Timothy And Rosemary Ingram, V Northwest Septic O & M

CourtCourt of Appeals of Washington
DecidedDecember 30, 2014
Docket44971-4
StatusUnpublished

This text of Timothy And Rosemary Ingram, V Northwest Septic O & M (Timothy And Rosemary Ingram, V Northwest Septic O & M) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Timothy And Rosemary Ingram, V Northwest Septic O & M, (Wash. Ct. App. 2014).

Opinion

FILED COURT OF APPEALS DIVISION II

2C I[ DEC 30 AM 9 7

STATE OF WASHINGTON

BY EPI TY

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II

TIMOTHY INGRAM and ROSEMARY No. 44971 -4 -II INGRAM, husband and wife, .

Appellants,

v.

AMERICAN CONTRACTOR INDEMNITY UNPUBLISHED OPINION COMPANY, a California corporation,

Respondent,

NORTHWEST SEPTIC 0 & M, INC., a Washington corporation, MARK WHISNANT CONSTRUCTION INC., a Washington corporation, and CALVIN L. ROWAN, an unmarried individual, d /b /a CAL' S CUSTOM CONSTRUCTION, AMERICAN STATES INSURANCE COMPANY, an Indiana corporation, CONTRACTORS BONDING AND INSURANCE COMPANY, a Washington corporation,

Defendants.

BJORGEN, J. — Timothy and Rosemary Ingram seek discretionary review of a trial court

order granting summary judgment in favor of the American Contractor Indemnity Company No. 44971 -4 -II

ACIC) and dismissing it from a suit arising out of construction on the Ingrams' property. The

trial court concluded that the Ingrams' suit was untimely based on the two -year statute of

limitations for suits against a contractor' s surety bond found in RCW 18. 27. 040( 3). 1 The Ingrams

argue that the trial court erred in granting summary judgment because material issues of fact

remain as to whether and when the statute of limitations commenced.

We hold that under the undisputed facts, construction was not substantially complete and

the contractor had not abandoned the project. For those reasons, the trial court erred in holding

that the Ingrams' suit was untimely under the statute of limitations. Therefore, we reverse the

order of summary judgment in favor of ACIC.

FACTS

In August 2008, the .Ingrams' septic system failed. The contractor the Ingrams hired to

replace the system informed them that the project would require the removal of the Ingrams' deck,

which the contractor promised to rebuild after replacing the septic system. The contractor also

assured the Ingrams that no permits would be required for replacing the septic system and deck.

After the replacement of the septic system, the Ingrams turned to a second contractor to

rebuild the deck and enclose it with a roof, transforming it into a sun -room. This second contractor

did not obtain any building permits for this work. The Ingrams terminated the services of this

1 RCW 18. 27. 040( 3) provides, in pertinent part: Action upon the bond or deposit brought by a residential homeowner for breach of contract by a party to the construction contract shall be commenced by filing the summons and complaint with the clerk of the appropriate superior court within two years from the date the claimed contract work was substantially completed or abandoned, whichever occurredfirst. Emphasis added.)

2 No. 44971 -4 -II

contractor because he repeatedly showed up for work intoxicated, and, as a result, his workmanship

on the deck and sun -room was poor.

In June 2009, the Ingrams hired Cal' s Construction to finish the partially completed deck

and sun -room and remedy the second contractor' s deficient performance. At the time of this

construction contract, and during its performance, ACIC bonded Cal' s with a " Contractor' s

Registration Act" surety bond, chapter 18. 27 RCW. Like the earlier contractors, Cal' s never

obtained any permits for the work. Cal' s finished performing labor and issued final invoices to

the Ingrams on June 17, 2009, stating that all work was complete. Believing the project finished,

the Ingrams paid Cal' s in full for all work performed. Cal' s never performed any further work at

the Ingrams' property after payment of this invoice.

In late 2011, the Kitsap County Department of Community Development issued the

Ingrams a notice demanding that they comply with Kitsap County building codes by obtaining the

necessary building permits, inspections, and approval to use the deck and sun -room. An

independent inspection of the deck and sun -room resulting from this notice revealed numerous

structural defects and code violations.

In October 2012, the Ingrams sued several defendants, including Cal' s and ACIC. The

Ingrams alleged that Cal' s had breached the construction contract between the parties by

performing defective work and that ACIC was Cal' s surety.

ACIC moved for dismissal under CR 12( c), alleging that the Ingrams failed to file their

claims against it within the two year statute of limitations for actions against a contractor' s bond

codified in RCW 18. 27. 040( 3). Under that provision, the statute of limitations for claims against

3 No. 44971 -4 -II

a surety bond commences at the earlier of a construction project' s substantial completion or

abandonment. RCW 18. 27. 040( 3). The Ingrams defended against this dismissal by arguing that

material issues of fact remained about whether the statute of limitations had commenced. The

Ingrams contended that the final invoice, code violations, and lack of approval to use or occupy

the deck and sun -room meant that the construction work was never substantially completed and

that the final invoice showed that no abandonment had occurred. Because the parties referenced

matters outside the pleadings, the trial court considered ACIC' s motion as one for summary

judgment under CR 56( c). The trial court granted ACIC' s motion, dismissing it from the suit with

prejudice and granting it reasonable attorney fees and costs as the prevailing party under RCW

18. 27. 040( 6).

The Ingrams appealed the trial court' s order granting summary judgment to ACIC.

Because the trial court had not entered final judgment on all of the Ingrams' claims under CR

54( b), our commissioner considered the Ingrams' notice of appeal as a motion for discretionary

review and granted the motion.

ANALYSIS

RCW 18. 27. 040( 3) states that an action against a contractor' s surety bond must commence

within two years of the earlier of either the date of "substantial complet[ ion]" or " abandonment"

of a construction contract. The Ingrams claim that the trial court improperly granted summary

judgment in favor of ACIC because Cal' s never substantially completed or abandoned the

construction contract for their deck and sun -room. We agree.

4 No. 44971 -4 -II

I. STANDARD OF REVIEW

We review de novo an order of summary judgment, performing the same inquiry as the

trial court. Am. States Ins. Co. v. Symes of Silverdale, Inc., 150 Wn.2d 462, 467, 78 P. 3d 1266

2003) ( citing Jones v. Allstate Ins. Co., 146 Wn. 2d 291, 300, 45 P. 3d 1068 ( 2002)). We consider

the facts and the inferences from those facts in the light most favorable to the Ingrams, the

nonmoving party here. Jones, 146 Wn.2d at 300 ( citing Bremerton Pub. Safety Ass 'n v. City of

Bremerton, 104 Wn. App. 226, 230, 15 P. 3d 688 ( 2001)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nolan v. Paramount Homes, Inc.
518 S.E.2d 789 (Court of Appeals of North Carolina, 1999)
Langford Tool & Drill Co. v. Phenix Biocomposites, LLC
668 N.W.2d 438 (Court of Appeals of Minnesota, 2003)
American States Ins. Co. v. Symes of Silverdale, Inc.
78 P.3d 1266 (Washington Supreme Court, 2003)
COSMOPOLITAN ENG. GROUP v. Ondeo Degremont, Inc.
149 P.3d 666 (Washington Supreme Court, 2006)
In Re Parentage of LB
122 P.3d 161 (Washington Supreme Court, 2005)
LAKEVIEW v. Apartment Sales Corp.
6 P.3d 74 (Court of Appeals of Washington, 2000)
State, Dept. of Ecology v. Campbell & Gwinn
43 P.3d 4 (Washington Supreme Court, 2002)
Cockle v. Dept. of Labor and Industries
16 P.3d 583 (Washington Supreme Court, 2001)
1519-1525 Lakeview Blvd. Condo. v. Asc
29 P.3d 1249 (Washington Supreme Court, 2001)
Jones v. Allstate Ins. Co.
45 P.3d 1068 (Washington Supreme Court, 2002)
Eastern & Western Lumber Co. v. Williams
276 P. 257 (Oregon Supreme Court, 1929)
Lybbert v. Grant County
1 P.3d 1124 (Washington Supreme Court, 2000)
Cockle v. Department of Labor & Industries
142 Wash. 2d 801 (Washington Supreme Court, 2001)
1519-1525 Lakeview Boulevard Condominium Ass'n v. Apartment Sales Corp.
144 Wash. 2d 570 (Washington Supreme Court, 2001)
Department of Ecology v. Campbell & Gwinn, L.L.C.
146 Wash. 2d 1 (Washington Supreme Court, 2002)
Jones v. Allstate Insurance
45 P.3d 1068 (Washington Supreme Court, 2002)
American States Insurance v. Symes of Silverdale, Inc.
150 Wash. 2d 462 (Washington Supreme Court, 2003)
Carvin v. Britain
155 Wash. 2d 679 (Washington Supreme Court, 2005)
Cosmopolitan Engineering Group, Inc. v. Ondeo Degremont, Inc.
159 Wash. 2d 292 (Washington Supreme Court, 2006)
State v. Garcia
318 P.3d 266 (Washington Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Timothy And Rosemary Ingram, V Northwest Septic O & M, Counsel Stack Legal Research, https://law.counselstack.com/opinion/timothy-and-rosemary-ingram-v-northwest-septic-o-m-washctapp-2014.