Zanello & Son v. Portland Central Heating Co.

139 P. 572, 70 Or. 69, 1914 Ore. LEXIS 219
CourtOregon Supreme Court
DecidedMarch 10, 1914
StatusPublished
Cited by6 cases

This text of 139 P. 572 (Zanello & Son v. Portland Central Heating Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zanello & Son v. Portland Central Heating Co., 139 P. 572, 70 Or. 69, 1914 Ore. LEXIS 219 (Or. 1914).

Opinion

Department 2.

Mr. Justice Ramsey

delivered the opinion of the court.

The plaintiffs brought this suit to foreclose a mechanic’s and materialman’s lien upon a building and a parcel of land 45 feet by 50 feet in dimensions, in Westover terraces, in the City of Portland, upon which said building is situated. This building and ground are [71]*71owned by the defendant, the Portland Central Heating Company.

At all times mentioned in the pleadings, P. A. Williams., the defendant, Grace B. Williams and E. Beckenridge were co-partners, doing business in the City of Portland under the firm name of the Pacific Heating-Engineering Company. The defendant P. A. Williams was business manager of said firm.

On July 23,1912, the defendant the Portland Central Heating Company, and the Pacific Heating-Engineering Company entered into a written contract, whereby the latter company undertook and promised to furnish all the material and all the labor for the construction and installation of a heating plant on the real premises above referred to, and, as a part of said plant, said company agreed to furnish all the material and labor and to construct for the company defendant a one-story power-house, according to certain plans and specifications, and, in the execution of said contract, and in all of the work of constructing said power-house, the Pacific Heating-Engineering Company was represented by the defendant P. A. Williams, as manager.

The Pacific Heating-Engineering Company, on August 15, 1912, entered into a contract with one Robert R. Sheay, whereby the latter undertook and promised to furnish all the material and labor, and to construct said power-house, for an agreed consideration. By said contract, said Sheay became a subcontractor for •the construction of the said power-house. On or about August 15, 1912, said Sheay entered into an oral contract with the plaintiffs, whereby the plaintiffs undertook and promised to furnish the material and perform the labor for the construction of, and to construct, the brick walls of said power-house, and the concrete footings thereof, for the sum of $1,700, and said Sheay agreed to pay the plaintiffs said sum for their work, [72]*72material and the construction of the brick walls and concrete footings of said building. The plaintiffs also entered into a further contract with said Sheay to do extra work on said building, for which the latter agreed to pay them the additional sum of $80. The total amount of the plaintiffs’ claims against said Sheay for material and labor by them furnished for said building was $1,780.

Before said building was completed, said Sheay is said to have absconded. Within 30 days after the completion of said building, the plaintiffs filed, and had recorded, upon said building and the real property referred to, a mechanic’s and materialman’s lien for said sum of $1,780; the whole thereof being unpaid. The claim of lien so filed and recorded is in due form, unless it is defective in that it fails to itemize the amount for which the lien is claimed.

The complaint is in proper form, and said Robert R. Sheay was made a party, but, being out of the state, he was not served with process. The defendants, the Portland Central Heating Company, and the said P. A. Williams filed a joint answer, denying much of the complaint, and setting up affirmative matter. A reply put in issue about all of the allegations of the answer. The court below held the plaintiffs’ lien to be invalid, and dismissed their complaint, and they appealed.

There are various objections made by the defendants to the said lien, and we will examine them separately.

1. Section 7420, L. O. L., provides that it is the duty of every person claiming a lien to file with the county clerk “a claim containing a true statement of his demand.” The notice filed by the plaintiffs in this case stated their demand thus:

“For labor performed and material furnished, as per contract, $1,780.”

[73]*73The defendants contend that this statement does not meet the requirements of the section above cited.

Among other things, the claim of lien contained the following statements, showing for what said lien was claimed:

“That the claimants were employed by the said Robert R. Sheay to perform labor and furnish the material necessary and required in building the brick walls and concrete footings for said building, for which labor and material he agreed to pay the claimants the sum of $1,780, and that the said claimants did, in pursuance of said employment, and under and by virtue of said contract with the said Robert R. Sheay, furnish the labor and material in erecting and constructing said brick walls and said concrete footings, and did build, erect, and construct the said brick walls and concrete footings for said building, and furnish- the labor and material therein, in all respects as required by their contract with the said Robert R. Sheay, and that they did duly perform all the terms and conditions of said agreement on their part to be kept and performed. That the contract and reasonable price of such labor and material so furnished, used, and employed in the said work, as aforesaid, was and is $1,780, lawful money of the United States. That said sum of $1,780 is now due and owing to the said claimants for said work, labor, and material so performed and furnished in the erection and construction of said building, and that no part thereof has been paid; said claim and account therefor being hereinafter specifically set forth and stated. That the following is a true and correct statement of the claim and demand due the claimants herein, after deducting all just credits and setoffs: ‘For labor performed and material furnished as per contract, $1,780.’ ”

The foregoing extracts from said claim of lien show that the amount for which the lien is claimed is $1,780; that said amount is due the plaintiffs for labor and material that they furnished under a contract with [74]*74Sheay; that said labor and material went into the brick walls of said building and the. concrete footings thereof; that said labor and material were furnished in all respects as required by the contract; that the plaintiffs duly performed all of the terms and conditions of the contract on their part; that the contract price and the reasonable value of said material and labor were $1,780, etc.

The statement of lien shows that the plaintiffs had the contract for the construction, not of the whole building, but of the brick walls and concrete footings thereof. The plaintiffs constructed all of the walls and concrete footings, but nothing else, and this is shown by the statement. Any competent man acquainted with such work could easily ascertain the amount of material that went into those walls and concrete footings, and the amount of labor that was required to do the work, and the reasonable cost of the material and labor. It was not necessary to set out in the claim the number of bricks, the number of pounds of cement and other material, and the number of days’ labor that went into the walls and the concrete footings of the building. It has been repeatedly held by this court that it is not necessary that the account be itemized, and that it is sufficient if it states in a general manner upon what it is based and the amount of the claim: Ainslie v. Kohn, 16 Or. 363 (19 Pac. 97); Curtis v. Sestanovich, 26 Or. 107 (37 Pac. 67);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cloyd v. McPherson
582 P.2d 423 (Oregon Supreme Court, 1978)
Culver v. RENDAHL ET UX
318 P.2d 275 (Oregon Supreme Court, 1957)
Paget v. Peters
289 P. 1119 (Oregon Supreme Court, 1930)
Niagara Fire Ins. Co. v. Waters
1928 OK 217 (Supreme Court of Oklahoma, 1928)
Myers v. Strowbridge Estate Co.
160 P. 135 (Oregon Supreme Court, 1916)
St. Johns Lumber Co. v. Pritz
146 P. 483 (Oregon Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
139 P. 572, 70 Or. 69, 1914 Ore. LEXIS 219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zanello-son-v-portland-central-heating-co-or-1914.