Cloyd v. McPherson

582 P.2d 423, 283 Or. 137, 1978 Ore. LEXIS 1014
CourtOregon Supreme Court
DecidedAugust 1, 1978
DocketTC 99118, SC 25566
StatusPublished
Cited by5 cases

This text of 582 P.2d 423 (Cloyd v. McPherson) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cloyd v. McPherson, 582 P.2d 423, 283 Or. 137, 1978 Ore. LEXIS 1014 (Or. 1978).

Opinion

*139 TONGUE, J.

This is a suit to foreclose a mechanic’s lien placed upon defendant’s property by plaintiff, a contractor who performed extensive alterations and repairs upon the property. Plaintiff alleged that he was entitled to payment of a balance due for work performed under a contract between the parties and also for work performed for "extras” in addition to the work required by that contract. Defendant alleged that all sums due under the contract had been paid or tendered and that the parties had agreed that all but approximately $200 of the "extras” would be offset by the fact that some of the work to be performed under the contract had been done in a "substandard” manner. The trial court denied foreclosure of the mechanic’s lien, awarded plaintiff $200, and also awarded $1,000 in attorney fees to defendant as the "prevailing party.” We affirm.

This being an appeal in a suit in equity, it is to be "tried anew upon the record.” ORS 19.125(3). Because there are conflicts in the testimony, however, we give considerable weight to the findings of the trial judge, who was in a better position to assess the credibility of the witnesses. Cf. Almond v. Anderegg, 276 Or 1041, 1043, 557 P2d 220 (1976); Adamson v. Adamson, 273 Or 382, 389, 541 P2d 460 (1975). We note that the trial court, in a letter opinion, stated:

"* * * Generally speaking, the defendant’s testimony was more convincing than that of the plaintiff, and most of [defendant’s] testimony was aptly [sic] corroborated by other witnesses and exhibit.”

Defendant owned an older residence in an area of the city of Salem subject to an urban renewal program under which defendant was able to obtain a low interest loan for the rehabilitation of the property. Under this program the city inspects the property and prepares a written list of the requirements for the rehabilitation of the property. The work is then put out for bids and the successful bidder and the owner enter into a written contract for the performance of that work.

*140 Plaintiff was the successful bidder for the rehabilitation of defendant’s property. The bid for the work to be performed was $17,500.50 and a written agreement describing that work was prepared and signed. On January 20, 1977, plaintiff filed a mechanic’s lien, attaching a copy of a letter he had written to defendant demanding payment for certain extra work allegedly requested by defendant. The amount of the mechanic’s lien included the contract price of $17,500.50, plus "extras” in the sum of $2,279.06, less payments made and credited. There is no dispute about defendant’s responsibility to pay the contract price.

Defendant testified that she had authorized payment to plaintiff of the balance due for work to be performed under the contract, but that plaintiff refused to accept such payment unless he was also paid for the "extras” for which he also claimed payment. Plaintiff offered evidence to prove the cost of the various items of "extra” work.

There is no contention by defendant that these "extras” were part of the original written agreement. Defendant’s contention, however, is that she agreed to pay only for certain minor "extras” totaling approximately $200 and that plaintiff agreed to absorb the costs of the other "extras” in consideration for defendant’s forgiveness of various deficiencies in plaintiff’s performance of work to be done under the contract. She testified as follows:

"Q Are you aware of a list of extra charges that Mr. Cloyd has presented?
"A I am.
"Q When were you first presented with the extra charges?
"A Mr. Cloyd finished his work at the home in about the second week of December. It was after Christmas that he came to my home and sat down with me in the front room and things looked pretty good. Then he opened up a paper and handed it to me and I sat down in shock because it was a list of items which he was making *141 claim for, among which were those I had said I would pay him for.
"Q Now may the witness be handed Plaintiff’s Exhibit 19? [Letter of December 31, 1976.]
"Now, when he presented you with this list of extras, did it include the same extras that are included on Plaintiff’s Exhibit #19 that you have there in your hand?
"A Yes, the only difference is that it merely listed the items. It didn’t contain all the extra verbiage and vitriolic sentences.
"Q When he presented you with this list of extras what was the crux of the conversation that took place?
"A Well, I said to Mr. Cloyd, 'George, it was my understanding that because I was accepting substandard—substitution of materials and lesser grade of work that you would allow me to have the extras which we talked about from the very beginning,’ and Mr. Cloyd said to me, 'Well, I haven’t made a bit of money on the job. I have to make something on this. I have done everything you wanted me to, now I have to make some money.’ And I said to him, 'George, from the very beginning and throughout our conversation, I told you the things that I would pay for because they were outside what I expected you to do and I will pay for those things but that’s all.’ I handed him the paper and he left.
"Q What were those things that you agreed to pay for?
"A The underlayment for the floor, because the carpet would not have maintained any quality without the underlayment and he felt it would and I felt it wouldn’t, because the carpet-layers told me it wouldn’t stand up under a guarantee. I said I would pay for the underlayment.
"The upstairs needed to be insulated because it was bare wall. All my heat would be lost through the ceiling. I said I would pay for the insulation cost for the upstairs and the drainline that was broken in the basement when it was removed. I said I would—because that was an unforeseen cost, I said I would assume the cost for that and the Lazy Susan that was installed at my request in the cabinets.
"Q As far as the drainline, you wanted to pay for the material costs?
*142 "A The material costs only.
"Q And did you offer to pay for those items at the time you met with Mr. Cloyd?
"A Yes.
"Q And did you have resources with which to pay those items at that time?
"A I did.
* * * * »

Plaintiff denied any such agreement.

As previously stated, the trial court found that defendant’s testimony was more convincing and resolved the dispute in her favor. After examining the entire record, we agree that defendant’s testimony was also corroborated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Citizens Valley Bank v. Douglas Robins, Inc.
687 P.2d 815 (Court of Appeals of Oregon, 1984)
King v. Suniga
634 P.2d 812 (Court of Appeals of Oregon, 1981)
Davison v. Parker
622 P.2d 1113 (Court of Appeals of Oregon, 1981)
Betz Construction, Inc. v. Peterson
614 P.2d 1184 (Court of Appeals of Oregon, 1980)
Matter of Guardianship of Willbanks
588 P.2d 118 (Court of Appeals of Oregon, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
582 P.2d 423, 283 Or. 137, 1978 Ore. LEXIS 1014, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cloyd-v-mcpherson-or-1978.