon said premises for its payment, and that said clerk duly recorded said claim in a book kept for that purpose in his office. The other defendants referred to claimed in their answers liens upon the said premises for work and material furnished by them respectively in the construction of said house; but as their claims are not in question on this appeal it is not necessary to mention the facts set out therein.

The defendant Bertha Kohn filed an answer to the complaint, in which she denied that said Loynachan was constructing the house for her in June, 1885, or that plaintiffs furnished any material or work for said house later than June 1st of that year; and she denied any knowledge or information sufficient to form a belief as to whether any statement or notice of claim against the premises was filed with the clerk of said county of Multnomah. She alleged in her answer that the said house was built under a contract entered into between her and said Loynaehan March 2,1885, and was completed prior to June 1st of that year, and that she never received any notice of plaintiffs5 claim.

[366]*366The ease was referred to a referee to find the facts and conclusions of law, and the referee appointed for that purpose found against said plaintiffs, and also against the said defendants, Thompson, De Hart & Co., and his report thereon having been confirmed by the said Circuit Court, the decree was entered in accordance therewith, from which the said appeal is taken. The proofs submitted to the referee showed that said Loynachan, on the second day of March, 1885, agreed in writing with Mrs. Kohn to furnish all the various kinds of materials and labor (except plumbing and gas fitting, staining, varnish, painting, graining, sewers, drains, lathing, and plastering) necessary to erect and completely finish the building referred to in the pleadings. The work was to be under the superintendence of architects, was to be pushed fast enough to insure its final completion by the 1st of June, 1885, and Loynachan was to pay five dollars for each day delayed beyond that time.

The contract price was $3,695, to be paid in four installments as the work progressed; the last one, $1,295, was to be made when the building was entirely finished and accepted by Mrs. Kohn, or the superintending architect for her. The architect had power to stop and report any work or materials not in accordance with the drawings and specifications. Loynachan commenced the work as agreed upon in the writing, and on the third day of March, 1885, entered into a contract with the plaintiffs that they should furnish the mill work, glass, and do the glazing on said house for $1,268, $600 to be paid after delivery of the cornice lumber, the brackets, window frames, and outside finish, the balance after the completion of the building. The plaintiffs furnished the said mill work, and did the glazing for the house under the said contract with Loynachan, between the 3d of March and the 1st of June, 1885, excepting that light was put in the transom, and the seat on the water-closet was changed by Loynachan at the direction of the architect, and .finished by plaintiffs after June 1st of said year. Loynachan paid plaintiffs on account upon said contract on the fourth day of May, 1885, $600. The plaintiffs furnished two openings of inside blinds, and changed the front doors to glass, in addition [367]*367to the material furnished under the contract, which material went into said house, and was of the value of $15.19, and which was done prior to June 1st, 1885. The plaintiffs filed with the county clerk of Multnomah County, Oregon, on July 7th, 1885, a statement of a claim for materials furnished in the construction of said house, for said $668, balance, and for $15.19, said extra material furnished, which was duly recorded as alleged in their complaint.

The defendants, Thompson, De Hart & Co., furnished said Loynachan hardware, between the sixteenth day of March and the seventeenth day of June, 1885, of the value of $263.53, which the latter used in the construction of said house under his said contract with Mrs. Kohn, and on the twenty-fifth day of June, 1885, .filed a statement of their claim against the said premises therefor, which was duly recorded as alleged in their answer in the suit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fircrest Supply, Inc. v. Plummer
634 P.2d 891 (Court of Appeals of Washington, 1981)
State Ex Rel. Town Concrete Pipe, Inc. v. Andersen
505 P.2d 1162 (Oregon Supreme Court, 1973)
Stephenson v. Ketchikan Spruce Mills, Inc.
412 P.2d 496 (Alaska Supreme Court, 1966)
Drake Lumber Co. v. Lindquist
170 P.2d 712 (Oregon Supreme Court, 1946)
Heacock Sash & Door Co. v. Weatherford
294 P. 344 (Oregon Supreme Court, 1930)
Paget v. Peters
289 P. 1119 (Oregon Supreme Court, 1930)
George v. Oregon, California & Eastern Railway Co.
247 P. 780 (Oregon Supreme Court, 1926)
James A. C. Tait & Co. v. Stryker
243 P. 104 (Oregon Supreme Court, 1926)
Christman v. Salway
205 P. 541 (Oregon Supreme Court, 1922)
Craig v. Crystal Realty Co.
173 P. 322 (Oregon Supreme Court, 1918)
St. Johns Lumber Co. v. Pritz
146 P. 483 (Oregon Supreme Court, 1915)
Zanello & Son v. Portland Central Heating Co.
139 P. 572 (Oregon Supreme Court, 1914)
Wills v. Zanello
117 P. 291 (Oregon Supreme Court, 1911)
Coffey v. Smith
97 P. 1079 (Oregon Supreme Court, 1908)
Turner v. St. John
77 N.W. 340 (North Dakota Supreme Court, 1898)
Fitch v. Howitt
52 P. 192 (Oregon Supreme Court, 1898)
Avery v. Butler
47 P. 706 (Oregon Supreme Court, 1897)
Inman v. Henderson
45 P. 300 (Oregon Supreme Court, 1896)
Chamberlain v. Hibbard
38 P. 437 (Oregon Supreme Court, 1894)
Pain v. Isaacs
38 P. 1038 (Washington Supreme Court, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
19 P. 97, 16 Or. 363, 1888 Ore. LEXIS 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-ainslie-co-v-bertha-kohn-thompson-de-hart-co-or-1888.