Seaton v. Chamberlain

32 Kan. 239
CourtSupreme Court of Kansas
DecidedJanuary 15, 1884
StatusPublished
Cited by6 cases

This text of 32 Kan. 239 (Seaton v. Chamberlain) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seaton v. Chamberlain, 32 Kan. 239 (kan 1884).

Opinion

The opinion of the court was delivered by

Hurd, J.:

The plaintiff in error commenced his suit in the district court of Harvey county, to recover from defendant Chamberlain the value of material furnished and used in building a county jail for Harvey county, and to have the same adjudged a lien against the jail and land on which it is situate, and to foreclose the lien, and for the sale of the property.

The allegations of the petition in the court below are in substance that on the first of March, 1880, the board of county commissioners of Harvey county entered iuto a written contract with the defendant Chamberlain for the construction and completion of a county jail on the lands of the county, in Newton, a copy of which is attached to and made a part of the petition; that by the terms of the contract, Chamberlain [240]*240was to furnish all material and perform all work and labor necessary to erect and complete the jail, for the sum of $5,975, to be paid in the manner specified in the contract; that about the — day of-, 1880, Chamberlain began work on the jail building, and completed it according to contract on or about the 20th day of March, 1881; that about March 20, 1880, the plaintiff entered into a verbal contract with Chamberlain, by which he agreed to furnish the iron work necessary to be used in the construction of the building under the contract between Chamberlain and the board of county commissioners, at and for the sum of $620; that he had furnished the iron work as agreed, and that it was used in the construction of the jail and incorporated into and became a part of it, and that the defendant board of county commissioners has refused to pay him therefor, and that he is entitled to recover from Chamberlain $620 and interest from February 2, 1881; that on April 5, 1881, he filed his statement in due form for a lien as sub-contractor, in the office of the clerk of the district court of Harvey county, and thereby claimed a lien for the ■contract price of the iron work upon the jail building, and the tract of land upon which it is situate; and demands judgment against Chamberlain for $620 and interest, and that it be declared a lien upon the jail so erected and constructed, and the tract of land on which it is situated, and that the lien be foreclosed and the land sold in payment of that sum and interest. Chamberlain did not appear or answer.

The defendant county board answered, setting up five defenses.

The first admits the corporate existence of Harvey county; that defendant board, on March first, 1880, entered into a contract in writing with Chamberlain for the erection of the county jail on the premises described in the petition, and that the contract set out as the exhibit to the petition is correct as far as it goes, and that the board had refused to pay the plaintiff^ demand against Chamberlain, or any part of it, and denies each and every other allegation of the petition.

The second defense states that in addition to the contract, [241]*241as set out in the petition and as a part of it, were certain plans and specifications, a copy of which is attached and made a part of this defense, and then states that Chamberdain did not complete the building within the time nor in the manner in the contract specified; and because of his failure to carry out the contract the county was damaged in the sum of $3,000, and claims to deduct that amount from the contract price.

The third defense states that if the plaintiff contributed material to the erection of said jail and it was so used, it was wholly unfit for the purpose, and was not worth more than $100.

The fourth defense states that the building was never completed according to the contract, but that at the time plaintiff says he filed the lien sought to be foreclosed in this suit, work was still going on, and continued to go on during that year until the building was abandoned, on the first day of October, 1881, and possession taken by said defendant board.

Fifth defense: No question is made in this court on this defense, and it is not necessary to give its contents.

The plaintiff demurred to the second, fourth and fifth grounds of defense of the answer of the defendant board, on the ground that neither of such defenses states facts sufficient to constitute a defense to this action. The demurrer was sustained by the court as to the second and fourth defenses, and overruled as to the fifth. The plaintiff filed his reply to the third and fifth defenses, denying every allegation thereof.

At the September term, 1883, of the district court of Harvey county, the cause was tried by the court without a jury, and the court made separate findings of fact and conclusions of law, which are as follows:

“At the request of the parties hereto, the court makes the following findings of fact and conclusions of law in the above-entitled case:
“1st. That Harvey county, Kansas, is the owner of the north half of block No. 22, in the city of Newton, Harvey county, Kansas, and has dedicated the same to the purpose of erecting and maintaining a county jail thereon.
.“2d. That on or about the first day of March, 1880, said [242]*242Harvey county duly, entered into the contract as set forth in plaintiff’s petition with S. Chamberlain to erect upon said premises a county jail.
“3d. That afterward, and on or about the 26th day of April, 1880, said S. Chamberlain sub-let to this plaintiff, John Seaton, the contract to furnish all the iron work for said jail, as set forth in plaintiff’s petition.
“4th. That in pursuance of his contract with said Chamberlain said Seaton, furnished all of said iron work, with the understanding and intention that the same should be used in the construction of said jail, aud that the same was so used and was necessary to'the completion of said jail in pursuance of the contract of Chamberlain with said county, and was all so furnished and embodied into said jail building prior to the first day of March, 1881.
■ “ 5th. That there is due to the plaintiff on account of the materials so furnished 'and from the said Chamberlain the sum of $711.25.
“ 6th. That plaintiff filed his mechanics’-lien statement in due form of law, on the 5th day of April, 1881, and served a copy thereof upon the said board of county commissioners in due and proper form as required by law, on- the 16th day of April, 1881.
“ 7th. That the contract price of said building' largely exceeds the amount of all claims existing or urged against said premises under the mechanics’-lien laws of the said state of Kansas.
“ 8th. That said jail building was occupied as a place of safekeeping for persons in the charge of the sheriff of said county during the March tei’m of court, 1881, and in the month of March of said year.
“ 9th. That the main structure of said building was completed outside prior to April 5, 1881, except the portico and some final work on the roof, and inside the main building was completed except a portion of the cells, .plastering of basement and placing in position of the last iron bars, braces and fulcrum ; and in the excepted particulars the work was completed after the 5th day of April, 1881, and a small portion of the roofing as late as July 20th, 1881.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bankers Investment Co. v. Butts
276 P. 824 (Supreme Court of Kansas, 1929)
Wills v. Zanello
117 P. 291 (Oregon Supreme Court, 1911)
Sparks v. Smeltzer
93 P. 338 (Supreme Court of Kansas, 1908)
Roylance v. San Luis Hotel Co.
20 P. 573 (California Supreme Court, 1887)
Catlin v. Douglass
33 F. 569 (U.S. Circuit Court, 1887)
Perry v. Brainard
8 P. 882 (California Supreme Court, 1885)

Cite This Page — Counsel Stack

Bluebook (online)
32 Kan. 239, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seaton-v-chamberlain-kan-1884.