Drake v. Riley

9 P.2d 130, 139 Or. 172, 1932 Ore. LEXIS 140
CourtOregon Supreme Court
DecidedFebruary 24, 1932
StatusPublished
Cited by4 cases

This text of 9 P.2d 130 (Drake v. Riley) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Drake v. Riley, 9 P.2d 130, 139 Or. 172, 1932 Ore. LEXIS 140 (Or. 1932).

Opinion

KELLY, J.

Plaintiff claims a lien for material furnished in the construction of a building and a dam intended to be used for the purposes of a fish hatchery.

When the work upon this hatchery was abandoned, is one of the questions involved herein. Mr. John Francisco, a witness in behalf of the appealing defendants, testified that he was working for A. 0. Riley, one of the defendants, until about the 15th of December, and that he saw Earl Smith working there “sometime the first of December, first week of December, maybe the 4th or 5th somewhere.” Defendant Riley was unable to state when the work ceased.

R. P. Smith, a witness for plaintiff, testified that his brother Earl Smith and one Matt Worton were the last to perform work upon the structure; that Worton told witness to go to the hatchery for an over-supply of shingles; that on December 23,1930, witness went to the hatchery, had quite a long tall? with defendant Worton, the man in charge there; that witness hauled the shingles back; and witness’ brother, Earl Smith, quit work there on the 24th of December, 1930.

*174 This constitutes a summary of all the testimony upon the question of when the work was abandoned, and we hold that it establishes such abandonment within thirty days of the filing of plaintiff’s claim of Ken which was filed on the 12th day of January, 1931.

Plaintiff had thirty days after the permanent abandonment of the work in which to file his notice of Ken: James A. C. Tait & Co. v. Stryker, 117 Or. 338 (243 P. 104), and cases there cited.

A distinction is made by appealing defendants between the case cited and the case at bar, in that, in the case last cited, the owner requested a temporary suspension of deliveries by plaintiff of material to be used in the construction of the building. We hold that this distinction does not render the rule above stated inappKcable to the case at bar.

The statement of account in plaintiff’s claim of Ken refers to the material furnished by invoice numbers and does not describe the kind nor give the quantity of the materials furnished. Appealing defendants argue that this rendered invalid plaintiff’s notice of Ken. In this they cite and are supported, by the case of East Side Mill Co. v. Wilcox, 69 Or. 266 (138 P. 843). In that respect, however, the case last cited is not in harmony with other cases decided by this court: Christman v. Salway, et al., 103 Or. 666, 687 (205 P. 541); Kollock & Co. v. Leyde, 77 Or. 569 (143 P. 621, 151 P. 733); Oregon Lumber & Fuel Co. v. Hall, 76 Or. 138 (148 P. 61); Oregon Lumber & Fuel Co. v. Nolan, 75 Or. 69 (143 P. 935, 146 P. 474); St. Johns Lumber Co. v. Pritz, 75 Or. 286 (146 P. 483, 486).

Another question of fact involved herein is whether plaintiff complied with the provisions of the statute (§ 51-101, Oregon Code 1930, to the effect that a Ken claimant shall, not later than five days after *175 the first delivery of material oj* supplies for which a lien may be claimed, deliver or mail to the owner or reputed owner of the property upon or about which said material or supplies are to be used a notice in writing stating in substance and effect that such lien claimant has commenced to deliver material and supplies for use thereon with the name of the contractor or agent or other person ordering the same and that a lien may be claimed therefor.

The date of the first invoice of goods delivered by plaintiff is September 22,1930.

Witness R. F. Smith testified that he mailed such notice to Mr. Riley on September 25, 1930, and submitted a purported copy thereof which was received in evidence without objection. Both Mr. and Mrs. Smith testified that it was their custom to mail such notices. Mr. Riley testified that he did not receive any such notice.

In the light of this record we hold that the mailing of the notice was established.

It is suggested that, because Mr. Riley did not receive the notice just mentioned, he was under no obligation to comply with the provisions of section 51-104, Oregon Code 1930, by posting a notice in writing that he would not be responsible for the construction, alteration or repair for which a lien might be claimed. It will be noted that said section 51-104 does not refer to a notice received by mail; but, on the other hand, provides that, unless within three days after the owner shall have obtained knowledge of the construction, alteration or repair, such notice of disclaimer shall have been posted; said construction, alteration or repair shall be deemed to have been constructed at the instance of the owner and the owner’s interest shall be subject to such lien.

*176 . The--undisputed. testimony discloses that .Mr. Eiley and Mrs. Eiley. both had personal knowledge of the construction of the.dam and building in suit and of the delivery of.material by plaintiff therefor.- The testimony also discloses ■ that no notice of disclaimer was posted by said defendants or either of them. . .

It is urged that the provisions of the statute, requiring the posting of such notice of disclaimer, is unconstitutional for the reason that the owner,- having contracted to sell the premises, would have no right to enter the same to post such notice. In the case at bar, there is a reservation in the contract of sale of' the right to install a ram, which reservation carried an implied right of entry on the part of defendant, A. G. Eiley. There is also a provision in said contract of sale to the effect that the second parties (defendants Worton and Golden Trout Fisheries, Ltd.) contemplate and agree to construct necessary dams and buildings and improvements. This contract was executed by all of the defendants herein and constituted Worton and Golden Trout Fisheries, Ltd., the agents of defendants Eiley for the purpose of constructing the building and dam in suit: Nicolai Neppach Co. v. Poore, et al., 120 Or. 163 (251 P. 268); Myers v. Strowbridge Estate Co., 82 Or. 29 (160 P. 135); Oregon Lumber & Fuel Co. v. Nolan, 75 Or. 69 (143 P. 935, 146 P. 474.)

The testimony also discloses that defendant Eiley was working upon the premises while the work on the hatchery was in progress. The question of the effect of the inability of an owner to enter premises for the purposé of posting a notice of dissent or disclaimer is not in this case.

The question, which we are unable to determine from the testimony herein, is how much land should be *177 subjected to plaintiff’s lien. . The statutory provision is that: . ■ :

“The land upon which-any building or other improvement as aforesaid shall be constructed, together with a convenient space about the same, or so much as may be required for the convenient use and oceupar tion thereof (to be determined by the judgment of the circuit court at the time of the foreclosure of such lien), shall also be subject to the liens created by this act,’’ etc. Section 51-102, Oregon Code 1930.

.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S Angelo v. Home Depot
New Mexico Court of Appeals, 2009
Erne v. Goshen Veneer, Inc.
437 P.2d 479 (Oregon Supreme Court, 1968)
Bradfield v. Bollier
128 P.2d 942 (Oregon Supreme Court, 1942)
Barr v. Lynch
97 P.2d 185 (Oregon Supreme Court, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
9 P.2d 130, 139 Or. 172, 1932 Ore. LEXIS 140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/drake-v-riley-or-1932.