Wills v. Zanello

117 P. 291, 59 Or. 291, 1911 Ore. LEXIS 141
CourtOregon Supreme Court
DecidedJuly 25, 1911
StatusPublished
Cited by9 cases

This text of 117 P. 291 (Wills v. Zanello) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wills v. Zanello, 117 P. 291, 59 Or. 291, 1911 Ore. LEXIS 141 (Or. 1911).

Opinion

Mr. Justice Bean

delivered the opinion of the court.

The complaint is in the usual form. The defendants, by their answer, allege that no more than 562,614 bricks were delivered by plaintiff and used in the building, amounting to $4,500.11, upon which they were entitled to a credit of $12, and deny the allegation as to attorneys’ fees.

1. The first question for determination is raised by the demurrer to the complaint, and the testimony in the case. The defendants contend that the lien was not filed within 30 days after the material was furnished, as provided by Section 7420, L. O. L., nor within 30 days after the completion of the building, according to the time stipulated in such section, together with Section 7425, L. O. L., yet contend that it was filed prematurely, being filed “before the completion of the building.

From the evidence it appears that the plaintiff commenced to deliver the brick about August 12, 1909, finishing his delivery thereof about September 27, 1909. The brick work was completed about October 13, 1909, and [293]*293the lien was filed on December 3, 1909, before the building was fully constructed. Construing together the two sections of the statute above alluded to, this Court has held that the laborer or materialman must file his lien within 30 days after the completion of the building, not necessarily within 30 days from the date of ceasing to furnish labor or materal. Ainslie v. Kohn, 16 Or. 363 (19 Pac. 97); Coffey v. Smith, 52 Or. 538 (97 Pac. 1079). The defendants claim that this lien was not filed within either of these sections; that is, that between the time allowed for filing, within 30 days from the time of furnishing the material and before the commencement' of 30 days after the completion of the building, there was a hiatus, during which period such lien could not be filed. In Ainslie v. Kohn, 16 Or. 363 (19 Pac. 97), it is.said that whether the claim was filed within 30 days after the work and material were furnished was unimportant, provided it was done within 30 days after the completion of the building. In this contention counsel for defendants relies upon the rule laid down in Roylance v. San Luis Hotel Company, 74 Cal. 273, at page 277 (20 Pac. 573, at page 575), but an examination of the opinion in that case, indicates that it is based upon a statute differing from ours. The reason for not allowing the lien to be filed prior to the completion of the building being that, “under the contract between the owner and the contractor, the owner agrees to pay the contractor a certain sum for constructing the building, and this sum is a fund which may be held under the statutes for the payment, so far as it will go, of all the claims of all the various subcontractors, for work and materials furnished by them to the contractor, who is the principal and head of all; and all the parties entitled to payment or contribution out of this fund should be able to reach the fund and get their proportionate shares thereof at the same time or within the same period of time.” From [294]*294the language used it would appear that this rule, following that prescribed in Davis v. Bullard, 32 Kan. 234 (4 Pac. 75); Seaton v. Chamberlain, 32 Kan. 239 (4 Pac. 89), and contained in Section 1428, 2 Jones, Liens, is applicable to a different statute than ours. Jones, Liens, § 1432, states that, “Where there are distinct contracts for different parts of a building, as for instance one contract to do all the stone work and to furnish all the material for the same, and another contract for the brick work, and another for the wood work, each contract must stand upon its own merits, and liens under the different contracts must be filed within the time limited .from the time of the completion of the work under each contract.” This .work is instructive, but neither of the sections referred to apply to our statute.

As to the necessity for prompt enforcement, it is said in Phillips, Mechanics’ Liens, § 322:

“It has been the policy of nearly every state which has established a system of mechanic’s lien to protect the rights of owners and others who may become interested in the property, by requiring those who are entitled to its benefits to be prompt in the enforcement of their claims. The privileges secured mechanics and material-men are unusual in their character, effective and sometimes oppressive in their behalf, and it is only just that they should be required to be diligent in their enforcement.”

This reasoning and a careful examination of our statute would indicate that the lien for materials can be filed at any time after the furnishing of the last material, and before the expiration of 30 days from the completion of the building, when the materials for its construction is furnished to the contractor or subcontractor in charge thereof, who, by Section 7416, L. O. L., “shall be held to be the agent of the owner for the purposes of this act.” Such we think, under the decisions construing the above mentioned statutes in Ainslie v. Kohn, 16 Or. 363 (19 Pac. 97), and Coffey v. Smith, 52 Or. 538 (97 Pac. [295]*2951079), was the legislative intent. To hold that one furnishing material to the person having the contract for the brick work of a building must, before filing his lien, wait until the other contractors — the carpenter, tinner, plumber and painter — finish their contracts, and the building is completed (which is often a question of dispute) and thereby limit his time for such filing to 30 days thereafter, would in our opinion nullify a part of the provisions of the statute.

2. As to the amount in controversy, the evidence relative thereto does not appear to be in conflict, except as to the manner of arriving at the number of bricks furnished. The plaintiff and his foreman testify that the brick was loaded in the yard and started for the car barns under the supervision of the foreman, who kept a record thereof in the form of small stub books of about 100 tickets, of which there were an original, duplicate and triplicate. When a load was sent out one of these tickets was filled with the number of bricks forwarded, nearly every load containing 1,950 bricks. The duplicate and triplicate were then given to the teamster, one to be left at the place of delivery, and the other signed by the person to whom the bricks were delivered and then returned to plaintiff, who from the stub of his ticket book each day copied on tally sheets, from which he made up his account of 623,300 delivered bricks. After the completion of the brick work the plaintiff and defendants agreed to, and did, “lump off” the brick remaining unused, estimating the number at 20,000. If it was understood or expected by either of the parties that the brick would be estimated from the number in the walls of the building after its completion there would have been no necessity for “lumping off,” or estimating such unused brick. When a wagon was filled it appears the number of bricks therein could be easily estimated. About two-thirds of the tickets were signed by the defendants or their foreman, and returned to plaintiff. The receipts for 97 loads, [296]*296hauled before defendants began construction, were unsigned for the reason that when delivery was made there was no one there to sign them. The plaintiff and his foreman testify that the record of these loads was kept in the same manner as that of the others.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Nilsen v. Hoff
474 P.2d 11 (Court of Appeals of Oregon, 1970)
State Highway Commission v. Kendrick
363 P.2d 1078 (Oregon Supreme Court, 1961)
Heacock Sash & Door Co. v. Weatherford
294 P. 344 (Oregon Supreme Court, 1930)
Nicolai-Neppach Co. v. Poore
251 P. 268 (Oregon Supreme Court, 1926)
Manley Auto Co. v. Jackson
237 P. 982 (Oregon Supreme Court, 1925)
State v. Ganong
184 P. 233 (Oregon Supreme Court, 1919)
Columbia River Door Co. v. Todd
175 P. 443 (Oregon Supreme Court, 1918)
Peerless Pacific Co. v. Rogers
158 P. 271 (Oregon Supreme Court, 1916)
Arctic Lumber Co. v. Borden
211 F. 50 (Ninth Circuit, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
117 P. 291, 59 Or. 291, 1911 Ore. LEXIS 141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wills-v-zanello-or-1911.