Gillis v. Gillette

184 F.2d 872, 13 Alaska 55, 1950 U.S. App. LEXIS 3197
CourtCourt of Appeals for the Ninth Circuit
DecidedOctober 30, 1950
Docket12145
StatusPublished
Cited by2 cases

This text of 184 F.2d 872 (Gillis v. Gillette) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gillis v. Gillette, 184 F.2d 872, 13 Alaska 55, 1950 U.S. App. LEXIS 3197 (9th Cir. 1950).

Opinion

BONE, Circuit Judge.

This ease was before us on a previous appeal, 177 F.2d 7, and was remanded with directions to make and enter further findings indicating: (1) whether appellant Gillis willfully abandoned the work before completion or abandoned it in compliance with a request made by appellee, Mrs. Gillette, (2) whether certain materials furnished for the job were furnished in compliance with a modification of an original agreement between the parties or in compliance with a new and separate agreement, and (3) if the court finds that the materials above mentioned were furnished by Gillis under a separate agreement to supply such materials, then to further find whether or not the Gillis claim of lien for these materials was filed within the proper time after ceasing to furnish them.

The present appeal is from the final judgment entered after the court had reconsidered the pleadings and evidence and made new findings and conclusions, including therein the findings and conclusions specifically required by our order. 1 The findings and conclusions now before us appear to cover in sufficient detail the material fact issues involved in the case.

In respect to the contract or contracts between the parties, the court, in its Finding No. 3, found among other matters:

“That on August 8, 1946, plaintiff undertook to pour a full concrete basement on the land described in paragraph II hereof, to move defendants’ dwelling house from its then location on the south side of Front Street in Nome, Alaska, across the street to the land described in paragraph II hereof, and to .construct an addition to said dwelling house, as shown and directed by the defendants; that by the terms of the agreement, the dwelling house was to be moved in October, 1946. That the moving operations, the pouring of the full concrete basement at the new site of the dwelling house and the construction of the addition thereto were to cost the defendants the sum of Two Thousand Eight Hundred Seventy-two and 28/100 ($2872.28) Dollars. That on October 10, 1946, defendants paid to plaintiff the sum of One Thousand ($1,000.00) Dollars to apply upon the total cost. That plaintiff did not move the dwelling house during the month of October, 1946, and not until freezing weather had set in, approximately November 12, 1946; that plaintiff continued to work on said dwelling from time to time until December 15, 1946, at which time he abandoned the work, leaving it unfinished in the following particulars: * * * ” 2

In response to the requirement of our order remanding the cause for additional findings on three fact issues the court found (as noted in its Finding No. 3) (1) that appellant continued to work on appellees’ dwelling house “from time to time” until December 15, 1946, at which time he “abandoned” the work, leaving the said dwelling unfinished in the five certain particulars set out in Note 2 and that this abandonment “was willful and without cause”; (2) that during “the moving and building opera *874 tions” appellant (with the consent of appellees, and as a separate agreement from that in which appellees were to furnish all materials to be used in such operations) did supply at his own cost certain extra services and supplies of the reasonable value of $526.08 in the securing and purchase of which- appellant acted as the agent and for the benefit of appellees and (3) that all of said services and supplies were furnished between the 12th day of November, 1946, and the 15th day of December, 1946, and the last of said supplies was furnished sometime prior to the 15th day of December, 1946, and more than ninety days prior to the filing of the purported lien herein, 3

In covering other pertinent matters the court also made further findings: (1) that in the latter part of January, 1947, appellant informed appellees that he was going to do nothing further upon appellees’ dwelling house or the concrete basement thereof, and then “quit and withdrew from the premises”; (2) that thereafter appellees completed the concrete basement at a reasonable cost of $327.50; (3) that appellant left the dwelling house “unbraced” so that it sagged five inches in the center in consequence of which the doors on the main floor would not open, all of which required appellees to have the building raised and five bracing posts put under it which work cost $190.00; (4) that appellees had thawed and excavated a sump in the basement of said dwelling at a cost of $39.75 which sump the appellant wantonly and negligently filled in and made it a total loss to appellees; (5) that plaintiff failed, neglected and refused to complete the addition to said dwelling house to be used as a dining room and defendants were compelled to complete the same at a cost of $260.00; (6) that appellant, in moving appellees’ dwelling house, cut off one corner of the same and neglected and refused to repair this damage and the reasonable cost of repair will be $100.00.

The total amount of the last five items of costs claimed as damages by appellees and noted in the preceding paragraph is $917.25. They are the items referred to in Note 2, and it is evident from the record and the findings that the court was fully persuaded, and we think correctly so, that by an expenditure of $917.25 the appellees were able to complete the work on their dwelling house which was required to be done under their contract with appellant, a contract which he wilfully abandoned without cause before completion of the work agreed upon.

Other specific findings which dispose of certain contentions in the case are that appellant did not remove a certain pressure pump from appellees’ dwelling house or property; that appellant was not shown to be responsible for having left the basement open, or for any damage by frost to the basement floor and the plumbing, or responsible for negligently pouring the concrete basement walls without proper foundation, or for appellees’ room rent during the moving operations. Appellees claimed (and the court rejected the claim) that the matters and things referred to in this paragraph represented compensable injuries suffered by them by reason of appellant’s acts. The total loss so claimed by appellees amounted to $1169.89. We think that the court properly rejected these claims of appellees.

Upon the facts so found the court entered Conclusions of Law reciting generally therein that appellant is not entitled to a judgment of foreclosure of his lien for labor furnished and material supplied, and that his purported lien should be discharged and cancelled of record; that appellant is entitled to judgment for $526.08 which sum represents the value of the materials furnished and paid for by him, these being supplied at the request of the appellees; that appellees are entitled to judgment in the sum of $917.25 which amount represents the damages (noted above) claimed to have been suffered by them by reason of the wrongful failure of appellant to complete the moving of appellees’ dwelling- house within the month of October, 1946, and by reason of appellant’s willful abandonment, without cause, of the work of moving, re *875 pair and building operations on the said dwelling house.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
184 F.2d 872, 13 Alaska 55, 1950 U.S. App. LEXIS 3197, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gillis-v-gillette-ca9-1950.