KETCHUM, KONKEL v. Heritage Mt.

784 P.2d 1217
CourtCourt of Appeals of Utah
DecidedDecember 1, 1989
Docket890284-CA
StatusPublished
Cited by1 cases

This text of 784 P.2d 1217 (KETCHUM, KONKEL v. Heritage Mt.) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KETCHUM, KONKEL v. Heritage Mt., 784 P.2d 1217 (Utah Ct. App. 1989).

Opinion

784 P.2d 1217 (1989)

KETCHUM, KONKEL, BARRETT, NICKEL & AUSTIN, d/b/a KKBNA Incorporated, a Utah corporation; Kent W. Walker and Michael V. Lee, a Utah partnership, d/b/a The Architectural Partnership; Sheldon L. Pollack Corporation, a California corporation; and Norbert W. Pieper, A.I.A., Inc., a California corporation, Plaintiffs and Appellants,
v.
HERITAGE MOUNTAIN DEVELOPMENT COMPANY, a Utah corporation, et al., Defendants and Respondents.

No. 890284-CA.

Court of Appeals of Utah.

December 1, 1989.

*1219 David M. Wahlquist (argued), James J. Cassity, Merrill F. Nelson, Kirton, McConkie & Bushnell, Salt Lake City, Attorneys at Law for Pollack & Pieper.

Richard C. Cahoon, Marsden, Orton & Cahoon, Salt Lake City, for Nordic Constructors.

David R. Olsen (argued), Carl F. Huefner, Michael W. Homer, Suitter, Axland, Armstrong & Hanson, Salt Lake City, for respondent, Guar. S & L.

Richard L. Hill, Jeffrey R. Hill, Olsen, Hintze, Nielson & Hill, Provo, for respondent, Heritage Mtn.

Before BENCH, BILLINGS and GREENWOOD, JJ.

BILLINGS, Judge:

Appellants Sheldon L. Pollack Corp., Norbert W. Pieper, A.I.A., Inc. ("appellants"), among other lien holders, filed actions to foreclose their mechanics' liens recorded against property being developed as a ski resort in Utah County. The construction lender, Guaranty Savings and Loan Association ("Guaranty"), moved for partial summary judgment claiming its trust deed had priority over all mechanics' liens on the property. The lien holders opposed the motion and filed cross-motions for partial summary judgment on the priority issue. The trial court ruled in favor of Guaranty, and certified its order as final under Utah Rules of Civil Procedure 54(b). Appellants appeal the trial court's order on priority.

We set forth the relevant, undisputed facts before the trial court when it granted summary judgment in this mechanics' liens priority dispute. In October 1972, Wilderness Associates, the predecessor in interest of Heritage Mountain Development Co. ("Heritage"), began the planning and development of a ski resort. The master plan for the ski resort contemplated the common development of three contiguous parcels of property in Utah County: 110 acres owned in fee simple ("Fee Property"); 41 acres leased from the State of Utah ("Leased Property"); and 4500 acres of federal land under a special use permit ("Permit Property").

Between September 1978 and the summer of 1982, Heritage remodeled a barn for a headquarters, and installed sewer and water lines, built parking lots, and made other improvements on the Leased Property. During the same period of time, Heritage cut construction access roads, flagged ski trails and excavated, and performed soil tests on all three parcels. From early 1981 to the summer of 1982, appellants performed architectural, engineering, surveying, consulting, and planning services for the entire ski development.

On November 17, 1982, a mortgage lender obtained a Judgment and Decree of Foreclosure on the Fee Property. Heritage repurchased the Fee Property on June 29, 1983.

Beginning in April of 1983, an engineering firm surveyed and staked the boundaries of the property. In June 1983, Heritage obtained a predevelopment loan from Guaranty. To secure the loan, Heritage executed a trust deed on the property. Guaranty recorded the trust deed on September 15, 1983. At the time of this loan, Guaranty knew that appellants had performed extensive design work on the project. Between June and September of 1983, appellants and others resumed design work on the project.

The long-term financing for the ski development fell through and no additional on-site construction took place. Heritage abandoned the project by the summer of 1984 and left appellants and other contractors unpaid. The lien holders, including appellants, sued to foreclose their mechanics' liens and Guaranty opposed the suits by asserting its trust deed had priority over all mechanics' liens.

The district court held that "commencement of work," for the purpose of establishing priority under Utah Code Ann. § 38-1-5 (1988), requires "visible, on-site" improvements, and thus appellants' mechanics' liens did not attach prior to the *1220 recording of Guaranty's trust deed. In addition, the court held the November 1982 foreclosure judgment on the Fee Property barred relation back of appellants' liens to on-site work performed on the property prior to the date of the foreclosure. The court also concluded that no on-site work occurred between the November 1982 foreclosure and the recording of Guaranty's trust deed on September 15, 1983, to which the liens could relate back. Appellants challenge each of the trial court's conclusions claiming the court should have held their mechanics' liens had priority over Guaranty's trust deed.

I. EFFECT OF OFF-SITE ARCHITECTURAL WORK ON MECHANICS' LIENS PRIORITY

Appellants claim that, under Utah Code Ann. §§ 38-1-5 and -10 (1988), their post-foreclosure, pre-trust deed, off-site design work on the project gives their mechanics' liens priority over Guaranty's trust deed. We disagree.

Under Utah law, architects' services are lienable. Utah Code Ann. § 38-1-3 (1981) expressly provides for liens for architectural services:

[L]icensed architects and engineers and artisans who have furnished designs, plats, plans, maps, specifications, drawings, estimates of cost, surveys or superintendence, or who have rendered other like professional service, or bestowed labor, shall have a lien upon the property upon or concerning which they have rendered service, performed labor, or furnished or rented materials... .

Guaranty does not challenge the validity of the appellants' liens, but claims its trust deed has priority over all valid mechanics' liens under the statutory scheme. Priority of mechanics' liens, including architectural liens, is governed by Utah Code Ann. § 38-1-5 (1988), which provides:

The liens herein provided for shall relate back to, and take effect as of, the time of the commencement to do work or furnish materials on the ground for the structure or improvement, and shall have priority over any lien, mortgage or other encumbrance which may have attached subsequently to the time when the building, improvement or structure was commenced, work begun, or first material furnished on the ground... .

Lien statutes are construed broadly in order to achieve their protective purpose. AAA Fencing Co. v. Raintree Dev. & Energy Co., 714 P.2d 289, 291 (Utah 1986); Interiors Contracting, Inc. v. Navalco, 648 P.2d 1382, 1386 (Utah 1982). Further, the phrase "commencement to do work" is construed in favor of the lien claimant. Calder Bros. Co. v. Anderson, 652 P.2d 922, 924 (Utah 1982) (citing Bankers Trust Co. v. El Paso Pre-Cast Co., 192 Colo.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mutual Savings Ass'n v. Res/Com Properties, L.L.C.
79 P.3d 184 (Court of Appeals of Kansas, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
784 P.2d 1217, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ketchum-konkel-v-heritage-mt-utahctapp-1989.