James A. C. Tait & Co. v. Stryker

243 P. 104, 117 Or. 338, 1926 Ore. LEXIS 154
CourtOregon Supreme Court
DecidedJanuary 20, 1926
StatusPublished
Cited by20 cases

This text of 243 P. 104 (James A. C. Tait & Co. v. Stryker) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James A. C. Tait & Co. v. Stryker, 243 P. 104, 117 Or. 338, 1926 Ore. LEXIS 154 (Or. 1926).

Opinion

RAND, J.

This appeal is from a decree foreclosing certain liens for labor and material furnished for the construction of an apartment house. The plaintiff James A. C. Tait & Company, a corporation, is one of said lien claimants, and furnished at the special instance and request of defendant George E. Mangas, who in his dealings with plaintiff was an original contractor, certain material for use in the construction of said apartment house. The defendant Jason C. Moore was at the time the labor and materials were furnished by plaintiff and the other lien claimants the owner of the premises and of the improvements then being placed thereon. Since that time, J. D. Stryker, another defendant, and the appellant herein, has acquired title to the property, and is now the owner thereof. Plaintiff had. judg *341 níent and decree in the court below against Mangas personally, and also had decree foreclosing his lien upon said property.

It is contended that the decree in favor of plaintiff is erroneous upon two grounds: (a) that plaintiff’s lien is not enforceable, because the notice thereof was not filed for record within thirty days from the day upon which the last delivery was made, and (b) that having obtained a personal judgment and decree in this suit against Mangas for the amount for which the lien is claimed, plaintiff is not entitled to have its lien enforced against the rights and interest of the present owner of the property, although plaintiff’s claim was, and still is, unpaid.

It appears from the testimony that the last delivery of material by plaintiff was made on April 27, 1923, and that the notice of lien was not filed until June 21, 1923, after a lapse of more than thirty days.

In Ainslie v. Kohn, 16 Or. 363 (19 Pac. 97), it was held that what are now Sections 10195 and 10200, Or. L., being parts of the same act, and relating to the same subject matter, are to be construed in pari materia, and that when so construed the statute directs that the original contractor must file his claim of lien within sixty days after the completion of his contract, and that all other persons are required to file their claims within thirty days from the completion of the building or improvement for which the lien is claimed. This construction of the statute has been upheld in Curtis v. Sestanovich, 26 Or. 107, 120 (37 Pac. 67), Fitch v. Howitt, 32 Or. 396, 404 (52 Pac. 192), Coffey v. Smith, 52 Or. 538, 541 (97 Pac. 1079), and Christman v. Salway, 103 Or. 666 (205 Pac. *342 541). It is contended that this well-settled rule was changed by the decision in Bernard v. Hassan, 60 Or. 62 (118 Pac. 201). What was there said must be considered in its relation to the particular facts of that case, and when so considered it will be found that there was no intention to change the rule. That case defines an original contract or within the meaning of the mechanic’s lien law, as one who furnishes labor or material upon a contract direct with the owner.

Plaintiff’s contract was not directly with the owner, but with Mangas, who had contracted with the owner to furnish all the labor and material necessary to construct a part of the building then being erected. As such, it was only required to file for record, its notice of lien within thirty days after the completion of the _ building. The building, however, has never been completed, and there has been an entire cessation of work thereon. The evidence discloses that the completion of the building has been permanently abandoned, and that no work has been done thereon since the latter part of May, 1923, but the evidence does disclose that work was done thereon, and that there was no intention to permanently abandon the construction of the building, upon the part of the owner, until less than thirty days before plaintiff’s notice of lien was filed, and it also discloses that other deliveries were to be made by plaintiff of material to be used in the construction of the building under its contract with Mangas, and that these deliveries were temporarily suspended at the request of the owner, who was then endeavoring to borrow money with which to complete the construction of the building, and that upon his inability to obtain money for that purpose, plaintiff *343 was notified to make no further delivery. Under such circumstances it seems to be the rule that since the building was not completed, plaintiff would have thirty days after the permanent abandonment of the work in which to file his notice of lien.

In Catlin v. Douglass, 33 Fed. 569, the statute then under consideration gave to lien claimants, four months from the completion of the building, in which to file their lien claims. A lien was claimed upon buildings which had not been completed, and upon which work had been permanently abandoned, and it was in effect held that the abandonment of the work constituted in legal effect a completion of the building for the purpose of filing mechanics’ liens. Such seems to be the rule followed in Pedretti v. Stichtenoth, 6 Ohio C. T. 517; McCarthy v. Groff, 48 Minn. 325 (51 N. W. 218); Shaw v. Stewart, 43 Kan. 572 (23 Pac. 616); Main Street Hotel Co. v. Horton Hardware Co., 56 Kan. 448 (43 Pac. 769).

There is no merit in plaintiff’s second contention. In dealing with plaintiff, Mangas was an original contractor; he had contracted with Moore to furnish the labor and material for the construction of a part of the building, and by the terms of the contract was to be paid certain stipulated sums or amounts as the work progressed. This obligated him to purchase and pay for such labor and material as he should use in the performance of his contract, and upon his employment of labor, or purchase of material, he became personally liable therefor. Neither by the terms of his contract with Moore, the owner of the property, nor by any relation arising therefrom did Mangas, become a common-law agent of Moore. Not being a common-law agent, he had no authority to bind Moore personally *344 for obligations incurred in the performance of his contract, bnt under the statute, he was authorized to incur obligations with third parties, which if not paid, could be made the basis of a lien against the building or improvement which he was constructing for Moore.

The transcript of testimony discloses that Man-g’as purchased certain material from plaintiff, for use in the construction of the building, for which he failed to pay; that plaintiff filed for record in the proper office a claim of lien in proper form, for the material thus furnished, and within the time provided by statute commenced this suit, making both Moore and Stryker parties defendant, and that in its complaint plaintiff prayed for judgment and decree against Mangas for the amount due, and for a decree foreclosing its lien upon said property, and the record shows that the relief thus prayed for was granted. Under the facts alleged, and the proof, plaintiff was entitled to the relief sought.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TRI-CITY BUILDING CENTER, INC. v. Wagner
548 P.2d 961 (Oregon Supreme Court, 1976)
Warner v. Fordham
424 P.2d 673 (Oregon Supreme Court, 1967)
Ward v. TOWN TAVERN
228 P.2d 216 (Oregon Supreme Court, 1951)
Drake Lumber Co. v. Lindquist
170 P.2d 712 (Oregon Supreme Court, 1946)
Bradfield v. Bollier
128 P.2d 942 (Oregon Supreme Court, 1942)
Bennett v. Bruchou
96 P.2d 762 (Oregon Supreme Court, 1939)
Barr v. Lynch
97 P.2d 185 (Oregon Supreme Court, 1939)
Groff v. Harris
18 Ohio Law. Abs. 101 (Ohio Court of Appeals, 1934)
Allison v. Schuler
36 P.2d 519 (New Mexico Supreme Court, 1934)
Drake v. Riley
9 P.2d 130 (Oregon Supreme Court, 1932)
Phillips v. Graves
9 P.2d 490 (Oregon Supreme Court, 1931)
Block v. Love
1 P.2d 588 (Oregon Supreme Court, 1931)
Heacock Sash & Door Co. v. Weatherford
294 P. 344 (Oregon Supreme Court, 1930)
Stark-Davis Co. v. Fellows
277 P. 110 (Oregon Supreme Court, 1929)
Eastern & Western Lumber Co. v. Williams
276 P. 257 (Oregon Supreme Court, 1929)
Bethlehem Construction Co. v. Christiana Construction Co.
144 A. 830 (Superior Court of Delaware, 1928)
Beach v. Cooper Et Ux.
266 P. 633 (Oregon Supreme Court, 1928)
Shea v. Peters
268 P. 989 (Oregon Supreme Court, 1928)
Nicolai-Neppach Co. v. Poore
251 P. 268 (Oregon Supreme Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
243 P. 104, 117 Or. 338, 1926 Ore. LEXIS 154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-a-c-tait-co-v-stryker-or-1926.