Eastern & Western Lumber Co. v. Williams

276 P. 257, 129 Or. 1, 1929 Ore. LEXIS 101
CourtOregon Supreme Court
DecidedFebruary 6, 1929
StatusPublished
Cited by17 cases

This text of 276 P. 257 (Eastern & Western Lumber Co. v. Williams) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern & Western Lumber Co. v. Williams, 276 P. 257, 129 Or. 1, 1929 Ore. LEXIS 101 (Or. 1929).

Opinion

ROSSMAN, J.

May 26, 1926, a corporation entitled Robnett & McClure and William and Ida Freeman, husband and wife, entered into a contract whereby the former undertook the construction of a house for the latter; the contract price was ap *3 proximately $6,500. June 10th construction work commenced. At the above times tbe Freemans were not tbe owners of tbe lot but were vendees under a contract dated August 26, 1925, wherein the Ladd Estate Company, as vendor, agreed to convey title upon the full payment of the purchase price, $1,250. A deed delivered and recorded July 19, 1926, conveyed title to the Freemans. The appellee, Williams, is interested in this property by virtue of a mortgage executed to secure payment of the sum of $4,500; this mortgage is dated June 29, 1926, and was recorded July 19, 1926. The respondent Eastern & Western Lumber Company, claims a lien upon this property; it alleges that it supplied lumber at the request of the contractor, and filed the proper lien notice required by Section 10195, Or. L. The respondent McCracken-Kipley Co. supplied cement, bricks and tile. The respondent Charles A. Shea, is the administrator of the estate of J. F. Shea, who performed the plumbing work and supplied the necessary fixtures. Both of these two claimants dealt with the contractor and by appropriate allegations averred that they were possessed of liens by virtue of Section 10195, Or. L. All three claimants prayed for the establishment and foreclosure of their alleged liens. The decree of the Circuit Court was in favor of the three claimants, and awarded to their liens priority over the mortgage of Williams; thereupon the latter appealed. The controversy before us is between these four parties only. Appellant Williams contends that the three liens are invalid; according to his contentions (1) the lien claimants did not file their lien notices within thirty days of the completion of the building, (2) a fatal variance exists *4 between the allegations of respondent Shea’s cross-complaint concerning his lien and the proof in support thereof, (3) the liens, if valid, can be enforced only against the building and whatever interest the Freemans had in the land when they contracted for the construction of the building.

We shall undertake to dispose of appellant’s contentions in the above order. He contends the house was completed November 26, 1926, and that since the lien notice of the Eastern & Western Lumber Company was not filed until January 25, 1927, the Shea lien notice not until April 2d, and the Mc-Cracken-Ripley notice not until April 19, 1927, the three liens are invalid. Since the claimants were subcontractors and materialmen it was their duty to file their lien notices within thirty days after the completion of the building; two late expressions to this effect are James A. C. Tail & Co. v. Stryker, 117 Or. 338 (243 Pac. 104); Nicolai-Neppach Co. v. Poore, 120 Or. 163 (251 Pac. 268).

The mortgagee does not contend that the general contractors had completely performed their undertaking November 26th, but argues (1) that the building was substantially completed on that day, and (2) the undertaking was permanently abandoned on or about November 26th, and relying upon the decisions in James A. C. Tait & Co. v. Stryker, supra; Shaw v. Stewart, 43 Kan. 572 (23 Pac. 616); Chicago Lbr. Go. v. Merrimack River Savings Bank, 52 Kan. 410 (34 Pac. 1045); 40 C. J. 192, contends that permanent abandonment in legal effect is the equivalent to the completion of the building, in its application to the fixing of the day for the filing of a lien notice. The appellant selects the date of November 26th *5 because that is the day when the Freemans moved their furniture into the house and began living there. For the week or two following November 26th, the painter was still engaged in and about the house; the evidence seems to warrant the conclusion that he left about December 15th and never returned. There is no reliable evidence that any carpentry or other work was done subsequent to that day. Although the contract required Eobnett and McClure to paint the roof, cover the exterior of the house with two coats of paint, and place bricks around the door and window openings, none of this work was done except the house was given one coat of paint. The brick work would have, required approximately 100 bricks of a select grade, and to put them in place would have required the services of a mason and his helper for one and one-half day’s time. We believe that we are fully justified in concluding that when the Freemans moved into the house November 26th, they had no intention of foregoing the above omitted items; the fact is conceded that they endeavored several times to persuade Eobnett and McClure to complete these items; the latter in turn tried to induce the paint and mason subcontractors to finish their work. Eobnett and McClure almost succeeded, so far as the latter was concerned, because March 3, 1927, he returned to the building and brought the necessary quantity of bricks and cement, with the intention of completing his subcontract the following day. Both he and the painting subcontractor had „ experienced difficulty in obtaining payment from Eobnett & McClure; as a result these two subcontracts were never completed.

*6 The precise time when the Freemans finally concluded that Robnett & McClure would not complete their contract is left in doubt. Appellant avers that November 26th that conclusion was reached, but it is evident they are mistaken because for some time after that date the Freemans were still engaged in their efforts to persuade the contractors to complete their contract. It is equally clear from the incident adverted to a moment ago that March 3d the contractors still definitely intended to finish their task. July 1st, at the latest, the undertaking was abandoned; for upon that day Robnett & McClure were adjudged bankrupts.

The following provision of the contract is significant :

“It is hereby mutually agreed that should the said contractor neglect or refuse to continue the work hereunder the owner shall have the right and privilege of giving five days’ written notice to the contractor at its last known place of residence to assume charge of said construction and to complete the work and charge the costs thereof against the contractor arising out of said neglect and default.”

The Freemans never gave any such a notice. January 20, 1927, Mr. Freeman signed the following statement addressed to the Eastern & Western Lumber Co.: “This is to certify that Robnett and McClure have not completed my house at 1077 Grlenwood Avenue this city”; another to similar effect was addressed to J. F. Shea and bore Freeman’s signature.

These circumstances persuade us that we would not be justified in concluding that the house was substantially completed November 26th. It is well settled in this jurisdiction that a contractor cannot extend the time for filing a lien by returning after the house *7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Timothy And Rosemary Ingram, V Northwest Septic O & M
Court of Appeals of Washington, 2014
Langford Tool & Drill Co. v. Phenix Biocomposites, LLC
668 N.W.2d 438 (Court of Appeals of Minnesota, 2003)
Emmert Industrial Corp. v. Sanders
883 P.2d 1304 (Court of Appeals of Oregon, 1994)
TRI-CITY BUILDING CENTER, INC. v. Wagner
548 P.2d 961 (Oregon Supreme Court, 1976)
Hayward Lumber & Investment Company v. Graham
449 P.2d 31 (Arizona Supreme Court, 1968)
Tabet Lumber Company v. Baughman
439 P.2d 706 (New Mexico Supreme Court, 1968)
Mercer Steel Co. v. Park Construction Co.
411 P.2d 262 (Oregon Supreme Court, 1966)
Bennett v. Bruchou
96 P.2d 762 (Oregon Supreme Court, 1939)
Spaeth v. Becktell
41 P.2d 1064 (Oregon Supreme Court, 1935)
Albuquerque Lumber Co. v. Montevista Co.
38 P.2d 77 (New Mexico Supreme Court, 1934)
Allison v. Schuler
36 P.2d 519 (New Mexico Supreme Court, 1934)
Hot Springs Plumbing & Heating Co. v. Wallace
27 P.2d 984 (New Mexico Supreme Court, 1933)
Shea v. Graves
19 P.2d 406 (Oregon Supreme Court, 1933)
Block v. Love
1 P.2d 588 (Oregon Supreme Court, 1931)
Paget v. Peters
289 P. 1119 (Oregon Supreme Court, 1930)
Stark-Davis Co. v. Fellows
277 P. 110 (Oregon Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
276 P. 257, 129 Or. 1, 1929 Ore. LEXIS 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-western-lumber-co-v-williams-or-1929.