Bradfield v. Bollier

128 P.2d 942, 169 Or. 425, 1942 Ore. LEXIS 89
CourtOregon Supreme Court
DecidedJune 30, 1942
StatusPublished
Cited by4 cases

This text of 128 P.2d 942 (Bradfield v. Bollier) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bradfield v. Bollier, 128 P.2d 942, 169 Or. 425, 1942 Ore. LEXIS 89 (Or. 1942).

Opinion

KELLY, C. J.

On the 11th day of July 1938, the original plaintiff herein, Fred E. Roberts, and defendant, E. Beatrice Bollier, also known as Ethel B. Bollier, entered into a contract that was partly written and partly oral, the written portion of which is as follows:

“This Agreement, Made this 11th day of July, 1938, by and between
Fred E. Roberts, hereinafter referred to as ‘Builder’, and Ethel B. Bollier, hereinafter referred to as ‘Owner’. Witnesseth:
That for the consideration of the payments hereinafter provided, the Builder agrees to construct completely, as hereinafter provided, a house on Lots 7 and 8, in Hurst Addition, Salem, Oregon, according to the blue prints and plans and specifications hereunto annexed which by this reference are made a part of this agreement, and the Owner agrees to pay said Builder for so constructing said house the sum of Thirty-Nine Hundred Fifty ($3950.00) Dollars, payable as follows:
One Thousand ($1,000.00) Dollars in cash when the basement and subfloors of said house are constructed.
One Thousand ($1,000.00) Dollars in cash when the roof is completed.
One Thousand ($1,000.00) Dollars in cash when the house is all plastered. The remaining balance in cash upon the completion of the construction of said house.
The construction of said house shall be completed within a reasonable length of time by the Builder.
The grading and cleaning of said premises is to be done by the Builder, and all extras or changes in or to said plans and specifications made by the Builder at the request of the Owner shall be paid for by the Owner on demand according to their *428 agreement which shall he noted in writing and signed by the parties and attached to this contract, and if the amount of such payment be not specified in such agreement, then any such extra construction or changes shall be paid for by the Owner according to their reasonable value.
The Builder is to furnish all material entering into the construction of said house, except window shades, linoleums, and heating plant, and except also the expense of light fixtures over ($50.00) Dollars.
The Builder shall construct said house in a good workmanlike manner and shall keep the expense of all labor and materials incurred by him promptly paid so that no liens will be filed against said house, and the Builder agrees to indemnify the Owner against claims for any injuries sustained by his employees during the construction of said house.
Witness our hands in duplicate this 11th day of July, 1938.
Fred E. Roberts
Builder
Ethel B. B oilier
Owner.”

A blueprint was used in the preparation of the foregoing document; but, other than that, no plans or specifications were reduced to paper or annexed to the contract.

As to what the plans and specifications were supplementing the written contract, the testimony is conflicting.

It is agreed that the foregoing contract did not provide for finishing the upper rooms and that a subsequent agreement was made that Roberts should complete and finish the second story of the house. Roberts contends that this was to be finished in fir at a cost of $1,000. Bollier insists that it was to be done for *429 $1,000 if finished in fir, but if finished in gumwood the price would be $1,050. Gumwood was employed in finishing it.

On May 19, 1939, Eoberts filed his notice of lien. Defendant, Bollier, as one of her defenses, alleged and the trial court found that on the 13th day of March 1939, Eoberts abandoned said construction contract.

Plaintiff urges, as his first assignment of error, that the court erred in holding that Eoberts was entitled to a judgment of only $106.42, and in not holding that he was entitled to a judgment of $2,107.70.

And, as his second assignment of error, plaintiff asserts that the court erred in holding that Eoberts was not entitled to a lien.

In support of his first assignment, plaintiff argues that in addition to the amount of the original contract Eoberts is entitled to $1,117 on subsequent contracts, and extras claimed by him amounting to $1,404.70 less offsets in the sum of $114; that in computing the reasonable value of extras, it is proper to base the same on the actual cost of labor and material plus ten per cent; and that there are no damages to the house which should be offset against Eoberts’ claim.

In support of his second assignment, plaintiff states that the contractor is entitled to a lien if the work is substantially completed; that there was no abandonment by Eoberts on March 13, 1939, or at any other time prior to substantial completion of the contract; and that Eoberts is not estopped from asserting a lien because of the terms of the contract, or because of the filing of other liens.

At the conclusion of the testimony, the trial court and counsel had a colloquy wherein the court stated in *430 effect that while there is some evidence of inconsequential work done later by subcontractors, the trial court was of the opinion that on the 13th day of March 1939, or practically on the 11th, at least on the 13th day of March, Roberts abandoned the project.

Upon being asked by plaintiff’s counsel as to the basis for the statement of abandonment, the trial court said:

“It isn’t profitable for the Court to enter into an argument with counsel, and I try to avoid that. However, I will say to you that I am perfectly satisfied with the statement of Mr. Moore when he called at his [Roberts’] place on the 13th of March. He [Roberts] stated that he was through with it and all done, and I have had the court reporter look up his testimony. On cross-examination when that conversation was called to his [Roberts’] mind he had the privilege at that time to say to this court that he didn’t intend to abandon the project, and that all he intended to say to Mr. Moore was to have Miss Bollier come in the house. Now, he didn’t say that, but to-day he changes that testimony and excuses it on that ground. I am not impressed by that kind of testimony. When a witness has the opportunity to state the truth of the matter in the first instance and a week later comes back and elaborates on it and puts in another statement which if true would mitigate the effect of his former statement, the Court isn’t satisfied. I don’t think it happened just that way. I am not just going into thin air to base any judgment I enter in any case. As counsel stated, there was violation of the contract which specifically provided that no liens would be filed and the work completed in accordance with the contract, free of mechanics liens, and it was not so done. He abandoned the project and permitted other parties to file liens. That is violation of the contract, and that would shut him out of any liens.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Engineering Corp. v. Evans Products Co.
570 P.2d 655 (Oregon Supreme Court, 1977)
Trachsel v. Barney
503 P.2d 696 (Oregon Supreme Court, 1972)
Gillis v. Gillette
184 F.2d 872 (Ninth Circuit, 1950)
Gabriel v. Corkum
196 P.2d 437 (Oregon Supreme Court, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
128 P.2d 942, 169 Or. 425, 1942 Ore. LEXIS 89, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bradfield-v-bollier-or-1942.